← Back
One story - permanent living quarter
67-46 179 STREET
QUEENS · BIN 4153065
💬 Discuss this project
1945Year Built
1.5Stories
A2Building Class
R2AZoning
1,906 sfGross Floor Area
1Units
1 Open Violation ▸FDNY Report ↗
One story - permanent living quarter · Owner of record: TZADIK HOLDINGS LLC · 7,500 sf lot · 0.25 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralMechanicalPlumbing
Roof6p · 2 filings · 20 docs
Floor 21p · 1 filing · 20 docs
Floor 1
Cellar2p · 1 filing · 2 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
BIG APPLE CONTRACTORS1304/09/2026
6746 179 LLC503/22/2026
TZADIK HOLDINGS403/21/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
02/15/2024$1.5M—Private party → TZADIK HOLDINGS LLC$803/sf building
09/04/2020$1.5M—Private party → 6746 179 LLC$797/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
CITISCAPE CONSULTING LTD512/08/2025
MICHELLE CONTRI112/20/2024
AMINOV DESIGN ENGINEER, PC104/15/2021
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
A D BUILDING SOLUTIONS1203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
BIG APPLE CONTRACTORS LLCGeneral Contractor307/08/2026
FOUR POINTS P & H CORPPlumbing207/08/2026
SUSTAINABLE STRATEGIESGeneral Contractor104/09/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
M-CON ENGINEERING7341112/20/2024
IP CONCRETE TESTING AND I6252206/14/2024
Building Lifecycle
All (48)Filed (7)Permit Issued (6)Signed Off (4)Violation (1)Inspection (6)Objection (4)Special Inspection (20)
03/18/2026
Signed off — Alteration
APPLICATION IS FILED INCONJUNCTION WITH BIS APPLICATION 440650993 FOR FOUNDATION, EXCAVATION,UNDERPINNING & STRUCTURALWORK TYPE.
Q00510271-I1
03/17/2026
Inspection — Pass-Final General Construction Non-Directive 14
Pass
View inspection ↗
02/12/2026
Signed off — Alteration
PLUMBING WORK TYPE IN CONJUNCTION TO ALT APPLICATION #440650993
Q01015827-I1
12/15/2025
Signed off — Alteration
Q00503091-I1
12/08/2025
Filed — Alteration
PLUMBING WORK TYPE IN CONJUNCTION TO ALT APPLICATION #440650993
Q01015827-P2
11/14/2025
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
08/01/2025
Permit issued — Plumbing
Q01015827-I1-PL
05/09/2025
Signed off — Alteration
Q01130452-I1
04/29/2025
Inspection — Certified Storm Drainage-ST-Piping-Underground
Certified
View inspection ↗
03/21/2025
Permit issued — Construction Fence
Q00503091-I1-FN
01/10/2025
Permit issued — Solar
Q01130452-I1-SL
12/20/2024
Filed — Alteration
Q01130452-I1
12/06/2024
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
10/31/2024
Filed — Alteration
PLUMBING WORK TYPE IN CONJUNCTION TO ALT APPLICATION #440650993
Q01015827-P1
08/07/2024
Inspection — Pass-Final PL - Underground
Pass
View inspection ↗
08/01/2024
Inspection — Pass-Final PL - Underground
Pass
View inspection ↗
07/15/2024
Special inspection requirement — Footing and Foundation
INDARDEO PARBHUNATH
07/15/2024
Special inspection requirement — Structural Stability – Alterations of existing buildings
INDARDEO PARBHUNATH
07/15/2024
Special inspection requirement — Concrete - Cast-In-Place
INDARDEO PARBHUNATH
07/15/2024
Special inspection requirement — Excavations - Sheeting, Shoring, and Bracing
INDARDEO PARBHUNATH
07/15/2024
Special inspection requirement — Structural Steel - Welding
INDARDEO PARBHUNATH
07/15/2024
Special inspection requirement — Subgrade Inspections
INDARDEO PARBHUNATH
07/15/2024
Special inspection requirement — Structural Steel - Details
INDARDEO PARBHUNATH
07/15/2024
Special inspection requirement — Underpinning
INDARDEO PARBHUNATH
07/15/2024
Special inspection requirement — Structural Steel - High Strength Bolting
INDARDEO PARBHUNATH
07/15/2024
Special inspection requirement — Final
NAVEEN KUMAR
07/03/2024
Permit issued — Plumbing
Q01015827-I1-PL
07/03/2024
Objection resolved — Addressed
06/21/2024
Objection raised — Scope
06/14/2024
Filed — Alteration
APPLICATION IS FILED INCONJUNCTION WITH BIS APPLICATION 440650993 FOR FOUNDATION, EXCAVATION,UNDERPINNING & STRUCTURALWORK TYPE.
