| Owner | Filings | Most Recent |
|---|---|---|
| COLLIERS | 7 | 08/16/2026 |
| COLLIERS INTERNATONAL | 7 | 07/10/2026 |
| BSD 685 NEW YORK PROPCO | 8 | 07/08/2026 |
| 681 FIFTH AVENUE | 233 | 03/22/2026 |
| 681 5 AVE LIC | 1 | 03/22/2026 |
| JT MEGEN & COMP INC 11TH | 1 | 03/22/2026 |
| FORTUNOFF | 11 | 03/22/2026 |
| AZTEC RESTORATION SERVICE | 3 | 03/22/2026 |
| 681 5TH AVE | 6 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| SCOTT MICHAEL STAPLETON, ARCH., PC | 3 | 02/05/2026 |
| O&S ASSOCIATES | 1 | 05/08/2025 |
| SURFACE DESIGN | 2 | 03/14/2025 |
| FL&M ENGINEERING DESIGN &INSPECTION | 1 | 11/15/2024 |
| PATUXENT ENGINEERING LLC | 2 | 08/24/2023 |
| 360 ENGINEERING P.C. | 2 | 07/20/2022 |
| AMA CONSULTING ENGINEERS, PC | 4 | 05/17/2021 |
| S.M. BERGER ARCHITECTURE PC | 1 | 05/22/2019 |
| JOEL PHAGOO P.E. PLLC | 1 | 07/23/2018 |
| Representative | Filings | Most Recent |
|---|---|---|
| ORION PLUMBING HEATING | 6 | 03/21/2026 |
| SYNERGY BUILDING CONSULTANTS | 1 | 03/21/2026 |
| PATUXENT ENGINEERING | 4 | 03/21/2026 |
| JAM CONSULTANTS, INC. | 10 | 03/21/2026 |
| MUNICIPAL BUILDING CONSULTANTS | 2 | 03/21/2026 |
| O S ASSOCIATES | 2 | 03/21/2026 |
| SPRING SCAFFOLDING LLC | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| SPIRE SCAFFOLDING & HOIST | General Contractor | 12 | 07/08/2026 |
| URBAN INTELLIGENCE, INC | General Contractor | 6 | 08/16/2026 |
| GANNON CONTRACTING LLC | General Contractor | 4 | 07/08/2026 |
| GS CONSTRUCTION GROUP INC | General Contractor | 3 | 06/27/2026 |
| TRIBUTE RESTORATION INC | General Contractor | 2 | 03/21/2026 |
| MC SUPERSTRUCTURE INC | General Contractor | 1 | 07/08/2026 |
| SPRING SCAFFOLDING LLC | General Contractor | 1 | 07/08/2026 |
| DIMOS PAPADIMAS | Electrical | 1 | 03/21/2026 |
| PREFERRED MECHANICAL INC | Plumbing | 1 | 07/08/2026 |
| FLINT MECHANICAL CORP | Fire Protection | 1 | 07/08/2026 |
| PAR FIRE PROTECTION LLC | Fire Protection | 1 | 07/08/2026 |
| ARGENTO GENERAL CONSTRUC* | General Contractor | 1 | 04/09/2026 |
| EXTERIOR WALL & BUILDING | General Contractor | 1 | 04/09/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| CONCESSI ENGINEERING, P.C | 540 | 1 | 02/05/2026 |
| SPACE ARCHITECTURE | 8347 | 2 | 01/09/2026 |
| KZ ENGINEERING, P.C. | 4665 | 1 | 07/15/2025 |
| O&S ASSOCIATES, INC. | 8393 | 1 | 05/08/2025 |
| SURFACE DESIGN PROFESSION | 3968 | 2 | 03/14/2025 |
| 360 ENGINEERING P.C. | 7496 | 1 | 07/20/2022 |
| ALAN MARGOLIN & ASSOC | 423 | 3 | 05/17/2021 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Sidewalk Shed | Permit Issued | URBAN INTELLIGENCE, INC | 08/14/2026 |
| DOB NOW | Suspended Scaffold | Permit Issued | GS CONSTRUCTION GROUP INC | 07/09/2026 |
| DOB NOW | General Construction | Permit Issued | GS CONSTRUCTION GROUP INC | 06/23/2026 |
| DOB NOW | Sidewalk Shed | Permit Issued | URBAN INTELLIGENCE, INC | 05/20/2026 |
| DOB NOW | Sprinklers | Signed-off | BLETSAS P&H CORP | 03/23/2026 |
| DOB NOW | General Construction | Signed-off | ARGENTO GENERAL CONSTRUC* | 01/07/2026 |
