Miscellaneous indoor public assembly
670 92 STREET
BROOKLYN · Bay Ridge · BIN 3156347
💬 Discuss this project
2019Year Built
3Stories
P9Building Class
R4BZoning
9,032 sfGross Floor Area
1Units
0 Open ViolationsFDNY Report ↗
Miscellaneous indoor public assembly · Owner of record: THE GREEK SCHOOL OF PLATO, LTD. · 4,520 sf lot · 2 FAR built · Flood zone X
Locations of Work
StructuralPlumbing
Roof2p · 1 filing · 19 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
HKS CONSTRUCTION3907/08/2026
GREEK SCHOOL OF PLATO3503/22/2026
THE GREEK SCHOOL OF PLAT0103/22/2026
GREEK SCHOOL403/21/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
SEARS TAMBASCO ARCHITECTURE, PC210/02/2020
ENTHINK ENGINEERS LLC210/04/2019
HAIDER ENGINEERING, P.E.1109/18/2019
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
SNR EXPEDITING DESIGN1203/21/2026
HAIDER ENGINEERING, P.E.703/21/2026
HAIDER ENGINEERING P E703/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
HKS CONSTRUCTION CORPGeneral Contractor1407/08/2026
WILLIAM RYANElectrical203/21/2026
RICHARD NEUElectrical103/22/2026
SWITCH ELECT OF THE FIVEElectrical103/22/2026
NAF PAK PLBG HTGGeneral Contractor103/22/2026
Building Lifecycle
All (53)Filed (15)Permit Issued (6)Signed Off (3)Violation (26)Special Inspection (3)
11/17/2020
Signed off — Alteration
B00239536-I1
11/17/2020
Signed off — Alteration
PROPOSED INSTALLATION OF HEAVY DUTY SIDEWALK SHED AS PER PLANS. LIVE LOAD 300 LBS PER SQUARE FEET. SIDEWALK SHED SHALL COMPLY WITH CHAPTER #33 OF THE NYC BUILDING CODE. NO CHANGE IN USE, OCCUPANCY, OR EGRESS UNDER THIS APPLICATION.
B00059139-I1
10/02/2020
Filed — No Work
B00406144-I1
10/02/2020
Filed — No Work
B00406104-I1
09/30/2020
Special inspection requirement — Public Assembly Emergency Lighting
SAMI HAJJAR P.E
05/22/2020
Violation issued (ECB, closed)
Construction
05/22/2020
Violation issued (ECB, closed)
Construction
10/11/2019
Violation issued (ECB, closed)
Construction
10/11/2019
Violation issued (ECB, closed)
Construction
10/11/2019
Violation issued (ECB, closed)
Construction
10/11/2019
Violation issued (ECB, closed)
Construction
10/07/2019
Permit issued — Supported Scaffold
B00239536-I1-SF
10/04/2019
Filed — Alteration
B00239536-I1
10/03/2019
Signed off — Alteration
PROPOSED INSTALLATION OF TEMPORARY PIPE SCAFFOLD FOR NEW BUILDING AS PER PLANS. WORK SHALL COMPLY WITH CHAPTER #33 OF THE NYC BUILDING CODE. NO CHANGE IN USE, OCCUPANCY, OR EGRESS UNDER THIS APPLICATION.
B00059143-I1
09/18/2019
Filed — Alteration
PROPOSED INSTALLATION OF TEMPORARY PIPE SCAFFOLD FOR NEW BUILDING AS PER PLANS. WORK SHALL COMPLY WITH CHAPTER #33 OF THE NYC BUILDING CODE. NO CHANGE IN USE, OCCUPANCY, OR EGRESS UNDER THIS APPLICATION.
B00059143-P7
09/18/2019
Special inspection requirement — Final
JAFAR HAIDER
09/10/2019
Filed — Alteration
PROPOSED INSTALLATION OF TEMPORARY PIPE SCAFFOLD FOR NEW BUILDING AS PER PLANS. WORK SHALL COMPLY WITH CHAPTER #33 OF THE NYC BUILDING CODE. NO CHANGE IN USE, OCCUPANCY, OR EGRESS UNDER THIS APPLICATION.
B00059143-P6
09/06/2019
Filed — Alteration
PROPOSED INSTALLATION OF TEMPORARY PIPE SCAFFOLD FOR NEW BUILDING AS PER PLANS. WORK SHALL COMPLY WITH CHAPTER #33 OF THE NYC BUILDING CODE. NO CHANGE IN USE, OCCUPANCY, OR EGRESS UNDER THIS APPLICATION.
