← Back
BROOKLYN
676 MYRTLE AVENUE
BROOKLYN · Bedford-Stuyvesant (West) · BIN 3429953
💬 Discuss this project
—Year Built
—Stories
—Building Class
—Zoning
—Gross Floor Area
—Units
Rent StabilizedFDNY Report ↗
Flood zone X
Locations of Work
ArchitectureStructuralMechanicalPlumbingFire Protection
Roof2p · 1 filing · 2 docs
Floor 55p · 1 filing · 20 docs
Floor 45p · 1 filing · 20 docs
Floor 35p · 1 filing · 20 docs
Floor 26p · 1 filing · 20 docs
Floor 18p · 1 filing · 20 docs
Cellar9p · 1 filing · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
WATERMARK3507/08/2026
OWNER'S REP1007/08/2026
OWNERS SOLUTION INC.503/22/2026
676 LLC203/21/2026
▾Design Consultants (Architect / Engineer of Record)
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
BUILDINGS REPRISENTATIVE LLC2003/21/2026
AE DESIGN SOLUTION203/21/2026
WMCM2003/21/2026
THE GREEN STUDIO103/21/2026
MILLENNIUM DESIGNS103/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
WMCM LLCGeneral Contractor1507/08/2026
GWT ENTERPRISES INCGeneral Contractor603/21/2026
MANHATTAN D ENTERPRISESGeneral Contractor407/08/2026
PRIME PIPING & HEATING INFire Protection107/08/2026
PRIME PIPING & HEATING INPlumbing107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
REGIONAL TESTING CORP.3941411/18/2024
SYED ENGINEERING, P.C.7054201/26/2024
Building Lifecycle
All (142)Filed (24)Permit Issued (16)Signed Off (10)Inspection (8)Objection (54)Special Inspection (30)
11/29/2024
Special inspection requirement — Fenestration and door U-factor and product ratings
Paul Raymond
11/29/2024
Special inspection requirement — Vestibules
Paul Raymond
11/29/2024
Special inspection requirement — Air barrier - visual inspection
Paul Raymond
11/29/2024
Special inspection requirement — Lighting in dwelling units
Paul Raymond
11/29/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
Paul Raymond
11/29/2024
Special inspection requirement — Electrical motors and elevators
Paul Raymond
11/29/2024
Special inspection requirement — Lighting controls
Paul Raymond
11/29/2024
Special inspection requirement — Exterior lighting power
Paul Raymond
11/29/2024
Special inspection requirement — Insulation placement and R values
Paul Raymond
11/29/2024
Special inspection requirement — Permanent certificate
Paul Raymond
11/29/2024
Special inspection requirement — Energy Code Compliance Inspections
Paul Raymond
11/29/2024
Special inspection requirement — Exterior Insulation and Finish Systems (EIFS)
Paul Raymond
11/29/2024
Special inspection requirement — Maintenance information
Paul Raymond
11/29/2024
Special inspection requirement — Fire-Resistance Rated Construction
Paul Raymond
11/29/2024
Special inspection requirement — Subgrade Inspections
Paul Raymond
11/29/2024
Special inspection requirement — Wall Panels, Curtain Walls, and Veneers
Paul Raymond
11/29/2024
Special inspection requirement — Metering
Paul Raymond
11/29/2024
Special inspection requirement — Fenestration air leakage
Paul Raymond
11/29/2024
Special inspection requirement — Interior lighting power
Paul Raymond
11/29/2024
Special inspection requirement — Fenestration areas
Paul Raymond
11/18/2024
Filed — New Building
foundation drawings in conjunction with NB filing
B00731678-A5
11/14/2024
Special inspection requirement — Air barrier - visual inspection
Paul Raymond
11/14/2024
Special inspection requirement — Subgrade Inspections
Paul Raymond
11/14/2024
Special inspection requirement — Lighting controls
Paul Raymond
11/14/2024
Special inspection requirement — Fenestration areas
Paul Raymond
11/14/2024
Special inspection requirement — Maintenance information
Paul Raymond
11/14/2024
Special inspection requirement — Interior lighting power
Paul Raymond
11/14/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