| DOB NOW | Sidewalk Shed | Permit Issued | EXTERIOR WALL & BUILDING | 12/08/2025 |
| DOB NOW | Suspended Scaffold | Permit Issued | GS CONSTRUCTION GROUP INC | 07/17/2025 |
| DOB NOW | General Construction | Permit Issued | GS CONSTRUCTION GROUP INC | 06/17/2025 |
| DOB NOW | Sidewalk Shed | Permit Issued | MC SUPERSTRUCTURE INC | 11/19/2024 |
| DOB NOW | Supported Scaffold | Signed-off | SPIRE SCAFFOLDING & HOIST | 06/14/2024 |
| DOB NOW | Sidewalk Shed | Signed-off | URBAN INTELLIGENCE, INC | 01/10/2024 |
| DOB NOW | Sidewalk Shed | Signed-off | URBAN INTELLIGENCE, INC | 08/14/2023 |
| DOB NOW | Supported Scaffold | Signed-off | SPIRE SCAFFOLDING & HOIST | 05/04/2023 |
| DOB NOW | Sidewalk Shed | Signed-off | SPIRE SCAFFOLDING & HOIST | 05/04/2023 |
| DOB NOW | Supported Scaffold | Signed-off | SPIRE SCAFFOLDING & HOIST | 05/04/2023 |
| DOB NOW | Sidewalk Shed | Signed-off | SPIRE SCAFFOLDING & HOIST | 04/18/2023 |
| DOB NOW | General Construction | Signed-off | TRIBUTE RESTORATION INC | 10/12/2022 |
| DOB NOW | Supported Scaffold | Signed-off | SPIRE SCAFFOLDING & HOIST | 07/20/2022 |
| DOB NOW | Sidewalk Shed | Signed-off | SPIRE SCAFFOLDING & HOIST | 04/29/2022 |
| DOB NOW | Sidewalk Shed | Signed-off | SPIRE SCAFFOLDING & HOIST | 08/26/2021 |
| DOB NOW | Mechanical Systems | Signed-off | GANNON CONTRACTING LLC | 03/07/2021 |
| DOB NOW | Mechanical Systems | Signed-off | GANNON CONTRACTING LLC | 02/16/2021 |
| DOB NOW | Sprinklers | Signed-off | LAWRENCE J. LEVINE | 12/17/2020 |
| DOB NOW | Mechanical Systems | Signed-off | GANNON CONTRACTING LLC | 12/17/2020 |
| DOB NOW | Plumbing | Signed-off | PREFERRED MECHANICAL INC | 12/17/2020 |
| DOB NOW | Supported Scaffold | Signed-off | SPRING SCAFFOLDING LLC | 07/23/2018 |
| BIS | OT | ISSUED | GANNON CONTRACTING LLC | 02/10/2021 |
| BIS | OT | ISSUED | GANNON CONTRACTING LLC | 12/11/2020 |
| BIS | SP | ISSUED | ACCURATE MECHANICAL INC | 11/13/2020 |
| BIS | OT | ISSUED | TRI-STAR CONSTRUCTION CORP | 10/22/2020 |
| BIS | MH | ISSUED | TRI-STAR CONSTRUCTION CORP | 04/01/2020 |
| BIS | OT | ISSUED | TRI-STAR CONSTRUCTION CORP | 03/31/2020 |
| BIS | MH | ISSUED | TRI-STAR CONSTRUCTION CORP | 03/27/2019 |
| BIS | OT | ISSUED | TRI-STAR CONSTRUCTION CORP | 03/27/2019 |
| BIS | OT | ISSUED | TRI-STAR CONSTRUCTION CORP | 03/27/2019 |
| BIS | PL | ISSUED | ACCURATE MECHANICAL INC | 01/29/2019 |
| BIS | SP | ISSUED | ACCURATE MECHANICAL INC | 10/17/2018 |
| BIS | MH | ISSUED | TRI-STAR CONSTRUCTION CORP | 04/06/2018 |
| BIS | OT | ISSUED | TRI-STAR CONSTRUCTION CORP | 04/06/2018 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 11/12/2025 | Permit Issued | VERTEX ELECTRIC CORP. | General Wiring |
| 12/26/2024 | Permit Issued | 5 J'S ELECTL CONTS CORP | — |
| 08/14/2023 | Complete | 5 J'S ELECTL CONTS CORP | — |
| 09/15/2022 | Complete | NASH ELECTRIC SERVICES IN | — |
| 12/15/2020 | Complete | COMMERCIAL ELECT CONT INC | General Wiring |
| 03/25/2019 | Complete | MATROS AUTOMATED ELEC'L C | General Wiring |