B00059143-P5
08/29/2019
Violation issued (ECB, closed)
Construction
08/29/2019
Violation issued (ECB, closed)
Site Safety
08/29/2019
Violation issued (ECB, closed)
Construction
08/29/2019
Violation issued (ECB, closed)
Construction
06/03/2019
Filed — Alteration
PROPOSED INSTALLATION OF TEMPORARY PIPE SCAFFOLD FOR NEW BUILDING AS PER PLANS. WORK SHALL COMPLY WITH CHAPTER #33 OF THE NYC BUILDING CODE. NO CHANGE IN USE, OCCUPANCY, OR EGRESS UNDER THIS APPLICATION.
B00059143-P4
05/23/2019
Filed — Alteration
PROPOSED INSTALLATION OF HEAVY DUTY SIDEWALK SHED AS PER PLANS. LIVE LOAD 300 LBS PER SQUARE FEET. SIDEWALK SHED SHALL COMPLY WITH CHAPTER #33 OF THE NYC BUILDING CODE. NO CHANGE IN USE, OCCUPANCY, OR EGRESS UNDER THIS APPLICATION.
B00059139-P3
05/23/2019
Filed — Alteration
PROPOSED INSTALLATION OF TEMPORARY PIPE SCAFFOLD FOR NEW BUILDING AS PER PLANS. WORK SHALL COMPLY WITH CHAPTER #33 OF THE NYC BUILDING CODE. NO CHANGE IN USE, OCCUPANCY, OR EGRESS UNDER THIS APPLICATION.
B00059143-P3
05/23/2019
Special inspection requirement — Final
Sunil Saigal
04/26/2019
Filed — Alteration
PROPOSED INSTALLATION OF TEMPORARY PIPE SCAFFOLD FOR NEW BUILDING AS PER PLANS. WORK SHALL COMPLY WITH CHAPTER #33 OF THE NYC BUILDING CODE. NO CHANGE IN USE, OCCUPANCY, OR EGRESS UNDER THIS APPLICATION.
B00059143-P2
04/20/2019
Violation issued (ECB, closed)
Construction
03/22/2019
Filed — Alteration
PROPOSED INSTALLATION OF TEMPORARY PIPE SCAFFOLD FOR NEW BUILDING AS PER PLANS. WORK SHALL COMPLY WITH CHAPTER #33 OF THE NYC BUILDING CODE. NO CHANGE IN USE, OCCUPANCY, OR EGRESS UNDER THIS APPLICATION.
B00059143-P1
03/22/2019
Filed — Alteration
PROPOSED INSTALLATION OF HEAVY DUTY SIDEWALK SHED AS PER PLANS. LIVE LOAD 300 LBS PER SQUARE FEET. SIDEWALK SHED SHALL COMPLY WITH CHAPTER #33 OF THE NYC BUILDING CODE. NO CHANGE IN USE, OCCUPANCY, OR EGRESS UNDER THIS APPLICATION.
B00059139-P2
03/19/2019
Permit issued — Sidewalk Shed
B00059139-I1-SH
03/15/2019
Permit issued — Sidewalk Shed
B00059139-I1-SH
03/13/2019
Permit issued — Supported Scaffold
B00059143-I1-SF
03/12/2019
Violation issued (ECB, closed)
Construction
03/12/2019
Violation issued (ECB, closed)
Construction
01/24/2019
Violation issued (ECB, closed)
Construction
01/24/2019
Violation issued (ECB, closed)
Cranes and Derricks
08/02/2018
Filed — Alteration
PROPOSED INSTALLATION OF HEAVY DUTY SIDEWALK SHED AS PER PLANS. LIVE LOAD 300 LBS PER SQUARE FEET. SIDEWALK SHED SHALL COMPLY WITH CHAPTER #33 OF THE NYC BUILDING CODE. NO CHANGE IN USE, OCCUPANCY, OR EGRESS UNDER THIS APPLICATION.
B00059139-P1
07/10/2018
Filed — Alteration
PROPOSED INSTALLATION OF HEAVY DUTY SIDEWALK SHED AS PER PLANS. LIVE LOAD 300 LBS PER SQUARE FEET. SIDEWALK SHED SHALL COMPLY WITH CHAPTER #33 OF THE NYC BUILDING CODE. NO CHANGE IN USE, OCCUPANCY, OR EGRESS UNDER THIS APPLICATION.
