← Back
Two family brick
68-33 64 PLACE
QUEENS · BIN 4088237
💬 Discuss this project
1920Year Built
2Stories
B1Building Class
R5BZoning
2,248 sfGross Floor Area
2Units
Two family brick · 2,400 sf lot · 0.94 FAR built · Flood zone X
Locations of Work
Plumbing
Floor 11p · 1 filing · 18 docs
Basement1p · 1 filing · 18 docs
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
03/03/2021$950K—Private party → Private party$423/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
STEFANO MORISI R.A.305/13/2025
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
MASON CONSTRUCTION SERVICGeneral Contractor707/08/2026
DPH PLUMBING & HTG CORPPlumbing207/08/2026
KWONG MING ELECTRIC INCElectrical103/22/2026
TRI CITY MECHANICAL GROUP CORPPlumbing107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
DYO DESIGN OFFICE LLC6701305/13/2025
Building Lifecycle
All (29)Filed (3)Permit Issued (6)Inspection (4)Special Inspection (16)
05/15/2025
Special inspection requirement — HVAC-R and service water piping design and insulation
stefano morisi
05/15/2025
Special inspection requirement — HVAC-R and service water heating system controls
stefano morisi
05/15/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
stefano morisi
05/15/2025
Special inspection requirement — Energy Code Compliance Inspections
stefano morisi
05/15/2025
Special inspection requirement — HVAC-R and service water heating equipment
stefano morisi
05/13/2025
Filed — Alteration
Minor alterations to interiors. New ceilings, new non load bearing partitions, new floor finishes.new hvac ductless split system.
Q00630713-P1
05/06/2025
Permit issued — Mechanical Systems
Q00630713-I1-GC-CX
09/03/2024
Permit issued — Plumbing
Q00630713-S1-PL
07/25/2024
Permit issued — Plumbing
Q00630713-S1-PL
07/23/2024
Inspection — Fail-Final PL - Up to 3 Requested Floors
Fail
View inspection ↗
07/15/2024
Inspection — Fail-Final PL - Up to 3 Requested Floors
Fail
View inspection ↗
06/24/2024
Inspection — Fail-Final PL - Up to 3 Requested Floors
Fail
View inspection ↗
03/25/2024
Permit issued — General Construction
Q00630713-I1-GC-CX
02/12/2024
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
01/17/2023
Permit issued — Plumbing
Q00630713-S1-PL
01/09/2023
Filed — Alteration
Minor alterations to interiors. New ceilings, new non load bearing partitions, new floor finishes.new hvac ductless split system.
Q00630713-S1
12/21/2022
Permit issued — General Construction
Q00630713-I1-GC-CX
12/16/2022
Filed — Alteration
Minor alterations to interiors. New ceilings, new non load bearing partitions, new floor finishes.new hvac ductless split system.
Q00630713-I1
12/16/2022
Special inspection requirement — HVAC-R and service water piping design and insulation
stefano morisi
12/16/2022
Special inspection requirement — Fire-Resistant Penetrations and Joints
stefano morisi
12/16/2022
Special inspection requirement — HVAC-R and service water heating system controls
stefano morisi
12/16/2022
Special inspection requirement — Insulation placement and R values
stefano morisi
12/16/2022
Special inspection requirement — Metering
stefano morisi
12/16/2022
Special inspection requirement — Fenestration air leakage
stefano morisi
12/16/2022
Special inspection requirement — Lighting in dwelling units
stefano morisi
12/16/2022
Special inspection requirement — HVAC-R and service water heating equipment
stefano morisi
12/16/2022
Special inspection requirement — Fenestration and door U-factor and product ratings
stefano morisi
11/13/2021
Special inspection requirement — Final
stefano morisi
11/13/2021
Special inspection requirement — Mechanical Systems
