Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Protection and Mechanical Methods · Standpipe · Structural · Supported Scaffold
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
4 documents
INSTALLATION OF TEMPORARY ROOF PROTECTION AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
2 documents
Installation of HVAC and refrigeration equipment as per plans filed.
On file for this project
8 documents · 1 drawing sheet
PenthouseUnder Construction1p · 2 filings · 10 docs
Architecture
Issued Permit Scope
General Construction
INTERIOR RENOVATION OF AN EXISTING APARTMENT ON THE 11TH FLOOR, MINOR PARTITION CHANGES AS PER PLANS. NO CHANGE OF USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
On file for this project
2 documents · 1 drawing sheet
RENOVATION OF PENTHOUSE BE DRESSING ROOM, WALK IN CLOSET, AND PRIMARY BEDROOM. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
8 documents
Floor 151 filing · 4 docs
EquipmentGeneralPlumbingStructural
Issued Permit Scope
Supported Scaffold
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
4 documents
Floor 141 filing · 4 docs
EquipmentGeneralPlumbingStructural
Issued Permit Scope
Supported Scaffold
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
4 documents
Floor 131 filing · 4 docs
EquipmentGeneralPlumbingStructural
Issued Permit Scope
Supported Scaffold
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
4 documents
Floor 121 filing · 4 docs
EquipmentGeneralPlumbingStructural
Issued Permit Scope
Supported Scaffold
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
4 documents
Floor 11Under Construction1 filing
ArchitectureElectricalEquipmentFire ProtectionGeneralMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Protection and Mechanical Methods · Standpipe · Structural · Supported Scaffold
INTERIOR RENOVATION OF AN EXISTING APARTMENT ON THE 11TH FLOOR, MINOR PARTITION CHANGES AS PER PLANS. NO CHANGE OF USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
On file for this project
2 documents
Floor 101p · 1 filing
ArchitectureElectricalEquipmentFire ProtectionGeneralMechanicalPlumbingStructural
Issued Permit Scope
Mechanical Systems · Plumbing · Protection and Mechanical Methods · Standpipe · Structural · Supported Scaffold
RENOVATION OF PENTHOUSE BE DRESSING ROOM, WALK IN CLOSET, AND PRIMARY BEDROOM. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
8 documents · 1 drawing sheet
Floor 9
Floor 8
Floor 7
Floor 6
Floor 52 filings
ArchitectureElectricalEquipmentFire ProtectionGeneralMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Protection and Mechanical Methods · Standpipe · Structural · Supported Scaffold
Renovation of an existing apartment#5B on the 5th Floor. work includes non-structural demolition and general construction . No change to use, egress or occupancy
On file for this project
7 documents
INSTALL MEDIUM DUTY SCAFFOLDING AS PER PLANS. PIPE SCAFFOLDING SHALL COMPLY WITH CHAPTER 33 OF THE NYC BUILDING CODE. SIDEWALK SHED FILED UNDER SEPARATE APPLICATION
On file for this project
3 documents
Floor 41p · 3 filings
ArchitectureDMElectricalEquipmentFire ProtectionGeneralMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Protection and Mechanical Methods · Standpipe · Structural · Supported Scaffold
UTILIZE EXISTING ELEVATOR SHAFT AS A DEBRIS CHUTE IN CONJUNCTION WITH FULL DEMO JOB 123906666
On file for this project
3 documents
INSTALL MEDIUM DUTY SCAFFOLDING AS PER PLANS. PIPE SCAFFOLDING SHALL COMPLY WITH CHAPTER 33 OF THE NYC BUILDING CODE. SIDEWALK SHED FILED UNDER SEPARATE APPLICATION
On file for this project
3 documents
INTERIOR REMOVALS OF NON LOAD BEARING PARTITIONS, AS INDICATED ON THE SUBMITTED DRAWINGS. NO CHANGE IN USE, EGRESS OR OCCUPANCY
On file for this project
3 documents · 1 drawing sheet
