| Owner | Filings | Most Recent |
|---|---|---|
| JOHN PSARAS REALTY | 3 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| CL ENGINEERING P.C. | 4 | 04/12/2024 |
| PETER CHO ARCHITECTS, PLLC | 1 | 03/05/2024 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| NY BUILDING ASSOCIATES IN | General Contractor | 2 | 03/21/2026 |
| AMERICAN STANDARD PLUMBING & | Fire Protection | 1 | 07/08/2026 |
| AMERICAN STANDARD P&H CORORP. | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| CL ENGINEERING P.C. | 6781 | 4 | 04/12/2024 |
| NKM ENGINEERING PLLC | 6244 | 3 | 04/12/2024 |
| D&E BUILD EVERGREEN I | 9342 | 1 | 03/05/2024 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Sprinklers | Signed-off | AMERICAN STANDARD P&H CORORP. | 03/26/2024 |
| DOB NOW | Sprinklers | Signed-off | AMERICAN STANDARD PLUMBIN | 03/26/2024 |
| DOB NOW | Mechanical Systems | Signed-off | NY BUILDING ASSOCIATES IN | 03/16/2024 |
| BIS | PL | ISSUED | ACE CONTRACTING, INC | 03/25/2015 |
| BIS | BL | ISSUED | ACE CONTRACTING, INC | 03/25/2015 |
| BIS | OT | ISSUED | DAHILL CONSTRUCTION CO.,I | 09/02/2014 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 03/27/2024 | Complete | GOODALL ELECTRIC CORP | — |
| Date | Type | Result | Report |
|---|---|---|---|
| 06/06/2025 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 03/17/2025 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 03/12/2025 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 03/10/2025 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 04/11/2024 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 04/11/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 04/16/2024 | Tenant Protection Plan Compliance | Danny Chen | special |
| 04/16/2024 | HVAC-R and service water heating system controls | NARESH MAHANGU | energy_progress |
| 04/16/2024 | HVAC-R and service water heating equipment | NARESH MAHANGU | energy_progress |
| 04/16/2024 | HVAC-R and service water piping design and insulation | NARESH MAHANGU | energy_progress |
| 04/16/2024 | Fire-Resistance Rated Construction | NARESH MAHANGU | progress |
| 04/16/2024 | Final | PETER CHO | progress |
| 04/16/2024 | Energy Code Compliance Inspections | NARESH MAHANGU | progress |
| 04/16/2024 | Mechanical Systems | Danny Chen | special |
| 04/16/2024 | Concrete - Cast-In-Place | Danny Chen | special |
| 04/16/2024 | Fire-Resistant Penetrations and Joints | Danny Chen | special |
| 04/15/2024 | HVAC-R and service water piping design and insulation | CHRISTIAN LOZADA | energy_progress |
| 04/15/2024 | Sprinkler Systems | CHRISTIAN LOZADA | special |
| 04/15/2024 | Tenant Protection Plan Compliance | NARESH MAHANGU | special |
| 04/15/2024 | Fire-Resistant Penetrations and Joints | CHRISTIAN LOZADA | special |
| 04/15/2024 | Energy Code Compliance Inspections | CHRISTIAN LOZADA | progress |
| 04/15/2024 | HVAC-R and service water heating equipment | CHRISTIAN LOZADA | energy_progress |
| 04/15/2024 | HVAC-R and service water heating system controls | CHRISTIAN LOZADA | energy_progress |
| 04/12/2024 | Concrete - Cast-In-Place | CHRISTIAN LOZADA | special |
| 04/12/2024 | HVAC-R and service water piping design and insulation | CHRISTIAN LOZADA | energy_progress |
| 04/12/2024 | HVAC-R and service water heating system controls | CHRISTIAN LOZADA | energy_progress |
| 04/12/2024 | HVAC-R and service water heating equipment | CHRISTIAN LOZADA | energy_progress |
| 04/12/2024 | Fire-Resistance Rated Construction | CHRISTIAN LOZADA | progress |
| 04/12/2024 | Final | CHRISTIAN LOZADA | progress |
| 04/12/2024 | Energy Code Compliance Inspections | CHRISTIAN LOZADA | progress |
| 04/12/2024 | Tenant Protection Plan Compliance | CHRISTIAN LOZADA | special |