Q00510271-P1
06/14/2024
Special inspection requirement — Concrete - Cast-In-Place
INDARDEO PARBHUNATH
06/14/2024
Special inspection requirement — Excavations - Sheeting, Shoring, and Bracing
INDARDEO PARBHUNATH
06/14/2024
Special inspection requirement — Structural Stability – Alterations of existing buildings
INDARDEO PARBHUNATH
06/14/2024
Special inspection requirement — Structural Steel - Details
INDARDEO PARBHUNATH
06/14/2024
Special inspection requirement — Structural Steel - High Strength Bolting
INDARDEO PARBHUNATH
06/14/2024
Special inspection requirement — Structural Steel - Welding
INDARDEO PARBHUNATH
06/14/2024
Special inspection requirement — Subgrade Inspections
INDARDEO PARBHUNATH
06/14/2024
Special inspection requirement — Underpinning
INDARDEO PARBHUNATH
06/14/2024
Special inspection requirement — Final
NAVEEN KUMAR
06/14/2024
Special inspection requirement — Footing and Foundation
INDARDEO PARBHUNATH
03/06/2024
Filed — Alteration
PLUMBING WORK TYPE IN CONJUNCTION TO ALT APPLICATION #440650993
Q01015827-I1
03/06/2024
Violation issued (ECB, open)
Construction
03/01/2024
Permit issued — Construction Fence
Q00503091-I1-FN
03/01/2024
Permit issued — Earth Work
Q00510271-I1-GC-CX
05/10/2021
Objection raised — Scope
05/10/2021
Objection resolved — Addressed
04/29/2021
Filed — Alteration
APPLICATION IS FILED INCONJUNCTION WITH BIS APPLICATION 440650993 FOR FOUNDATION, EXCAVATION,UNDERPINNING & STRUCTURALWORK TYPE.
Q00510271-I1
04/15/2021
Filed — Alteration
Q00503091-I1
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWPlumbingSigned-offFOUR POINTS P & H CORP08/01/2025
DOB NOWConstruction FenceSigned-offBIG APPLE CONTRACTORS LLC03/21/2025
DOB NOWSolarSigned-offSUSTAINABLE STRATEGIES01/10/2025
DOB NOWPlumbingSigned-offFOUR POINTS P & H CORP07/03/2024
DOB NOWConstruction FenceSigned-offBIG APPLE CONTRACTORS LLC03/01/2024
DOB NOWEarth WorkSigned-offBIG APPLE CONTRACTORS LLC03/01/2024
BIS—ISSUEDBIG APPLE CONTRACTORS LLC03/21/2025
BIS—ISSUEDBIG APPLE CONTRACTORS LLC03/15/2024
BIS—RE-ISSUEDBIG APPLE CONTRACTORS LLC03/12/2024
2 projects · most recent 10/14/2024
General Wiring
FiledStatusContractorScope
10/14/2024CompleteSOURCE ELECTRIC INC1 meters
08/07/2024CompleteKINGS ELECTRIC CO., INC.General Wiring
▾Field Inspections (DOB CAP) — 6
DateTypeResultReport
03/17/2026Pass-Final General Construction Non-Directive 14PassView ↗
11/14/2025Pass-Final PL - Up to 3 Requested FloorsPassView ↗
04/29/2025Certified Storm Drainage-ST-Piping-UndergroundCertifiedView ↗
12/06/2024Pass-Final PL - Up to 3 Requested FloorsPassView ↗
08/07/2024Pass-Final PL - UndergroundPassView ↗
08/01/2024Pass-Final PL - UndergroundPassView ↗
▾Special Inspection Requirements (DOB NOW) — 20