Paul Raymond
11/14/2024
Special inspection requirement — Permanent certificate
Paul Raymond
11/14/2024
Special inspection requirement — Fenestration and door U-factor and product ratings
Paul Raymond
11/14/2024
Special inspection requirement — Metering
Paul Raymond
11/06/2024
Signed off — New Building
foundation drawings in conjunction with NB filing
B00731678-S5
08/23/2024
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
07/02/2024
Signed off — Alteration
Installation of a single footing (foundation) in conjunction with NB application B00731678-I1
B00739279-I1
06/30/2024
Signed off — Alteration
B00860699-I1
06/27/2024
Signed off — New Building
foundation drawings in conjunction with NB filing
B00731678-S1
06/27/2024
Signed off — New Building
foundation drawings in conjunction with NB filing
B00731678-S4
06/27/2024
Signed off — New Building
foundation drawings in conjunction with NB filing
B00731678-S2
06/26/2024
Signed off — Alteration
FILLING PAATO SHOWS ANCHORS ON THE ROOF
B00985059-I1
06/04/2024
Signed off — New Building
foundation drawings in conjunction with NB filing
B00731678-S3
05/29/2024
Signed off — New Building
foundation drawings in conjunction with NB filing
B00731678-S6
05/16/2024
Inspection — Certified Storm Drainage-ST-Fixtures-Finish
Certified
View inspection ↗
05/16/2024
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
05/06/2024
Filed — New Building
foundation drawings in conjunction with NB filing
B00731678-A4
04/18/2024
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
04/12/2024
Inspection — Certified Sprinkler-SP-Fixtures-Finish
Certified
View inspection ↗
04/02/2024
Inspection — Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test
Certified
View inspection ↗
03/28/2024
Filed — New Building
foundation drawings in conjunction with NB filing
B00731678-A3
03/28/2024
Signed off — Alteration
INSTALLATION OF 300 PSF SIDEWALK SHED, PIPE SCAFFOLDNG, OVERHEAD PROTECTION, AND ROOF PROTECTION AS PER PLANS. ALL EQUIPMENT SHALL COMPLY WITH CHAPTER #33 OF THE 2022 CODE. NO CHANGE IN USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
B00934456-I1
02/27/2024
Filed — New Building
foundation drawings in conjunction with NB filing
B00731678-A2
01/26/2024
Filed — Alteration
FILLING PAATO SHOWS ANCHORS ON THE ROOF
B00985059-P1
01/18/2024
Permit issued — Suspended Scaffold
B00985059-I1-SC
01/18/2024
Inspection — Pass-Final PL - Up to 9 Requested Floors
Pass
View inspection ↗
01/10/2024
Permit issued — Sidewalk Shed
B00934456-I1-SH
01/08/2024
Permit issued — Sidewalk Shed
B00934456-I1-SF
01/04/2024
Filed — Alteration
FILLING PAATO SHOWS ANCHORS ON THE ROOF
B00985059-I1
12/14/2023
Permit issued — Mechanical Systems
B00731678-S4-MS
12/14/2023
Permit issued — Structural
B00731678-S1-ST
11/22/2023
Inspection — Pass-Final PL - Underground
Pass
View inspection ↗
11/21/2023
Objection resolved — Addressed
Latest 60 of 142 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSuspended ScaffoldSigned-offHARMEL SINGH01/18/2024
DOB NOWSidewalk ShedSigned-offGWT ENTERPRISES INC01/10/2024
DOB NOWSidewalk ShedSigned-offGWT ENTERPRISES INC01/08/2024
DOB NOWMechanical SystemsSigned-offWMCM LLC12/14/2023
DOB NOWStructuralSigned-offWMCM LLC12/14/2023
DOB NOWSidewalk ShedSigned-offMANHATTAN D ENTERPRISES09/21/2023
DOB NOWSidewalk ShedSigned-offMANHATTAN D ENTERPRISES09/21/2023
DOB NOWPlumbingSigned-offPRIME PIPING & HEATING IN09/19/2023
DOB NOWSupport of ExcavationSigned-offWMCM LLC08/17/2023
DOB NOWFoundationSigned-offWMCM LLC08/16/2023
DOB NOWGeneral ConstructionPermit IssuedWMCM LLC07/26/2023
DOB NOWSupport of ExcavationSigned-offWMCM LLC07/11/2023
DOB NOWGeneral ConstructionPermit IssuedWMCM LLC07/05/2023