B00059139-I1
07/10/2018
Permit issued — Sidewalk Shed
B00059139-I1-SH
07/06/2018
Filed — Alteration
PROPOSED INSTALLATION OF TEMPORARY PIPE SCAFFOLD FOR NEW BUILDING AS PER PLANS. WORK SHALL COMPLY WITH CHAPTER #33 OF THE NYC BUILDING CODE. NO CHANGE IN USE, OCCUPANCY, OR EGRESS UNDER THIS APPLICATION.
B00059143-I1
07/06/2018
Permit issued — Supported Scaffold
B00059143-I1-SF
01/24/2018
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
11/03/2017
Violation issued (ECB, closed)
Construction
11/03/2017
Violation issued (ECB, closed)
Construction
11/03/2017
Violation issued (ECB, closed)
Construction
11/03/2017
Violation issued (ECB, closed)
Unknown
10/11/2017
Violation issued (ECB, closed)
Construction
10/11/2017
Violation issued (ECB, closed)
Construction
11/22/2016
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
10/13/2016
Violation issued (ECB, closed)
Construction
10/13/2016
Violation issued (ECB, closed)
Construction
10/13/2016
Violation issued (ECB, closed)
Construction
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSupported ScaffoldSigned-offHKS CONSTRUCTION CORP10/07/2019
DOB NOWSidewalk ShedSigned-offHKS CONSTRUCTION CORP03/19/2019
DOB NOWSidewalk ShedSigned-offHKS CONSTRUCTION CORP03/15/2019
DOB NOWSupported ScaffoldSigned-offHKS CONSTRUCTION CORP03/13/2019
DOB NOWSidewalk ShedSigned-offHKS CONSTRUCTION CORP07/10/2018
DOB NOWSupported ScaffoldSigned-offHKS CONSTRUCTION CORP07/06/2018
BIS—ISSUEDHE GREEK SCHOOL OF PLATO09/29/2020
BIS—ISSUEDTHE GREEK SCHOOL OF PLATO05/08/2020
BIS—ISSUEDTHE GREEK SCHOOL OF PLATO05/06/2020
BIS—ISSUEDTHE GREEK SCHOOL OF PLATO02/14/2020
BISPLISSUEDNAF PAK PLBG & HTG CORP11/25/2019
BISMHISSUEDTHE GREEK SCHOOL OF PLATO06/20/2019
BIS—ISSUEDTHE GREEK SCHOOL OF PLATO02/28/2019
BIS—ISSUEDTHE GREEK SCHOOL OF PLATO08/29/2018
BISEQISSUEDTHE GREEK SCHOOL OF PLATO08/29/2018
BISEQISSUEDTHE GREEK SCHOOL OF PLATO08/23/2017
BIS—ISSUEDTHE GREEK SCHOOL OF PLATO08/23/2017
BIS—ISSUEDMICHAEL HARRIS09/21/2016
BISEQISSUEDMICHAEL HARRIS09/21/2016
6 projects · most recent 07/22/2020
General Wiring
FiledStatusContractorScope
07/22/2020CompleteSWITCH ELECT OF THE FIVEGeneral Wiring
10/17/2019CompleteRICHARD NEU—
10/07/2019CompleteSWITCH ELECT OF THE FIVE—
07/16/2018CompleteCONTACT PLUS ELEC'L CORP—
07/06/2018CompleteRICHARD NEU—
05/19/2018CompleteALL PURPOSE ELECTRIC CORP1 meters, 1 new_meters
▾Special Inspection Requirements (DOB NOW) — 3
DateRequirementInspectorRole
09/30/2020Public Assembly Emergency LightingSAMI HAJJAR P.Eprogress
09/18/2019FinalJAFAR HAIDERprogress
05/23/2019FinalSunil Saigalprogress
▾Documents — 249 on file (BIS + DOB NOW)
▸Plans & Drawings17
▸DOB NOWPlans/Sketch - Supported Scaffold9
09/03/2026B00059143-I1Request digital key ↗
09/02/2026B00239536-I1Request digital key ↗
08/15/2026B00059143-P5Request digital key ↗
Showing 3 of 9 on file for this type
▸DOB NOWPlans/Sketch - Sidewalk Shed3
09/03/2026B00059139-I1Request digital key ↗
08/15/2026B00059139-P3Request digital key ↗
08/15/2026B00059139-P2Request digital key ↗
▸DOB NOWPlans/Sketch3