DateRequirementInspectorRole
07/15/2024Footing and FoundationINDARDEO PARBHUNATHprogress
07/15/2024Structural Stability – Alterations of existing buildingsINDARDEO PARBHUNATHspecial
07/15/2024Concrete - Cast-In-PlaceINDARDEO PARBHUNATHspecial
07/15/2024Excavations - Sheeting, Shoring, and BracingINDARDEO PARBHUNATHspecial
07/15/2024Structural Steel - WeldingINDARDEO PARBHUNATHspecial
07/15/2024Subgrade InspectionsINDARDEO PARBHUNATHspecial
07/15/2024Structural Steel - DetailsINDARDEO PARBHUNATHspecial
07/15/2024UnderpinningINDARDEO PARBHUNATHspecial
07/15/2024Structural Steel - High Strength BoltingINDARDEO PARBHUNATHspecial
07/15/2024FinalNAVEEN KUMARprogress
06/14/2024Concrete - Cast-In-PlaceINDARDEO PARBHUNATHspecial
06/14/2024Excavations - Sheeting, Shoring, and BracingINDARDEO PARBHUNATHspecial
06/14/2024Structural Stability – Alterations of existing buildingsINDARDEO PARBHUNATHspecial
06/14/2024Structural Steel - DetailsINDARDEO PARBHUNATHspecial
06/14/2024Structural Steel - High Strength BoltingINDARDEO PARBHUNATHspecial
06/14/2024Structural Steel - WeldingINDARDEO PARBHUNATHspecial
06/14/2024Subgrade InspectionsINDARDEO PARBHUNATHspecial
06/14/2024UnderpinningINDARDEO PARBHUNATHspecial
06/14/2024FinalNAVEEN KUMARprogress
06/14/2024Footing and FoundationINDARDEO PARBHUNATHprogress
▾Documents — 87 on file (BIS + DOB NOW)
▸Plans & Drawings4
▸DOB NOWPlans/Sketch4
08/27/2026Q00503091-I1Request digital key ↗
08/22/2026Q00510271-I1Request digital key ↗
08/21/2026Q01130452-I1Request digital key ↗
Showing 3 of 4 on file for this type
▸Applications & Permits15
▸BISPLAN / WORK APPROVAL APPLICATION8
02/17/2026440662944Open ↗
06/03/2025440650993Open ↗
12/23/2024440650993Open ↗
Showing 3 of 8 on file for this type
▸BISBPP-5 - Authorization to the Department of Transportation2
10/15/2025440662944Open ↗
01/25/2021440662944Open ↗
▸BISWORK PERMIT APPLICATION2
04/08/2025440650993Open ↗
03/15/2024440650993Open ↗
▸BISPARTIAL DEMO: 10-DAY NOTICE (FOR AL/EW-OT PERMITS)1
03/13/2024440650993Open ↗
▸BISPARTIAL DEMO PLAN & DS1 (FOR AL/EW-OT PERMITS)1
06/28/2021440650993Open ↗
▸BISCERTIFICATE OF OCCUPANCY: APPLICATION1
12/18/2025440650993Open ↗
▸Zoning, Tax Lot & Property Records5
▸BISZONING DIAGRAM2
04/22/2021440650993Open ↗
02/19/2021440650993Open ↗
▸BISVERIFY TAX LOT1
02/13/2026440650993Open ↗
▸BISCO OBJ: VERIFY ADDRESS-TOPO STAMP1
02/13/2026440650993Open ↗
▸BISPD1 FORM WITH BP TOPO UNIT VERIFICATION(ZR 12-10 #ZONING LOT#)1
02/19/2021440650993Open ↗
▸Seals & Professional Certifications27
▸DOB NOWSpecial Inspector Seal & Signature16
09/01/2026Q00510271-I1Open ↗
09/01/2026Q00510271-I1Open ↗
09/01/2026Q00510271-I1Open ↗
Showing 3 of 16 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature5
