674 WYONA STREET
BROOKLYN · BIN 3096591
💬 Discuss this project
1930Year Built
2Stories
C1Building Class
R6Zoning
3,869 sfGross Floor Area
9Units
Rent Stabilized0 Active ViolationsFDNY Report ↗
Over six families without stores · Owner of record: 674 Wyona Holding · 2,750 sf lot · 1.41 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralMechanicalPlumbingFire ProtectionGeneral
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
RoofZoning analysis and bicycle parking3p · 1 filing · 20 docs
Floor 2Zoning analysis and bicycle parking31p · 1 filing · 20 docs
Floor 1Zoning analysis and bicycle parking30p · 1 filing · 20 docs
CellarZoning analysis and bicycle parking1p · 1 filing · 20 docs
BasementZoning analysis and bicycle parking34p · 1 filing · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
674 Wyona Holding203/22/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
06/10/2024$900K—Private party → 674 WYONA HOLDING LLC$233/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
Adb Associates705/02/2025
Chun Engineering Consultant101/17/2025
Vasilios Artemiou PE105/22/2024
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
NYC Design File903/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
Builders Group USAGeneral Contractor407/08/2026
Power Direct ElectricElectrical103/22/2026
B&B Mechanical Plumbing & HeatingPlumbing107/08/2026
Mpi PlumbingPlumbing107/08/2026
Prime Piping & HeatingFire Protection107/08/2026
Target Piping NYFire Protection107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
HRF Services56161205/02/2025
Shahrish Shuvo Engineering8524101/17/2025
Building Lifecycle
05/06/2026
(a) § hmc:file annual bedbug report in accordance with HPD rule as described on the back of this notice of violation or as described on HPDs…
HPD violation · closed
06/25/2025
Permit expired, never signed off — General Construction
The city's record still shows this permit as issued, with no sign-off on its filing
B01026778-I1-GC
05/15/2025
Signed off — Alteration CO
Filing Structural application subsequent to primary approved job #B01026778-I1
B01026778-S5
05/13/2025
Special inspection requirement — Insulation placement and R values
FAHAD FATEH
05/13/2025
Special inspection requirement — Air barrier - visual inspection
FAHAD FATEH
92 history events on file for this building. Sign in free to see the full history. Sign in · Create account
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWStructuralSigned-offBuilders Group USA05/12/2025
DOB NOWSprinklersSigned-offTarget Piping NY07/24/2024
DOB NOWPlumbingSigned-offTarget Piping NY07/24/2024
DOB NOWSprinklersSigned-offAmb Mechanical07/12/2024
DOB NOWPlumbingSigned-offYG Services07/09/2024
DOB NOWGeneral ConstructionPermit IssuedBuilders Group USA06/25/2024
DOB NOWMechanical SystemsSigned-offBuilders Group USA06/21/2024
1 project · most recent 05/02/2025
Storm Water/Sanitary
FiledStatusContractorScope
05/02/2025Signed-offTarget Piping NYStorm, Water/Sanitary
2 projects · most recent 02/03/2025
General Wiring
FiledStatusContractorScope
02/03/2025CompletePower Direct ElectricGeneral Wiring
07/10/2024CompletePower Direct Electric—
1 project · most recent 05/02/2025
Masonry Wood
FiledStatusContractorScope
05/02/2025Signed-offBuilders Group USAMasonry, Wood
▾Field Inspections (DOB CAP) — 8
DateTypeResultReport
01/21/2025Pass-Final CND-Occupancy InspectionPassView ↗
01/09/2025Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
01/08/2025Pass-Final SP - Up to 3 Requested FloorsPassView ↗
01/02/2025Pass-Final PL - UndergroundPassView ↗
01/01/2025Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
11/13/2024Pass-Final PL - Up to 9 Requested FloorsPassView ↗
11/01/2024No Access-Final PL - Up to 3 Requested FloorsNo AccessView ↗
09/26/2024Pass-Final PL - UndergroundPassView ↗
▾Special Inspection Requirements (DOB NOW) — 70
DateRequirementInspectorRole
05/13/2025Fire-Resistant Penetrations and JointsFAHAD FATEHspecial
05/13/2025Structural Stability – Alterations of existing buildingsFAHAD FATEHspecial
05/13/2025Exterior Insulation and Finish Systems (EIFS)FAHAD FATEHspecial
05/13/2025Energy Code Compliance InspectionsFAHAD FATEHprogress
05/13/2025Fire-Resistance Rated ConstructionFAHAD FATEHprogress
05/13/2025Lighting in dwelling unitsFAHAD FATEHenergy_progress
05/13/2025Permanent certificateFAHAD FATEHenergy_progress
05/13/2025Air barrier - visual inspectionFAHAD FATEHenergy_progress
05/13/2025Fenestration and door U-factor and product ratingsFAHAD FATEHenergy_progress
05/13/2025Fenestration areasFAHAD FATEHenergy_progress
05/13/2025Insulation placement and R valuesFAHAD FATEHenergy_progress
05/13/2025Maintenance informationFAHAD FATEHenergy_progress
05/13/2025MeteringFAHAD FATEHenergy_progress
05/13/2025Fenestration air leakageFAHAD FATEHenergy_progress
01/27/2025Fenestration areasFAHAD FATEHenergy_progress
01/27/2025Exterior Insulation and Finish Systems (EIFS)FAHAD FATEHspecial
01/27/2025Fire-Resistant Penetrations and JointsFAHAD FATEHspecial
01/27/2025Structural Stability – Alterations of existing buildingsFAHAD FATEHspecial
01/27/2025Energy Code Compliance InspectionsFAHAD FATEHprogress
01/27/2025Fire-Resistance Rated ConstructionFAHAD FATEHprogress
01/27/2025MeteringFAHAD FATEHenergy_progress
01/27/2025Air barrier - visual inspectionFAHAD FATEHenergy_progress
01/27/2025Fenestration air leakageFAHAD FATEHenergy_progress
01/27/2025Insulation placement and R valuesFAHAD FATEHenergy_progress
01/27/2025Permanent certificateFAHAD FATEHenergy_progress
Latest 25 of 70.
56 filed documents on file for this building. Sign in free to see the full history. Sign in · Create account