09/03/2026B00059143-I1Request digital key ↗
09/03/2026B00059139-I1Request digital key ↗
09/03/2026B00059139-P1Request digital key ↗
▸DOB NOWPlans/Sketch - Place of Assembly2
09/02/2026B00406104-I1Request digital key ↗
09/02/2026B00406144-I1Request digital key ↗
▸Applications & Permits56
▸BISPLAN / WORK APPROVAL APPLICATION40
05/12/2021320932871Open ↗
05/10/2021320932871Open ↗
05/07/2021320932871Open ↗
Showing 3 of 40 on file for this type
▸BISWORK PERMIT APPLICATION13
05/08/2020320932871Open ↗
05/07/2020320932871Open ↗
02/18/2020320932871Open ↗
Showing 3 of 13 on file for this type
▸BISCERTIFICATE OF OCCUPANCY: APPLICATION2
09/09/2020320932871Open ↗
08/05/2020320932871Open ↗
▸BISBPP-5 - Authorization to the Department of Transportation1
02/12/2018321141689Open ↗
▸Zoning, Tax Lot & Property Records6
▸BISZONING EXHIBIT III:DESC. & OWNRSHP.STMNT1
04/06/2015320932871Open ↗
▸BISVERIFY TAX LOT1
05/20/2021320932871Open ↗
▸BISCO OBJ: VERIFY ADDRESS-TOPO STAMP1
06/01/2021320932871Open ↗
▸BISZONING DIAGRAM1
12/17/2015320932871Open ↗
▸BISZONING EXHIBIT I: CERTIFICATION1
04/06/2015320932871Open ↗
▸BISZONING RESOLUTION DETERMINATION1
04/27/2021320932871Open ↗
▸Seals & Professional Certifications24
▸DOB NOWDPL-1: Design Professional Seal & Signature15
09/03/2026B00059143-I1Open ↗
09/03/2026B00059143-P1Open ↗
09/03/2026B00059143-P2Open ↗
Showing 3 of 15 on file for this type
▸DOB NOWProgress Inspector Seal & Signature3
09/01/2026B00406104-I1Open ↗
08/29/2026B00059139-I1Open ↗
08/25/2026B00059143-I1Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT2
03/08/2019340656285Open ↗
12/10/2015321141689Open ↗
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION2
12/05/2018320932871Open ↗
08/24/2017320932871Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY1
03/08/2019340656285Open ↗
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION1
03/08/2019340656285Open ↗
▸Trade Schedules & Equipment21
▸BISSCHEDULE B - PLUMBING9
05/12/2021320932871Open ↗
04/13/2021320932871Open ↗
03/22/2021320932871Open ↗
Showing 3 of 9 on file for this type
▸BISEQUIPMENT USE PERMITS2
06/16/2021320932871Open ↗
05/06/2021340656285Open ↗
▸BISEQUIPMENT USE APPLICATION/PERMIT2
06/16/2021320932871Open ↗
05/06/2021340656285Open ↗
▸BISFIRE ALARM TEST1
05/20/2021320932871Open ↗
▸BISSEWER/HOUSE CON SIGNOFF: DEP HC 0211
09/09/2019320932871Open ↗
▸BISELEVATOR JOB SIGNOFF1
06/01/2021320932871Open ↗
▸BIS* SEWER CONNECTION: DEP SD1 & SD21
12/17/2015320932871Open ↗
▸BISDEP SANITARY SEWER CERTIFICATION (HCP/SCP)1
06/01/2021320932871Open ↗
▸BISFA - FDNY APPROVAL : FD-FAA1
02/23/2021321768903Open ↗
▸BISFIRE ALARM/SIGNAL SYSTEM (FA) SIGNOFF1
05/20/2021320932871Open ↗
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE1
01/11/2016320932871Open ↗
▸Safety & Tenant Protection5
▸BISSTREET TREE CHECKLIST2
12/17/2015320932871Open ↗
04/06/2015320932871Open ↗
▸BISSTREET TREE SUPPORTING DOCUMENT1
08/24/2017320932871Open ↗
▸BISSTREET TREE SIGNOFF1
05/20/2021320932871Open ↗
▸BISEXCAVATION OR DEMOLITION: 5-DAY NOTICE1
08/24/2017320932871Open ↗
▸Energy Compliance13
