| Owner | Filings | Most Recent |
|---|---|---|
| NEW YORK UNIVERSITY | 166 | 07/08/2026 |
| LUXURY HOME IMPROVEMENT CORP | 9 | 03/22/2026 |
| COASTAL COMM SERV INC | 1 | 03/21/2026 |
| NYU OFFICE OF CONSTRUCTION | 1 | 03/21/2026 |
| NYU OFFICE OF CONSTRUCTION MGMT | 5 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| TITAN ENGINEERING PC | 1 | 06/15/2026 |
| HC PEC | 3 | 04/16/2026 |
| POLISE CONSULTING ENGINEER | 3 | 01/20/2026 |
| MATIZ ARCHITECTURE AND DESIGN | 3 | 01/16/2026 |
| SUPERSTRUCTURES ENG. + ARCH. | 1 | 06/30/2025 |
| N.E.E.D. ARCHITECTURE LLC | 3 | 06/24/2025 |
| GUTH DECONZO CONSULTING ENGINEERS, | 1 | 06/28/2024 |
| ENVIRONETICS | 1 | 06/25/2024 |
| POLISE CONSULTING ENGINEERS DPC | 3 | 10/11/2023 |
| SOYU ARCHITECTURE, INC. | 3 | 12/06/2022 |
| JONG HAE CHANG ARCHITECT | 3 | 12/05/2022 |
| NICOLAS BARATTO ARCHITECT P.C. | 1 | 07/20/2022 |
| 360 ENGINEERING P.C. | 4 | 04/20/2021 |
| Representative | Filings | Most Recent |
|---|---|---|
| AE DESIGN SOLUTION | 8 | 03/21/2026 |
| RENAISSANCE CODE CONSULTANTS | 4 | 03/21/2026 |
| HTX BUILDING CONSULTING | 3 | 03/21/2026 |
| C PLUS DESIGN GROUP | 6 | 03/21/2026 |
| LUXURY HOME IMPROVEMENT | 6 | 03/21/2026 |
| SYNERGY BUILDING CONSULTANTS | 1 | 03/21/2026 |
| YAO W GUO ARCHITECT, PC | 2 | 03/21/2026 |
| CONVERSANO ASSOCIATES, INC. | 10 | 03/21/2026 |
| BURNHAM NATIONWIDE INC | 8 | 03/21/2026 |
| SUPERSTRUCTURES ENG + ARCH | 1 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| PJP INSTALLERS INC | General Contractor | 9 | 07/08/2026 |
| BROSNA CONSTRUCTION CORPO | General Contractor | 6 | 03/21/2026 |
| SITE ENTER INC | General Contractor | 4 | 04/09/2026 |
| FINALY GENL CONTR CORP | General Contractor | 4 | 03/21/2026 |
| MANHATTAN D ENTERPRISES | General Contractor | 4 | 07/08/2026 |
| SPK/LEWIS CONSTRUCTION LL | General Contractor | 2 | 04/09/2026 |
| A W R GROUP INC | General Contractor | 2 | 07/08/2026 |
| ANESIS SERVICES CORP | Fire Protection | 1 | 07/08/2026 |
| SKINNER PLMNG & HTG CORP | Fire Protection | 1 | 07/08/2026 |
| LUXURY HOME IMPROVEMENT | General Contractor | 1 | 07/08/2026 |
| ARIANA CONTRACTING INC | Plumbing | 1 | 07/08/2026 |
| DPH PLUMBING & HTG CORP | Plumbing | 1 | 07/08/2026 |
| HYDROKINETIC PLBG & HTG I | Plumbing | 1 | 07/08/2026 |
| BARBIERI, LAWRENCE | Electrical | 1 | 03/21/2026 |
| XH&RC PLBG AND HTG INC | Plumbing | 1 | 07/08/2026 |
| BENI, CARMINE | Electrical | 1 | 03/21/2026 |
| CESAR QUERY | Electrical | 1 | 03/21/2026 |
| ESCORCE, MANUEL | Electrical | 1 | 03/21/2026 |
| HEMNAUTH, SUDESH | Electrical | 1 | 03/21/2026 |
| R.D.I. ASSOCIATES INC | Electrical | 1 | 03/21/2026 |
| WALTON, MARC | Electrical | 1 | 03/21/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| RICHMOND TESTING LAB | 263 | 7 | 01/20/2026 |
| SUPERSTRUCTURES ENGINEERI | 374 | 1 | 06/30/2025 |
| KZ ENGINEERING, P.C. | 4665 | 1 | 06/25/2025 |
| SY ENGINEERING PLLC | 5149 | 3 | 06/24/2025 |
| FENAGH, INC | 6942 | 2 | 06/28/2024 |
| KLINE ENGINEERING, PC | 1007 | 5 | 10/11/2023 |
| SOYU ARCHITECTURE, INC. | 7399 | 3 | 12/06/2022 |
| JONG HAE CHANG ARCHITECT | 6169 | 3 | 12/05/2022 |
| NICOLAS BARATTO ARCHITECT | 847 | 1 | 07/20/2022 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | General Construction | Permit Issued | A W R GROUP INC | 06/08/2026 |
| DOB NOW | Construction Fence | Permit Issued | PJP INSTALLERS INC | 04/17/2026 |
| DOB NOW | Plumbing | Signed-off | DPH PLUMBING & HTG CORP | 02/04/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | SPK/LEWIS CONSTRUCTION LL | 02/03/2026 |
| DOB NOW | General Construction | Permit Issued | SPK/LEWIS CONSTRUCTION LL | 01/30/2026 |
