| Owner | Filings | Most Recent |
|---|---|---|
| CREATIVE BUILDERS& DEVEL* | 2 | 03/22/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 06/11/2020 | $1.4M | — | Private party → Private party | $413/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| AMR OUDA | 5 | 05/02/2024 |
| ADVANCED ENGINEERING & INSPECT. PLL | 3 | 12/14/2023 |
| FL&M ENGINEERING DESIGN &INSPECTION | 1 | 12/23/2022 |
| KCE CONSULTING ENGINEERING PLLC | 4 | 11/15/2022 |
| ENGINEERING PROFESSIONAL SERVICE P. | 1 | 05/16/2022 |
| Representative | Filings | Most Recent |
|---|---|---|
| AVALON DESIGNS | 24 | 03/21/2026 |
| ISLE CONSULTING | 2 | 03/21/2026 |
| GREEN STUDIO | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| CREATIVE BUILDERS& DEVEL* | General Contractor | 24 | 07/08/2026 |
| MANHATTAN D ENTERPRISES | General Contractor | 6 | 03/21/2026 |
| AMR OUDA | General Contractor | 3 | 03/22/2026 |
| AMR OUDA | Electrical | 2 | 03/21/2026 |
| TARGET PIPING NY LLC | Fire Protection | 1 | 07/08/2026 |
| B&B MECH PLBG & HTG LLC | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| HRF SERVICES CORP | 5616 | 11 | 05/02/2024 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Curb Cut | Signed-off | CREATIVE BUILDERS& DEVEL* | 11/15/2023 |
| DOB NOW | Mechanical Systems | Signed-off | CREATIVE BUILDERS& DEVEL* | 09/01/2023 |
| DOB NOW | Construction Fence | Signed-off | CREATIVE BUILDERS& DEVEL* | 08/24/2023 |
| DOB NOW | General Construction | Permit Issued | CREATIVE BUILDERS& DEVEL* | 06/10/2023 |
| DOB NOW | Plumbing | Signed-off | TARGET PIPING NY LLC | 05/03/2023 |
| DOB NOW | Plumbing | Signed-off | TARGET PIPING NY LLC | 03/28/2023 |
| DOB NOW | Sidewalk Shed | Signed-off | MANHATTAN D ENTERPRISES | 12/26/2022 |
| DOB NOW | Supported Scaffold | Signed-off | MANHATTAN D ENTERPRISES | 12/26/2022 |
| DOB NOW | General Construction | Permit Issued | CREATIVE BUILDERS& DEVEL* | 11/18/2022 |
| DOB NOW | Support of Excavation | Signed-off | CREATIVE BUILDERS& DEVEL* | 09/13/2022 |
| DOB NOW | General Construction | Permit Issued | CREATIVE BUILDERS& DEVEL* | 09/09/2022 |
| DOB NOW | General Construction | Signed-off | CREATIVE BUILDERS& DEVEL* | 09/09/2022 |
| DOB NOW | Construction Fence | Signed-off | CREATIVE BUILDERS& DEVEL* | 09/06/2022 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 05/02/2024 | Signed-off | CREATIVE BUILDERS& DEVEL* | Air Conditioning Systems, Heating Systems | Cooling Mitsubishi Electric MXZ-SM36NAM 36,000 BTU · Heat Pump Outdoor ×2 MXZ-SM48NAM 60,000 BTU · Heat Pump Outdoor ×1 Heating Mitsubishi Electric MXZ-SM48NAM 66,000 BTU · Heat Pump Outdoor ×3 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/02/2024 | Signed-off | TARGET PIPING NY LLC | Sprinkler System |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/02/2024 | Signed-off | B&B MECH PLBG & HTG LLC | Gas, Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/25/2023 | Complete | HIGH STANDARD ELECTRIC | General Wiring |
| 12/06/2022 | Complete | HIGH STANDARD ELECTRIC | — |
| 12/01/2022 | Complete | HIGH STANDARD ELECTRIC | 3 meters, 3 new_meters |
| 11/19/2022 | Complete | SOLAS ELECTRICAL CORP | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/02/2024 | Signed-off | CREATIVE BUILDERS& DEVEL* | Steel |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/02/2024 | Signed-off | CREATIVE BUILDERS& DEVEL* | Fence |
| Date | Type | Result | Report |
|---|---|---|---|
| 05/13/2024 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 05/08/2024 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 05/07/2024 | Pass-Final Curb Cut Non-Directive 14 | Pass | View ↗ |
| 04/17/2024 | Fail-Final CND-Occupancy Inspection | Fail | View ↗ |
| 04/17/2024 | Fail-Final Curb Cut Non-Directive 14 | Fail | View ↗ |
| 01/09/2024 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 01/08/2024 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 01/08/2024 | Pass-Final PL - Up to 9 Requested Floors | Pass | View ↗ |
| 01/02/2024 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 11/09/2023 | Pass-Final PL - Underground | Pass | View ↗ |
| 06/15/2023 | Pass-Final PL - Up to 9 Requested Floors | Pass | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 05/01/2024 | Protection of exposed foundation insulation | FAHAD FATEH | energy_progress |
| 05/01/2024 | Fenestration air leakage | FAHAD FATEH | energy_progress |
| 05/01/2024 | Air barrier - visual inspection | FAHAD FATEH | energy_progress |
| 05/01/2024 | Lighting in dwelling units | FAHAD FATEH | energy_progress |
| 05/01/2024 | Fenestration areas | FAHAD FATEH | energy_progress |
| 05/01/2024 | Metering | FAHAD FATEH | energy_progress |
| 05/01/2024 | Maintenance information | FAHAD FATEH | energy_progress |
| 05/01/2024 | Interior lighting power | FAHAD FATEH | energy_progress |
| 05/01/2024 | Lighting controls | FAHAD FATEH | energy_progress |
| 05/01/2024 | Exterior lighting power | FAHAD FATEH | energy_progress |
| 05/01/2024 | Fire-Resistant Penetrations and Joints | FAHAD FATEH | special |
| 05/01/2024 | Subgrade Inspections | FAHAD FATEH | special |
| 05/01/2024 | Energy Code Compliance Inspections | FAHAD FATEH | progress |
| 05/01/2024 | Fire-Resistance Rated Construction | FAHAD FATEH | progress |
| 05/01/2024 | Fenestration and door U-factor and product ratings | FAHAD FATEH | energy_progress |
| 05/01/2024 | Insulation placement and R values | FAHAD FATEH | energy_progress |
| 02/15/2024 | Energy Code Compliance Inspections | FAHAD FATEH | progress |
| 02/15/2024 | Fire-Resistant Penetrations and Joints | FAHAD FATEH | special |
| 02/15/2024 | Subgrade Inspections | FAHAD FATEH | special |
| 02/15/2024 | Fire-Resistance Rated Construction | FAHAD FATEH | progress |
| 02/15/2024 | Maintenance information | FAHAD FATEH | energy_progress |
| 02/15/2024 | Interior lighting power | FAHAD FATEH | energy_progress |
| 02/15/2024 | Fenestration and door U-factor and product ratings | FAHAD FATEH | energy_progress |
| 02/15/2024 | Air barrier - visual inspection | FAHAD FATEH | energy_progress |
| 02/15/2024 | Metering | FAHAD FATEH | energy_progress |