| Owner | Filings | Most Recent |
|---|---|---|
| ACER CONSTRUCTION | 1 | 03/22/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 12/18/2023 | $2.5M | — | Private party → 668 BALTIC LLC | — not available |
| Firm | Filings | Most Recent |
|---|---|---|
| PAUL CHRISTAKOS ARCHITECTURE | 10 | 03/10/2025 |
| FABIAN CRUZ PE PLLC | 2 | 12/30/2024 |
| JIAN ENGINEERING PLLC | 2 | 04/09/2024 |
| JOEL PHAGOO P.E. PLLC | 2 | 02/13/2024 |
| Representative | Filings | Most Recent |
|---|---|---|
| ACCRETE CONSTRUCTION | 8 | 03/21/2026 |
| A1 EXPEDITING SERVICE | 4 | 03/21/2026 |
| H Z BUILDING NY | 4 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| ACER CONSTRUCTION INC | General Contractor | 11 | 07/08/2026 |
| ACCRETE CONSTRUCTION GROUP | General Contractor | 4 | 07/08/2026 |
| AKM CONSTRUCTION NY CORP | General Contractor | 3 | 07/08/2026 |
| SUNSHINE BUILDERS INC | General Contractor | 3 | 03/21/2026 |
| PRECISION SPKLR SVCS LLC | Fire Protection | 1 | 07/08/2026 |
| INFINITI ESC PLUMBING COR | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| JIAN ENGINEERING PLLC | 7397 | 8 | 03/10/2025 |
| PAUL CHRISTAKOS ARCHITECT | 5894 | 4 | 03/10/2025 |
| IP CONCRETE TESTING AND I | 6252 | 3 | 10/02/2024 |
| JOEL PHAGOO ,PE, PLLC | 2416 | 1 | 02/13/2024 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Mechanical Systems | Signed-off | ACER CONSTRUCTION INC | 03/05/2025 |
| DOB NOW | Curb Cut | Signed-off | SUNSHINE BUILDERS INC | 12/10/2024 |
| DOB NOW | Sprinklers | Signed-off | PRECISION SPKLR SVCS LLC | 07/29/2024 |
| DOB NOW | General Construction | Permit Issued | ACER CONSTRUCTION INC | 07/11/2024 |
| DOB NOW | Plumbing | Signed-off | INFINITI ESC PLUMBING COR | 06/06/2024 |
| DOB NOW | Structural | Signed-off | ACER CONSTRUCTION INC | 03/18/2024 |
| DOB NOW | Construction Fence | Signed-off | ACER CONSTRUCTION INC | 02/28/2024 |
| DOB NOW | General Construction | Signed-off | ACER CONSTRUCTION INC | 02/28/2024 |
| DOB NOW | Sidewalk Shed | Signed-off | AKM CONSTRUCTION NY | 02/14/2024 |
| DOB NOW | Supported Scaffold | Signed-off | AKM CONSTRUCTION NY | 02/14/2024 |
| DOB NOW | Construction Fence | Signed-off | ACCRETE CONSTRUCTION GROU | 01/22/2024 |
| DOB NOW | General Construction | Signed-off | ACCRETE CONSTRUCTION GROU | 11/28/2023 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 03/10/2025 | Signed-off | INFINITI ESC PLUMBING COR | Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 02/13/2024 | Complete | HIGH QUALITY ELECTRIC OF | — |
| 02/01/2024 | Complete | K.A.B. ELECTRIC CORP | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 03/10/2025 | Signed-off | ACER CONSTRUCTION INC | Steel, Concrete, Masonry |
| Date | Type | Result | Report |
|---|---|---|---|
| 05/07/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 04/21/2025 | Certified Storm Drainage-ST-Fixtures-Finish | Certified | View ↗ |
| 03/12/2025 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 03/09/2025 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 02/26/2025 | Pass-Final Curb Cut Non-Directive 14 | Pass | View ↗ |
| 07/03/2024 | Certified Storm Drainage-ST-Piping-Roughing | Certified | View ↗ |
| 07/03/2024 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 07/03/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 07/03/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 02/26/2025 | Fire-Resistant Penetrations and Joints | Paul Christakos | special |
| 02/26/2025 | Energy Code Compliance Inspections | Paul Christakos | progress |
| 02/26/2025 | Fenestration and door U-factor and product ratings | Paul Christakos | energy_progress |
| 02/26/2025 | Structural Stability – Alterations of existing buildings | JIAN DENG | special |
| 02/26/2025 | Fire-Resistance Rated Construction | Paul Christakos | progress |
| 02/26/2025 | Maintenance information | JIAN DENG | energy_progress |
| 02/26/2025 | Metering | Paul Christakos | energy_progress |
| 02/26/2025 | Exterior lighting power | Paul Christakos | energy_progress |
| 02/26/2025 | Interior lighting power | Paul Christakos | energy_progress |
| 02/26/2025 | Lighting controls | Paul Christakos | energy_progress |
| 02/26/2025 | Insulation placement and R values | Paul Christakos | energy_progress |
| 02/26/2025 | Protection of exposed foundation insulation | JIAN DENG | energy_progress |
| 02/26/2025 | Fenestration air leakage | Paul Christakos | energy_progress |
| 02/26/2025 | Air barrier - visual inspection | Paul Christakos | energy_progress |
| 02/26/2025 | Fenestration areas | Paul Christakos | energy_progress |
| 02/26/2025 | Lighting in dwelling units | Paul Christakos | energy_progress |
| 01/14/2025 | Duct leakage testing, insulation and design | JIAN DENG | energy_progress |
| 01/11/2025 | Maintenance information | JIAN DENG | energy_progress |
| 01/02/2025 | HVAC-R and service water heating equipment | JIAN DENG | energy_progress |
| 01/02/2025 | Shutoff dampers | JIAN DENG | energy_progress |
| 01/02/2025 | HVAC-R and service water piping design and insulation | JIAN DENG | energy_progress |
| 01/02/2025 | HVAC-R and service water heating system controls | JIAN DENG | energy_progress |
| 10/01/2024 | Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation | INDARDEO PARBHUNATH | special |
| 10/01/2024 | HVAC-R and service water heating equipment | Paul Christakos | energy_progress |
| 10/01/2024 | HVAC-R and service water heating system controls | Paul Christakos | energy_progress |