| Firm | Filings | Most Recent |
|---|---|---|
| Azsk Architects | 7 | 08/04/2023 |
| Representative | Filings | Most Recent |
|---|---|---|
| MMSR Consulting Group | 14 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| Tri City Construction | General Contractor | 4 | 07/08/2026 |
| Paramount Plumbing & Heating | Plumbing | 2 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| Buildtech Engineering | 6369 | 2 | 03/09/2023 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Signed-off | Paramount Plumbing & Heating | 03/11/2023 |
| DOB NOW | General Construction | Signed-off | Tri City Construction | 12/01/2022 |
| DOB NOW | Plumbing | Signed-off | Paramount Plumbing & Heating | 04/14/2022 |
| DOB NOW | General Construction | Signed-off | Tri City Construction | 03/10/2022 |
| BIS | PL | ISSUED | Duo Plumbing & Heating | 03/20/2007 |
| BIS | — | ISSUED | JTD Construction | 01/26/2007 |
| BIS | EQ | ISSUED | JTD Construction | 08/14/2006 |
| BIS | — | ISSUED | JTD Construction | 08/14/2006 |
| BIS | — | ISSUED | JTD Construction | 01/10/2006 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/20/2023 | Complete | J.V.C. Electric Service | General Wiring |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 03/16/2023 | Air barrier - visual inspection | Luis Pichardo | energy_progress |
| 03/16/2023 | Structural Stability – Alterations of existing buildings | Luis Pichardo | special |
| 03/16/2023 | Insulation placement and R values | Luis Pichardo | energy_progress |
| 03/16/2023 | Final | NANIK MASSAND | progress |
| 03/09/2023 | Final | — | progress |
| 01/04/2023 | Air barrier - visual inspection | Luis Pichardo | energy_progress |
| 01/04/2023 | Structural Stability – Alterations of existing buildings | Luis Pichardo | special |
| 01/04/2023 | Insulation placement and R values | Luis Pichardo | energy_progress |