08/22/2026Q00510271-I1Open ↗
08/21/2026Q01130452-I1Open ↗
08/13/2026Q00503091-I1Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWProgress Inspector Seal & Signature4
09/01/2026Q00510271-I1Open ↗
09/01/2026Q00510271-I1Open ↗
08/30/2026Q00510271-P1Open ↗
Showing 3 of 4 on file for this type
▸BISAPPLICANT OWNER SIGNATURE2
01/25/2021440662944Open ↗
11/27/2020440650993Open ↗
▸Trade Schedules & Equipment3
▸BISDEP STORMWATER SEWER CERTIFICATION (HCP/SCP)-DEFERRED AS PER DBC INSTRUCTION. SEE HOLD-HARMLESS LETTER1
04/22/2021440650993Open ↗
▸BISDEP SANITARY SEWER CERTIFICATION (HCP/SCP)1
02/13/2026440650993Open ↗
▸BISDEP SANITARY SEWER CERTIFICATION (HCP/SCP)-DEFFERED AS PER DBC INSTRUCTION. SEEHOLD HARMLESS LETTER.1
04/22/2021440650993Open ↗
▸Safety & Tenant Protection1
▸BISSTREET TREE CHECKLIST1
12/31/2020440650993Open ↗
▸Environmental & Asbestos4
▸DOB NOWDEP ACP-5: Asbestos Assessment Report3
08/22/2026Q00510271-I1Open ↗
08/13/2026Q00510271-P1Open ↗
08/13/2026Q01015827-P2Open ↗
▸BISASBESTOS: CERTIFICATION (DEP ACP5)1
11/27/2020440650993Open ↗
▸Energy Compliance3
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY3
03/04/2024440650993Open ↗
01/22/2021440650993Open ↗
11/27/2020440650993Open ↗
▸Inspections & Test Reports8
▸BISTECHNICAL REPORT: RESPONSIBILITY4
03/04/2024440650993Open ↗
12/31/2020440650993Open ↗
12/31/2020440650993Open ↗
Showing 3 of 4 on file for this type
▸BISSOIL PERC. TEST-PVT ON-SITE STORM WATER DRAINAGE DISPOSAL SYS & DET. FACL.1
03/06/2024440650993Open ↗
▸BISSOIL REPORT1
12/31/2020440650993Open ↗
▸BISTR2: CONCRETE FIELD TESTING TECHNICAL REPORT1
03/04/2024440650993Open ↗
▸BISTR3: CONCRETE DESIGN MIX TECHNICAL REPORT1
03/04/2024440650993Open ↗
▸Approvals, Objections & Sign-offs5
▸BISLETTERS - SUPPORTING DOCUMENTATION2
02/19/2026440662944Open ↗
02/26/2024440650993Open ↗
▸BISSCHEDULE A - OCCUPANCY / USE2
02/26/2024440650993Open ↗
02/26/2021440650993Open ↗
▸DOB NOWUtility Company Final Acceptance Letter1
08/13/2026Q01130452-I1Open ↗
▸Cost, Insurance & Ownership1
▸BISCOST AFFIDAVIT1
01/22/2021440650993Open ↗
▸Filing & Intake Forms7
▸BISADDITIONAL INFORMATION3
02/19/2026440662944Open ↗
05/14/2021440650993Open ↗
03/08/2021440650993Open ↗
▸BISEFILING JOB APPLICATION COVER SHEET2
01/25/2021440662944Open ↗
11/27/2020440650993Open ↗
▸BISBOROUGH INTAKE FORM1
04/08/2025440650993Open ↗
▸BISBPP: CHECKLIST IN LIEU OF PLANS-ALT31
02/19/2026440662944Open ↗
▸Other Documents4
▸BISBPP - SUPPORTING DOCUMENTATION1
01/25/2021440662944Open ↗
▸BISSUSTAINABLE ROOF ZONE FORM1
11/27/2020440650993Open ↗
▸DOB NOWAdjoining Owners Notification1
08/13/2026Q00510271-I1Open ↗
▸DOB NOWPARTIAL DEMO: 10-DAY Notice1
08/13/2026Q00510271-I1Open ↗