DOB NOWSprinklersSigned-offA M B MECHANICAL INC06/13/2023
DOB NOWConstruction FenceSigned-offWMCM LLC05/02/2023
DOB NOWFoundationSigned-offWMCM LLC06/08/2022
1 project · most recent 11/18/2024
Heating and Air Conditioning Systems Heating Systems Ventilation Systems
FiledStatusContractorScopeMake / Model / Capacity
11/18/2024Signed-offWMCM LLCHeating and Air Conditioning Systems, Heating Systems, Ventilation Systems
Heat / Cool
Mitsubishi Electric PUMY-P36NKMU3 3 tons · Vrf Outdoor ×42
PUY-A12NKA7 12 tons · Heat Pump Outdoor ×2
Heating
A.O. Smith MUH 03-8 7,168,000 BTU · Electric Heater ×14
Ventilation
Renewaire HE1XRT 640 CFM · Erv ×4
1 project · most recent 11/18/2024
Sprinkler System
FiledStatusContractorScope
11/18/2024Signed-offPRIME PIPING & HEATING INSprinkler System
1 project · most recent 11/18/2024
Storm Water/Sanitary
FiledStatusContractorScope
11/18/2024Signed-offPRIME PIPING & HEATING INStorm, Water/Sanitary
5 projects · most recent 04/11/2024
General Wiring
FiledStatusContractorScope
04/11/2024CompleteHIVOLTS ELECTRICAL INCGeneral Wiring
03/13/2024CompleteTUXEDO ELEC'L CONTR'G INC—
09/13/2023CompleteSOLAS ELECTRICAL CORP—
08/08/2023CompleteHIVOLTS ELECTRICAL INCGeneral Wiring
05/17/2023CompleteHIVOLTS ELECTRICAL INC1 meters, 1 new_meters
1 project · most recent 11/18/2024
Steel Concrete
FiledStatusContractorScope
11/18/2024Signed-offWMCM LLCSteel, Concrete
1 project · most recent 11/18/2024
Support of Excavation
FiledStatusContractorScope
11/18/2024Signed-offWMCM LLCSupport of Excavation
▾Field Inspections (DOB CAP) — 8
DateTypeResultReport
08/23/2024Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
05/16/2024Certified Storm Drainage-ST-Fixtures-FinishCertifiedView ↗
05/16/2024Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
04/18/2024Pass-Final CND-Occupancy InspectionPassView ↗
04/12/2024Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
04/02/2024Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
01/18/2024Pass-Final PL - Up to 9 Requested FloorsPassView ↗
11/22/2023Pass-Final PL - UndergroundPassView ↗
▾Special Inspection Requirements (DOB NOW) — 143
DateRequirementInspectorRole
11/29/2024Fenestration areasPaul Raymondenergy_progress
11/29/2024Electrical motors and elevatorsPaul Raymondenergy_progress
11/29/2024VestibulesPaul Raymondenergy_progress
11/29/2024Insulation placement and R valuesPaul Raymondenergy_progress
11/29/2024Interior lighting powerPaul Raymondenergy_progress
11/29/2024Air barrier - visual inspectionPaul Raymondenergy_progress
11/29/2024Exterior lighting powerPaul Raymondenergy_progress
11/29/2024Fenestration air leakagePaul Raymondenergy_progress
11/29/2024MeteringPaul Raymondenergy_progress
11/29/2024Lighting controlsPaul Raymondenergy_progress
11/29/2024Maintenance informationPaul Raymondenergy_progress
11/29/2024Fenestration and door U-factor and product ratingsPaul Raymondenergy_progress
11/29/2024Lighting in dwelling unitsPaul Raymondenergy_progress
11/29/2024Energy Code Compliance InspectionsPaul Raymondprogress
11/29/2024Fire-Resistance Rated ConstructionPaul Raymondprogress
11/29/2024Fire-Resistant Penetrations and JointsPaul Raymondspecial
11/29/2024Exterior Insulation and Finish Systems (EIFS)Paul Raymondspecial
11/29/2024Wall Panels, Curtain Walls, and VeneersPaul Raymondspecial
11/29/2024Subgrade InspectionsPaul Raymondspecial
11/29/2024Permanent certificatePaul Raymondenergy_progress
11/14/2024Lighting controlsPaul Raymondenergy_progress
11/14/2024Exterior Insulation and Finish Systems (EIFS)Paul Raymondspecial
11/14/2024Fire-Resistant Penetrations and JointsPaul Raymondspecial
11/14/2024Subgrade InspectionsPaul Raymondspecial
11/14/2024Wall Panels, Curtain Walls, and VeneersPaul Raymondspecial
Latest 25 of 143.