| 02/08/2018 | Complete | R.C.M. ELECTRIC CORP. | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/08/2025 | Permit Issued | GS CONSTRUCTION GROUP INC | 1 scope_items |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/15/2025 | Permit Issued | GS CONSTRUCTION GROUP INC | Suspended Scaffold (SC) |
| Date | Type | Result | Report |
|---|---|---|---|
| 08/10/2026 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 08/10/2026 | Certified Sprinkler - SP - Roughing | Certified | View ↗ |
| 07/20/2026 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 06/04/2026 | Fail-Final CND-Occupancy Inspection | Fail | View ↗ |
| 04/02/2026 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 03/30/2026 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 12/19/2025 | Fail-Final Construction Permit Withdrawal | Fail | View ↗ |
| 10/20/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 08/20/2024 | Pass-Final PL - Up to 9 Requested Floors | Pass | View ↗ |
| 06/27/2024 | Pass-Final PL - Underground | Pass | View ↗ |
| 12/28/2023 | Fail-Final PL - Up to 3 Requested Floors | Fail | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 02/04/2026 | Sprinkler Systems | Robert Concessi | special |
| 01/20/2026 | Lighting controls | Scott Stapleton | energy_progress |
| 01/20/2026 | Interior lighting power | Scott Stapleton | energy_progress |
| 01/20/2026 | Lighting in dwelling units | Scott Stapleton | energy_progress |
| 01/20/2026 | Fire-Resistant Penetrations and Joints | Scott Stapleton | special |
| 01/20/2026 | Final | Scott Stapleton | progress |
| 01/08/2026 | Fire-Resistant Penetrations and Joints | Scott Stapleton | special |
| 01/08/2026 | Interior lighting power | Scott Stapleton | energy_progress |
| 01/08/2026 | Lighting controls | Scott Stapleton | energy_progress |
| 01/08/2026 | Lighting in dwelling units | Scott Stapleton | energy_progress |
| 01/08/2026 | Final | Scott Stapleton | progress |
| 07/10/2025 | Alternative Materials - OTCR Buildings Bulletin Number | Karol Zdancewicz | special |
| 07/10/2025 | Post-installed Anchors | Karol Zdancewicz | special |
| 04/28/2025 | Masonry | Prabhu Perumalsamy | special |
| 04/28/2025 | Structural Steel - Welding | Prabhu Perumalsamy | special |
| 04/25/2025 | Final | Prabhu Perumalsamy | progress |
| 04/25/2025 | Structural Stability – Alterations of existing buildings | Prabhu Perumalsamy | special |
| 03/20/2025 | Masonry | MOLLY FORR | special |
| 03/20/2025 | Post-installed Anchors | MOLLY FORR | special |
| 03/20/2025 | Final | Benson Gillespie | progress |
| 03/20/2025 | Air barrier - visual inspection | Benson Gillespie | energy_progress |
| 11/14/2023 | Air barrier - visual inspection | Benson Gillespie | energy_progress |
| 11/14/2023 | Final | Benson Gillespie | progress |
| 11/14/2023 | Post-installed Anchors | MOLLY FORR | special |
| 11/14/2023 | Masonry | MOLLY FORR | special |
| Tenant | Space | Floors | Renovation projects |
|---|---|---|---|
| Propercloth | Retail | Floor 6 | Project M00341200 |