Floor 31p · 3 filings
ArchitectureDMElectricalEquipmentFire ProtectionGeneralMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Protection and Mechanical Methods · Standpipe · Structural · Supported Scaffold
UTILIZE EXISTING ELEVATOR SHAFT AS A DEBRIS CHUTE IN CONJUNCTION WITH FULL DEMO JOB 123906666
On file for this project
3 documents
INSTALL MEDIUM DUTY SCAFFOLDING AS PER PLANS. PIPE SCAFFOLDING SHALL COMPLY WITH CHAPTER 33 OF THE NYC BUILDING CODE. SIDEWALK SHED FILED UNDER SEPARATE APPLICATION
On file for this project
3 documents
INTERIOR REMOVALS OF NON LOAD BEARING PARTITIONS, AS INDICATED ON THE SUBMITTED DRAWINGS. NO CHANGE IN USE, EGRESS OR OCCUPANCY
On file for this project
3 documents · 1 drawing sheet
Floor 23 filings
ArchitectureDMElectricalEquipmentFire ProtectionGeneralMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Protection and Mechanical Methods · Standpipe · Structural · Supported Scaffold
UTILIZE EXISTING ELEVATOR SHAFT AS A DEBRIS CHUTE IN CONJUNCTION WITH FULL DEMO JOB 123906666
On file for this project
3 documents
INSTALL MEDIUM DUTY SCAFFOLDING AS PER PLANS. PIPE SCAFFOLDING SHALL COMPLY WITH CHAPTER 33 OF THE NYC BUILDING CODE. SIDEWALK SHED FILED UNDER SEPARATE APPLICATION
On file for this project
3 documents
INTERIOR REMOVALS OF NON LOAD BEARING PARTITIONS, AS INDICATED ON THE SUBMITTED DRAWINGS. NO CHANGE IN USE, EGRESS OR OCCUPANCY
On file for this project
3 documents
Floor 14p · 5 filings · 20 docs
ArchitectureCivilDMElectricalEquipmentFire ProtectionGeneralMechanicalPlumbingStructuralOtherZ
Issued Permit Scope
Earth Work · Foundation · General Construction · Mechanical Systems · Plumbing · Protection and Mechanical Methods · Standpipe · Structural · Supported Scaffold · Support of Excavation
Interior fit-out renovation for eating and drinking establishment on first and cellar floors. No change in egress, use or occupancy.
On file for this project
24 documents · 3 drawing sheets
Install kitchen exhaust and make up air systems
On file for this project
6 documents · 1 drawing sheet
UTILIZE EXISTING ELEVATOR SHAFT AS A DEBRIS CHUTE IN CONJUNCTION WITH FULL DEMO JOB 123906666
On file for this project
3 documents
Latest 3 of 5 filings on this floor.
Cellar2p · 1 filing · 20 docs
ArchitectureCivilDMElectricalFire ProtectionGeneralMechanicalPlumbingStructural
Issued Permit Scope
Earth Work · Foundation · General Construction · Mechanical Systems · Plumbing · Protection and Mechanical Methods · Standpipe · Structural · Support of Excavation
Interior fit-out renovation for eating and drinking establishment on first and cellar floors. No change in egress, use or occupancy.
On file for this project
24 documents · 2 drawing sheets
Site & exterior8 filings
ArchitectureCivilElectricalEquipmentFire ProtectionGeneralMechanicalPlumbingStructural
Issued Permit Scope
Construction Fence · Earth Work · Foundation · Protection and Mechanical Methods · Sidewalk Shed · Supported Scaffold · Support of Excavation
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
4 documents · 8 drawing sheets
INSTALLATION OF TEMPORARY PLYWOOD FENCE AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
6 documents · 11 drawing sheets
INSTALLATION OF TEMPORARY OVERHEAD PROTECTION AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
4 documents · 8 drawing sheets
Latest 3 of 8 filings on this floor.
Filed — no permit issued2 filings · 6 docs
ArchitectureDMGeneral
No filed description on record for this project.
On file for this project
2 documents · 1 drawing sheet
INTERIOR RENOVATION WORK ON EXISTING OFFICE SPACE ON THE 2ND,3RD, AND 4TH FLOORS. REPLACE FIXTURES IN BATHROOMS AT EXISTING ROUGH-IN LOCATIONS, AND ADDITIONAL SINK AND FAUCET AT A NEW WELLNESS ROOM ON FLOORS 2, 3, AND 4.
On file for this project