stefano morisi
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWMechanical SystemsPermit IssuedMASON CONSTRUCTION SERVIC05/06/2025
DOB NOWPlumbingSigned-offFLAVIO MECHANICAL CORP09/03/2024
DOB NOWPlumbingSigned-offDPH PLUMBING & HTG CORP07/25/2024
DOB NOWGeneral ConstructionPermit IssuedMASON CONSTRUCTION SERVIC03/25/2024
DOB NOWPlumbingSigned-offDPH PLUMBING & HTG CORP01/17/2023
DOB NOWGeneral ConstructionPermit IssuedMASON CONSTRUCTION SERVIC12/21/2022
1 project · most recent 05/13/2025
Air Conditioning Systems Heating Systems
FiledStatusContractorScopeMake / Model / Capacity
05/13/2025Permit IssuedMASON CONSTRUCTION SERVICAir Conditioning Systems, Heating Systems
Cooling
Fujitsu ARU12RLF 12,000 BTU · Fan Coil Indoor ×2
ARU7RLF 7,000 BTU · Vrf Indoor ×2
ARU9RLF 9,000 BTU · Fan Coil Indoor ×2
ASU18RLF 18,000 BTU · Fan Coil Indoor ×2
AOU36RLXFZ 36,000 BTU · Condensing Unit ×1
AOU45RLXFZ 45,000 BTU · Condensing Unit ×1
Heating
Navien NCB-240/130H 130,000 BTU · Boiler ×2
1 project · most recent 05/13/2025
Gas Water/Sanitary
FiledStatusContractorScope
05/13/2025Signed-offTRI CITY MECHANICAL GROUPGas, Water/Sanitary
1 project · most recent 06/07/2023
General Wiring
FiledStatusContractorScope
06/07/2023Permit IssuedKWONG MING ELECTRIC INCGeneral Wiring
▾Field Inspections (DOB CAP) — 4
DateTypeResultReport
07/23/2024Fail-Final PL - Up to 3 Requested FloorsFailView ↗
07/15/2024Fail-Final PL - Up to 3 Requested FloorsFailView ↗
06/24/2024Fail-Final PL - Up to 3 Requested FloorsFailView ↗
02/12/2024Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 16
DateRequirementInspectorRole
05/15/2025HVAC-R and service water piping design and insulationstefano morisienergy_progress
05/15/2025HVAC-R and service water heating system controlsstefano morisienergy_progress
05/15/2025Fire-Resistant Penetrations and Jointsstefano morisispecial
05/15/2025Energy Code Compliance Inspectionsstefano morisiprogress
05/15/2025HVAC-R and service water heating equipmentstefano morisienergy_progress
12/16/2022HVAC-R and service water piping design and insulationstefano morisienergy_progress
12/16/2022Fire-Resistant Penetrations and Jointsstefano morisispecial
12/16/2022HVAC-R and service water heating system controlsstefano morisienergy_progress
12/16/2022Insulation placement and R valuesstefano morisienergy_progress
12/16/2022Meteringstefano morisienergy_progress
12/16/2022Fenestration air leakagestefano morisienergy_progress
12/16/2022Lighting in dwelling unitsstefano morisienergy_progress
12/16/2022HVAC-R and service water heating equipmentstefano morisienergy_progress
12/16/2022Fenestration and door U-factor and product ratingsstefano morisienergy_progress
11/13/2021Finalstefano morisiprogress
11/13/2021Mechanical Systemsstefano morisispecial
▾Documents — 18 on file (BIS + DOB NOW)
▸Plans & Drawings3
▸DOB NOWPlans/Sketch3
08/25/2026Q00630713-S1Request digital key ↗
08/25/2026Q00630713-I1Request digital key ↗
08/25/2026Q00630713-P1Request digital key ↗
▸Seals & Professional Certifications12
▸DOB NOWProgress Inspector Seal & Signature7
08/30/2026Q00630713-S1Open ↗
08/30/2026Q00630713-S1Open ↗
08/29/2026Q00630713-I1Open ↗
Showing 3 of 7 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature3
08/25/2026Q00630713-S1Open ↗
08/25/2026Q00630713-I1Open ↗
08/25/2026Q00630713-P1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature2
08/30/2026Q00630713-S1Open ↗
08/29/2026Q00630713-I1Open ↗
▸Environmental & Asbestos3
▸DOB NOWDEP ACP-5: Asbestos Assessment Report3
08/25/2026Q00630713-S1Open ↗
08/25/2026Q00630713-I1Open ↗
08/25/2026Q00630713-P1Open ↗