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY8
06/01/2021320932871Open ↗
06/01/2021320932871Open ↗
05/20/2021320932871Open ↗
Showing 3 of 8 on file for this type
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS1
12/05/2018320932871Open ↗
▸BISAS-BUILT ENERGY ANALYSIS (EN2)1
03/24/2021340656285Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY FOR ENERGY CODE PROGRESS INSPECTIONS1
03/08/2019340656285Open ↗
▸BISNYCECC SUBMIT WINDOW PERFORMANCECERTIFICATE VERIFYING WINDOW ASSEMBLY U-FACTOR OF 0.29 AS SHOWN IN COMCHECK1
08/06/2021320932871Open ↗
▸BISAS-BUILT ENERGY ANALYSIS1
05/20/2021320932871Open ↗
▸Inspections & Test Reports23
▸BISTECHNICAL REPORT: RESPONSIBILITY18
06/02/2021320932871Open ↗
06/01/2021320932871Open ↗
06/01/2021320932871Open ↗
Showing 3 of 18 on file for this type
▸BISTECHNICAL REPORT: CONCRETE/TEST CYLINDER2
08/24/2017320932871Open ↗
07/13/2017320932871Open ↗
▸BISHYDRO FLOW TEST LETTER1
02/08/2016320932871Open ↗
▸BISSOIL REPORT1
12/17/2015320932871Open ↗
▸BISTECHNICAL REPORT: CONCRETE DESIGN MIX1
12/05/2018320932871Open ↗
▸Approvals, Objections & Sign-offs32
▸BISSCHEDULE A - OCCUPANCY / USE18
05/10/2021320932871Open ↗
04/30/2021320932871Open ↗
04/28/2021320932871Open ↗
Showing 3 of 18 on file for this type
▸DOB NOWFee Exempt Supporting Document - DOF ACRIS report or BIB letter6
09/03/2026B00059139-P3Open ↗
09/03/2026B00059139-I1Open ↗
09/03/2026B00059139-P2Open ↗
Showing 3 of 6 on file for this type
▸BISLETTERS - SUPPORTING DOCUMENTATION3
03/08/2021321141689Open ↗
11/11/2014320932871Open ↗
11/11/2014320932871Open ↗
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST2
05/06/2021340656285Open ↗
02/23/2021321768903Open ↗
▸BISADMINISTRATIVE OBJECTIONS1
04/14/2015321103550Open ↗
▸BISMECHANICAL (MH) SIGNOFF1
05/20/2021320932871Open ↗
▸BISCONSTRUCTION CODE DETERMINATION1
01/06/2016320932871Open ↗
▸Cost, Insurance & Ownership8
▸BISCOST AFFIDAVIT4
03/24/2021340656285Open ↗
02/23/2021321768903Open ↗
03/08/2019340656285Open ↗
Showing 3 of 4 on file for this type
▸BISPROJECT-SPECIFIC GL INSURANCE3
05/08/2020320932871Open ↗
03/01/2019320932871Open ↗
08/24/2017320932871Open ↗
▸BISAcord 25 (Acord Certificate of Liability Insurance)1
08/24/2017320932871Open ↗
▸Filing & Intake Forms35
▸BISADDITIONAL INFORMATION26
08/06/2021320932871Open ↗
06/01/2021320932871Open ↗
06/01/2021320932871Open ↗
Showing 3 of 26 on file for this type
▸BISEFILING COVER SHEET7
06/20/2018321768903Open ↗
12/17/2015320932871Open ↗
12/17/2015320932871Open ↗
Showing 3 of 7 on file for this type
▸BISEFILING JOB APPLICATION COVER SHEET1
03/08/2019340656285Open ↗
▸BISBPP: CHECKLIST IN LIEU OF PLANS-ALT31
02/12/2018321141689Open ↗
▸Other Documents9
▸DOB NOWBSA Meeting Minutes/BSA Resolution4
08/13/2026B00059139-P3Open ↗
08/13/2026B00059139-P2Open ↗
08/13/2026B00059139-P1Open ↗
Showing 3 of 4 on file for this type
▸BISCONSTRUCTION - SUPPORTING DOCUMENTATION2
03/11/2016321103550Open ↗
03/11/2016321103550Open ↗
▸BISPLOT DIAGRAM1
06/01/2021320932871Open ↗
▸BISEXTERNAL FORMS - SUPPORTING DOCUMENTATION1
06/02/2017320932871Open ↗
▸DOB NOWAlternate Plan 11