| Owner | Filings | Most Recent |
|---|---|---|
| 676 MANHATTAN REALTY | 4 | 09/01/2026 |
| 676 MANHATTAN AVENUE COMPANY LL | 5 | 03/22/2026 |
| 676 FOOD CORP | 1 | 03/22/2026 |
| 676 MANHATTAN FOOD CROP | 1 | 03/21/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 07/06/2022 | $3.5M | — | — → — | $667/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| TL ENGINEERING, PC | 4 | 03/18/2026 |
| JONG HAE CHANG ARCHITECT | 8 | 12/22/2022 |
| Representative | Filings | Most Recent |
|---|---|---|
| C PLUS DESIGN GROUP | 16 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| IKAHN CONSTRUCTION INC | General Contractor | 3 | 03/21/2026 |
| YOON DUCT INC | General Contractor | 3 | 03/21/2026 |
| XH&RC PLBG AND HTG INC | Plumbing | 2 | 07/08/2026 |
| WILLDAN ELECTRICAL OF NY | Electrical | 1 | 03/22/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| TL ENGINEERING, PC | 1222 | 2 | 03/18/2026 |
| JONG HAE CHANG ARCHITECT | 6169 | 5 | 12/22/2022 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Signed-off | XH&RC PLBG AND HTG INC | 08/09/2023 |
| DOB NOW | General Construction | Signed-off | IKAHN CONSTRUCTION INC | 08/04/2023 |
| DOB NOW | Plumbing | Signed-off | XH&RC PLBG AND HTG INC | 09/16/2022 |
| DOB NOW | Mechanical Systems | Signed-off | YOON DUCT INC | 08/31/2022 |
| BIS | FP | ISSUED | NY FIRE LLC | 10/06/2011 |
| BIS | MH | ISSUED | REMODELING J&D CONSTRUC I | 06/20/2011 |
| BIS | OT | ISSUED | MARCO POLO DESIGN CORP | 06/03/2011 |
| BIS | PL | ISSUED | THE PLUMBING COMPANY INC | 06/03/2011 |
| BIS | OT | ISSUED | EIN CONTRNG CORP | 07/24/2008 |
| BIS | PL | ISSUED | PETER PLUMBING ASSOC. INC. | 07/24/2008 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/18/2022 | Permit Issued | JOSEPH WEINSTEIN ELECTRIC | General Wiring |
| 10/28/2019 | Complete | WILLDAN ELECTRICAL OF NY | — |
| 07/23/2019 | Complete | WILLDAN ELECTRICAL OF NY | — |
| 05/29/2019 | Complete | WILLDAN ELECTRICAL OF NY | General Wiring |
| Date | Type | Result | Report |
|---|---|---|---|
| 03/30/2026 | Pass-Final General Construction Non-Directive 14 | Pass | View ↗ |
| 12/22/2023 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 11/20/2023 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 11/14/2023 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 08/25/2023 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 08/25/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 05/15/2023 | Pass-Final General Construction Non-Directive 14 | Pass | View ↗ |
| 05/11/2023 | Pass-Final General Construction Non-Directive 14 | Pass | View ↗ |
| 11/09/2022 | Fail-Final General Construction Non-Directive 14 | Fail | View ↗ |
| 10/24/2022 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 10/19/2022 | Fail-Final PL - Up to 3 Requested Floors | Fail | View ↗ |
| 09/30/2022 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 09/30/2022 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 09/27/2022 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 03/19/2026 | Fire-Resistant Penetrations and Joints | Simon Lee | special |
| 03/02/2026 | Fire-Resistant Penetrations and Joints | Simon Lee | special |
| 12/22/2022 | Mechanical Systems | Jong Hae Kim | special |
| 12/22/2022 | Fire-Resistant Penetrations and Joints | Jong Hae Kim | special |
| 12/22/2022 | Final | Jong Hae Kim | progress |
| 12/22/2022 | Interior lighting power | Jong Hae Kim | energy_progress |
| 12/22/2022 | Lighting controls | Jong Hae Kim | energy_progress |
| 12/17/2022 | Final | Jong Hae Kim | progress |
| 12/17/2022 | Fire-Resistant Penetrations and Joints | Jong Hae Kim | special |
| 12/17/2022 | Mechanical Systems | Jong Hae Kim | special |
| 12/17/2022 | Lighting controls | Jong Hae Kim | energy_progress |
| 12/17/2022 | Interior lighting power | Jong Hae Kim | energy_progress |
| 12/05/2022 | Mechanical Systems | Jong Hae Kim | special |
| 12/05/2022 | Fire-Resistant Penetrations and Joints | Jong Hae Kim | special |
| 12/05/2022 | Final | Jong Hae Kim | progress |
| 12/05/2022 | Interior lighting power | Jong Hae Kim | energy_progress |
| 12/05/2022 | Lighting controls | Jong Hae Kim | energy_progress |
| 11/30/2022 | Fire-Resistant Penetrations and Joints | Jong Hae Kim | special |
| 11/30/2022 | Lighting controls | Jong Hae Kim | energy_progress |
| 11/30/2022 | Interior lighting power | Jong Hae Kim | energy_progress |
| 11/30/2022 | Final | Jong Hae Kim | progress |
| 11/30/2022 | Mechanical Systems | Jong Hae Kim | special |