| DOB NOW | Sprinklers | Permit Issued | SKINNER PLMNG & HTG CORP | 01/29/2026 |
| DOB NOW | General Construction | Permit Issued | A W R GROUP INC | 08/11/2025 |
| DOB NOW | Protection and Mechanical Methods | Permit Issued | PJP INSTALLERS INC | 07/28/2025 |
| DOB NOW | Sidewalk Shed | Permit Issued | PJP INSTALLERS INC | 07/28/2025 |
| DOB NOW | Plumbing | Signed-off | ARIANA CONTRACTING INC | 07/16/2025 |
| DOB NOW | General Construction | Signed-off | SITE ENTER INC | 07/10/2025 |
| DOB NOW | Mechanical Systems | Signed-off | SITE ENTER INC | 07/10/2025 |
| DOB NOW | Suspended Scaffold | Permit Issued | A W R GROUP INC | 06/27/2025 |
| DOB NOW | Mechanical Systems | Signed-off | FINALY GENL CONTR | 07/25/2024 |
| DOB NOW | General Construction | Signed-off | FINALY GENL CONTR | 07/25/2024 |
| DOB NOW | General Construction | Signed-off | LUXURY HOME IMPROVEMENT | 11/01/2022 |
| DOB NOW | Plumbing | Signed-off | XH&RC PLBG AND HTG INC | 10/31/2022 |
| DOB NOW | General Construction | Signed-off | BROSNA CONSTRUCTION CORPO | 07/25/2022 |
| DOB NOW | Sprinklers | Signed-off | HYDROKINETIC PLBG & HTG I | 05/20/2022 |
| DOB NOW | Sprinklers | Signed-off | THOMAS FAY | 05/20/2022 |
| DOB NOW | Mechanical Systems | Signed-off | BROSNA CONSTRUCTION CORPO | 05/16/2022 |
| DOB NOW | General Construction | Signed-off | BROSNA CONSTRUCTION CORPO | 04/25/2022 |
| DOB NOW | Construction Fence | Signed-off | PJP INSTALLERS INC | 03/24/2021 |
| DOB NOW | Sidewalk Shed | Signed-off | PJP INSTALLERS INC | 03/24/2021 |
| DOB NOW | Construction Fence | Signed-off | PJP INSTALLERS INC | 03/05/2020 |
| DOB NOW | Sidewalk Shed | Signed-off | PJP INSTALLERS INC | 03/05/2020 |
| DOB NOW | Sidewalk Shed | Signed-off | MANHATTAN D ENTERPRISES | 03/03/2020 |
| DOB NOW | Construction Fence | Signed-off | MANHATTAN D ENTERPRISES | 03/03/2020 |
| BIS | OT | ISSUED | ADLER WINDOWS INC | 04/26/2021 |
| BIS | SP | ISSUED | FULL CAPACITY FIRE CORP | 07/02/2019 |
| BIS | MH | ISSUED | SPK/LEWIS CONSTRUCTION LL | 06/26/2019 |
| BIS | OT | ISSUED | PRP MECHANICAL CONTRACTOR INC. | 08/29/2017 |
| BIS | SP | ISSUED | SKINNER PLMNG & HTG CORP | 04/28/2017 |
| BIS | OT | ISSUED | SUNLIGHT CONSTRUCTION AA | 04/10/2017 |
| BIS | PL | ISSUED | TOP PLUMBING GROUP,INC | 04/10/2017 |
| BIS | OT | ISSUED | SKYLINE RESTORATION INC | 06/15/2016 |
| BIS | EQ | ISSUED | PJP INSTALLERS INC | 06/07/2016 |
| BIS | MH | ISSUED | PRP MECHANICAL CONTRACTOR INC. | 10/30/2015 |
| BIS | SP | ISSUED | C.R.U. MECHAN & HEATIN IN | 07/16/2015 |
| BIS | PL | ISSUED | C.R.U. MECHAN & HEAT INC | 07/16/2015 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 01/20/2026 | Permit Issued | SKINNER PLMNG & HTG CORP | 100 heads |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/30/2026 | Permit Issued | ACCURATE ELEC'L CONTR'S C | General Wiring |
| 11/13/2025 | Complete | DELTA POWER ELECTRICAL | General Wiring |
| 08/13/2025 | Permit Issued | TOP SHELF ELECTRIC CORP | — |
| 10/25/2022 | Complete | AL-LECTRIC ELECT'L CONTRG | General Wiring |
| 04/18/2022 | Complete | M.C. ELECTRICAL NY INC | General Wiring |
| 02/12/2020 | Complete | TOP SHELF ELECTRIC CORP | — |
| 09/16/2019 | Complete | CONDUCTOR ELECL SVCS INC | General Wiring |
| 07/04/2019 | Complete | JUMPER ELECTRIC CORP | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/16/2026 | Permit Issued | PJP INSTALLERS INC | Fence |
| 07/26/2025 | Permit Issued | PJP INSTALLERS INC | Sidewalk Shed |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/30/2025 | Permit Issued | A W R GROUP INC | Tenant Protection Plan 72 Hour |
| Date | Type | Result | Report |