▾Documents — 253 on file (BIS + DOB NOW)
▸Plans & Drawings24
▸DOB NOWPlans/Sketch24
08/29/2026B00739279-P1Request digital key ↗
08/29/2026B00739279-I1Request digital key ↗
08/28/2026B00731678-A2Request digital key ↗
Showing 3 of 24 on file for this type
▸Applications & Permits2
▸BISPLAN / WORK APPROVAL APPLICATION2
08/07/2024322117507Open ↗
09/15/2023340860928Open ↗
▸Zoning, Tax Lot & Property Records7
▸DOB NOWZD1: DOB Zoning Diagram3
08/13/2026B00731678-A5Open ↗
08/13/2026B00731678-A3Open ↗
08/13/2026B00731678-I1Open ↗
▸DOB NOWZoning Exhibit form (1-5)3
08/13/2026B00731678-A5Open ↗
08/13/2026B00731678-I1Open ↗
Showing 2 of 3 on file for this type
▸DOB NOWHouse Number Verification: TOPO Stamp1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Seals & Professional Certifications147
▸DOB NOWProgress Inspector Seal & Signature89
09/01/2026B00739279-I1Open ↗
09/01/2026B00739279-I1Open ↗
08/22/2026B00739279-P1Open ↗
Showing 3 of 89 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature34
08/29/2026B00985059-P1Open ↗
08/22/2026B00731678-A5Open ↗
08/22/2026B00731678-S2Open ↗
Showing 3 of 34 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature22
08/29/2026B00739279-I1Open ↗
08/28/2026B00731678-A3Open ↗
08/28/2026B00731678-P5Open ↗
Showing 3 of 22 on file for this type
▸BISAPPLICANT OWNER SIGNATURE1
08/01/2022340860928Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY1
08/01/2022340860928Open ↗
▸Trade Schedules & Equipment3
▸DOB NOWDEP: Sewer Certification (Sanitary/Storm)3
08/13/2026B00731678-A3Open ↗
08/13/2026B00731678-A5Open ↗
Showing 2 of 3 on file for this type
▸Safety & Tenant Protection10
▸DOB NOWStreet Tree Checklist3
08/28/2026B00731678-A3Open ↗
08/28/2026B00731678-I1Open ↗
08/13/2026B00731678-A5Open ↗
▸BISBPP: STREET TREES SITE PLAN1
08/01/2022340860928Open ↗
▸BISSTREET TREE SIGNOFF1
06/10/2024340860928Open ↗
▸BISSTREET TREES: RECEIPT OF STREET TREES SITE PLAN1
12/21/2022340860928Open ↗
▸BISSTREET TREES SITE PLAN1
12/21/2022340860928Open ↗
▸DOB NOWParks Department Acknowledgment Letter for Street Trees Plan1
08/13/2026B00731678-I1Open ↗
▸DOB NOWStreet Trees Site Plan1
08/13/2026B00731678-I1Open ↗
▸DOB NOWStreet Tree Sign Off1
08/13/2026B00731678-I1Open ↗
▸Environmental & Asbestos21
▸DOB NOWOER: Notice to Proceed12
08/13/2026B00731678-A5Open ↗
08/13/2026B00731678-S1Open ↗
08/13/2026B00731678-S5Open ↗
Showing 3 of 12 on file for this type
▸DOB NOWOER: Notice of Satisfaction8
08/13/2026B00731678-S5Open ↗
08/13/2026B00731678-S4Open ↗
08/13/2026B00731678-I1Open ↗
Showing 3 of 8 on file for this type
▸BISENVIRONMENTAL RESTRICTIONS - OER NOTICE OF SATISFACTION1
06/28/2024340860928Open ↗
▸Energy Compliance3
▸DOB NOWPreliminary Commissioning Report Certification2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸DOB NOWEN2: As Built Energy Analysis1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Approvals, Objections & Sign-offs9
▸BISLETTERS - SUPPORTING DOCUMENTATION9
09/25/2024322117507Open ↗
08/09/2024322117507Open ↗
08/09/2024322117507Open ↗
Showing 3 of 9 on file for this type
▸Filing & Intake Forms5
▸BISADDITIONAL INFORMATION2
09/20/2023340860928Open ↗
12/21/2022340860928Open ↗
▸BISEFILING COVER SHEET1
08/07/2024322117507Open ↗
▸BISEFILING JOB APPLICATION COVER SHEET1
07/28/2022340860928Open ↗
▸BISBPP: CHECKLIST IN LIEU OF PLANS-ALT31
07/28/2022340860928Open ↗
▸Other Documents22
▸DOB NOWSite Survey: Initial3
08/13/2026B00731678-A5Open ↗
08/13/2026B00731678-I1Open ↗
Showing 2 of 3 on file for this type
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone3
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 3 on file for this type
▸DOB NOWProperty Ownership Certification3
08/28/2026B00731678-A3Open ↗
08/28/2026B00731678-I1Open ↗
Showing 2 of 3 on file for this type
▸BISBPP - SUPPORTING DOCUMENTATION2
09/20/2023340860928Open ↗
08/01/2022340860928Open ↗
▸DOB NOWManufacturer's Specifications2
08/13/2026B00985059-P1Open ↗
08/13/2026B00985059-I1Open ↗
▸DOB NOWEvaluation of Adjacent Building Report (BC 1817.3)2
08/13/2026B00731678-S2Open ↗
Showing 1 of 2 on file for this type
▸DOB NOWAdjoining Owners Notification2
08/13/2026B00739279-I1Open ↗
08/13/2026B00731678-S3Open ↗
▸DOB NOWCalculations2
08/13/2026B00985059-I1Open ↗
08/13/2026B00985059-P1Open ↗
▸BISPLOT DIAGRAM1
08/09/2024322117507Open ↗
▸BISCONSTRUCTION - SUPPORTING DOCUMENTATION1
12/21/2022340860928Open ↗
▸DOB NOWFinal Survey1
08/13/2026B00731678-I1Open ↗