Two family frame
68 GALLOWAY AVENUE
STATEN ISLAND · BIN 5028746
💬 Discuss this project
1970Year Built
2Stories
B2Building Class
R3XZoning
2,184 sfGross Floor Area
2Units
Two family frame · 4,510 sf lot · 0.48 FAR built · Flood zone X
Locations of Work
Architecture
Roof1p · 1 filing · 8 docs
Floor 21 filing · 3 docs
Floor 11 filing · 3 docs
Cellar3p · 1 filing · 3 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
BASIC GROUPS CORP503/22/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
TOM PETERSEN ARCHITECT, LLC107/30/2024
KL INNOVATIVE DESIGN INC110/19/2021
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
UniSolar103/21/2026
BASIC GROUPS203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
CENTURION SOLAR ENERGYGeneral Contractor303/21/2026
CUBE BUILDERS GROUP NYGeneral Contractor303/21/2026
BERGER QUALITY ELEC'L CONElectrical103/22/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
THOMAS PETERSEN ARCHITECT7854107/30/2024
KL INNOVATIVE DESIGN INC7225110/19/2021
Building Lifecycle
All (10)Filed (2)Permit Issued (2)Signed Off (1)Special Inspection (5)
10/23/2024
Signed off — Alteration
SCOPE OF WORK IS SOLELY FOR THE INSTALLATION OF THE SOLAR ELECTRONICGENERATING SYSTEM. ALL OTHER WORK IS NOT TO BE RELIED UPON AS BEINGAPPROVED AND/OR PERMITTED BY THE NYC DEPARTMENT OF BUILDINGS.*NO CHANGE TO USE, EGRESS OR OCCUPANCY.*
S01082348-I1
08/14/2024
Permit issued — Solar
S01082348-I1-SL
07/30/2024
Filed — Alteration
SCOPE OF WORK IS SOLELY FOR THE INSTALLATION OF THE SOLAR ELECTRONICGENERATING SYSTEM. ALL OTHER WORK IS NOT TO BE RELIED UPON AS BEINGAPPROVED AND/OR PERMITTED BY THE NYC DEPARTMENT OF BUILDINGS.*NO CHANGE TO USE, EGRESS OR OCCUPANCY.*
S01082348-I1
07/17/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
TOM PETERSEN
07/17/2024
Special inspection requirement — Structural Stability – Alterations of existing buildings
TOM PETERSEN
07/17/2024
Special inspection requirement — Energy Code Compliance Inspections
TOM PETERSEN
07/17/2024
Special inspection requirement — Final
TOM PETERSEN
07/17/2024
Special inspection requirement — Air barrier - visual inspection
TOM PETERSEN
10/22/2021
Permit issued — General Construction
S00611967-I1-GC
10/19/2021
Filed — Alteration
S00611967-I1
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSolarSigned-offCENTURION SOLAR ENERGY08/14/2024
DOB NOWGeneral ConstructionPermit IssuedCUBE BUILDERS GROUP NY10/22/2021
1 project · most recent 07/17/2024
FiledStatusContractorScope
07/17/2024CompleteBERGER QUALITY ELEC'L CON—
▾Special Inspection Requirements (DOB NOW) — 5
DateRequirementInspectorRole
07/17/2024Fire-Resistant Penetrations and JointsTOM PETERSENspecial
07/17/2024Structural Stability – Alterations of existing buildingsTOM PETERSENspecial
07/17/2024Energy Code Compliance InspectionsTOM PETERSENprogress
07/17/2024FinalTOM PETERSENprogress
07/17/2024Air barrier - visual inspectionTOM PETERSENenergy_progress
▾Documents — 11 on file (BIS + DOB NOW)
▸Plans & Drawings2
▸DOB NOWPlans/Sketch2
08/25/2026S00611967-I1Request digital key ↗
08/21/2026S01082348-I1Request digital key ↗
▸Seals & Professional Certifications7
▸DOB NOWProgress Inspector Seal & Signature3
08/30/2026S01082348-I1Open ↗
08/30/2026S01082348-I1Open ↗
08/30/2026S01082348-I1Open ↗
▸DOB NOWDPL-1: Design Professional Seal & Signature2
08/25/2026S00611967-I1Open ↗
08/21/2026S01082348-I1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature2
08/30/2026S01082348-I1Open ↗
08/30/2026S01082348-I1Open ↗
▸Environmental & Asbestos1
▸DOB NOWDEP ACP-5: Asbestos Assessment Report1
08/25/2026S00611967-I1Open ↗
▸Approvals, Objections & Sign-offs1
▸DOB NOWUtility Company Final Acceptance Letter1
08/13/2026S01082348-I1Open ↗