|---|---|---|---|
| 07/14/2026 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 07/09/2026 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 07/09/2026 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 07/09/2026 | Certified Sprinkler - SP - Roughing | Certified | View ↗ |
| 03/24/2026 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 02/20/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 02/18/2026 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 11/01/2025 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 10/31/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 08/20/2025 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 08/20/2025 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 08/05/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 01/11/2023 | Pass-Final General Construction Non-Directive 14 | Pass | View ↗ |
| 01/05/2023 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 01/04/2023 | Pass-Final General Construction Non-Directive 14 | Pass | View ↗ |
| 12/22/2022 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 12/02/2022 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 09/08/2022 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 09/07/2022 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 09/07/2022 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 08/24/2022 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 06/15/2022 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 06/04/2026 | Tenant Protection Plan Compliance | — | special |
| 05/29/2026 | Final | — | progress |
| 05/29/2026 | Mechanical Systems | — | special |
| 05/29/2026 | Emergency and Standby Power Systems (Generator) | — | special |
| 09/09/2025 | Lighting in dwelling units | RICHARD LEMANSKY | energy_progress |
| 08/22/2025 | Lighting controls | RICHARD LEMANSKY | energy_progress |
| 08/22/2025 | Energy Code Compliance Inspections | RICHARD LEMANSKY | progress |
| 08/22/2025 | Final | RICHARD LEMANSKY | progress |
| 08/22/2025 | Interior lighting power | RICHARD LEMANSKY | energy_progress |
| 08/22/2025 | Fire-Resistant Penetrations and Joints | RICHARD LEMANSKY | special |
| 08/22/2025 | Tenant Protection Plan Compliance | RICHARD LEMANSKY | special |
| 06/24/2025 | Alternative Materials - OTCR Buildings Bulletin Number | Karol Zdancewicz | special |
| 06/24/2025 | Post-installed Anchors | Karol Zdancewicz | special |
| 06/24/2025 | Tenant Protection Plan Compliance | SUNGBOM YI | special |
| 06/14/2025 | Interior lighting power | SUNGBOM YI | energy_progress |
| 06/14/2025 | Fire-Resistant Penetrations and Joints | SUNGBOM YI | special |
| 06/14/2025 | Energy Code Compliance Inspections | SUNGBOM YI | progress |
| 06/14/2025 | Lighting controls | SUNGBOM YI | energy_progress |
| 05/16/2025 | Final | SANGMOK KIM | progress |
| 05/08/2024 | Maintenance information | AILANTO DANIEL MINAWI | energy_progress |
| 05/08/2024 | Tenant Protection Plan Compliance | AILANTO DANIEL MINAWI | special |
| 05/07/2024 | HVAC-R and service water piping design and insulation | AILANTO DANIEL MINAWI | energy_progress |
| 05/07/2024 | Tenant Protection Plan Compliance | AILANTO DANIEL MINAWI | special |
| 05/07/2024 | HVAC-R and service water heating equipment | AILANTO DANIEL MINAWI | energy_progress |
| 05/07/2024 | HVAC-R and service water heating system controls | AILANTO DANIEL MINAWI | energy_progress |
| Tenant | Space | Floors | Renovation projects |
|---|---|---|---|
| Soyu Interior | Retail | Floor 1 | Project M08024525 |
| Nyu Steinhardt Art Studios | Education | Basement | Project M00670089 Project M00670102 |