Two family frame
67-11 50 AVENUE
QUEENS · Woodside · BIN 4056202
💬 Discuss this project
1930Year Built
2Stories
B2Building Class
R4-1Zoning
1,785 sfGross Floor Area
2Units
Two family frame · 2,500 sf lot · 0.71 FAR built · Flood zone X
Locations of Work
Electrical
Roof1 filing · 6 docs
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
MOMENTUM SOLAR109/03/2025
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
MXV SIA LLC9281109/03/2025
Building Lifecycle
All (7)Filed (1)Permit Issued (1)Special Inspection (5)
09/05/2025
Permit issued — Solar
Q01280895-I1-SL
09/03/2025
Filed — Alteration
Installation of solar panels, rooftop, grid tied, railed, 16 modules, 6.88 KW
Q01280895-I1
09/03/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
Mina Makar
09/03/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
Mina Makar
09/03/2025
Special inspection requirement — Energy Code Compliance Inspections
Mina Makar
09/03/2025
Special inspection requirement — Final
Mina Makar
09/03/2025
Special inspection requirement — Air barrier - visual inspection
Mina Makar
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSolarPermit IssuedMOMENTUM SOLAR09/05/2025
1 project · most recent 09/03/2025
FiledStatusContractorScope
09/03/2025Permit IssuedISLAND ELECTRIC CORP—
1 project · most recent 09/03/2025
FiledStatusContractorScope
09/03/2025Permit IssuedMOMENTUM SOLAR16 panels, 6.88 kw, 281 roof_area_sqft
▾Special Inspection Requirements (DOB NOW) — 5
DateRequirementInspectorRole
09/03/2025Fire-Resistant Penetrations and JointsMina Makarspecial
09/03/2025Structural Stability – Alterations of existing buildingsMina Makarspecial
09/03/2025Energy Code Compliance InspectionsMina Makarprogress
09/03/2025FinalMina Makarprogress
09/03/2025Air barrier - visual inspectionMina Makarenergy_progress
▾Documents — 6 on file (BIS + DOB NOW)
▸Plans & Drawings1
▸DOB NOWPlans/Sketch1
08/19/2026Q01280895-I1Request digital key ↗
▸Seals & Professional Certifications4
▸DOB NOWProgress Inspector Seal & Signature2
08/23/2026Q01280895-I1Open ↗
08/23/2026Q01280895-I1Open ↗
▸DOB NOWDPL-1: Design Professional Seal & Signature1
08/19/2026Q01280895-I1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature1
08/23/2026Q01280895-I1Open ↗
▸Environmental & Asbestos1
▸DOB NOWDEP ACP-5: Asbestos Assessment Report1
08/19/2026Q01280895-I1Open ↗