| Owner | Filings | Most Recent |
|---|---|---|
| TOPLINE NYC CONTRACTING | 3 | 07/08/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| ASR ENGINEERING PC | 1 | 08/29/2022 |
| TL ENGINEERING, PC | 2 | 02/05/2020 |
| Representative | Filings | Most Recent |
|---|---|---|
| ADVANCED BUILDERS SERVICES | 1 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| MGM CONSTRUCTION NY INC | General Contractor | 4 | 03/22/2026 |
| L&J PLG & HTG CO OF NY IN | Plumbing | 4 | 07/08/2026 |
| RICHARD NEU | Electrical | 1 | 03/21/2026 |
| SERGIO GIANNACHI | Electrical | 1 | 03/21/2026 |
| LELIS, ARILSON | Electrical | 1 | 03/21/2026 |
| TOPLINE NYC CONTRACTING | General Contractor | 1 | 07/08/2026 |
| YOUNG CHOE | Electrical | 1 | 03/21/2026 |
| NEU, RICHARD | Electrical | 1 | 03/21/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| TL ENGINEERING, PC | 1222 | 2 | 02/05/2020 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Sidewalk Shed | Permit Issued | TOPLINE NYC CONTRACTING | 08/29/2022 |
| DOB NOW | Mechanical Systems | Permit Issued | MGM CONSTRUCTION NY INC | 07/07/2020 |
| DOB NOW | Plumbing | Signed-off | L&J PLG & HTG CO OF NY IN | 02/14/2020 |
| BIS | OT | ISSUED | MGM CONSTRUCTION NY INC | 01/29/2020 |
| BIS | FP | ISSUED | MEGA FIRE PROTECTION INC | 02/06/2001 |
| BIS | FP | ISSUED | IDEAL FIRE CONTROL INC | 11/29/1999 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/07/2022 | Permit Issued | RICHARD NEU | — |
| 02/11/2020 | Complete | Y.S ELECTRIC | General Wiring, Lighting |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/29/2022 | Permit Issued | TOPLINE NYC CONTRACTING | Sidewalk Shed |
| Date | Type | Result | Report |
|---|---|---|---|
| 02/05/2024 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |