← Back
Primarily 2 family with 1 store or office
687 6 AVENUE
BROOKLYN · BIN 3017183
💬 Discuss this project
1899Year Built
3Stories
S2Building Class
R6BZoning
2,000 sfGross Floor Area
3Units
0 Open ViolationsFDNY Report ↗
Primarily 2 family with 1 store or office · Owner of record: TLM 687 LLC · 1,200 sf lot · 1.67 FAR built · Flood zone X
Locations of Work
ArchitectureElectricalMechanicalPlumbing
Floor 14p · 1 filing · 20 docs
Cellar4p · 1 filing · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
TLM 6871607/08/2026
687 6TH AVENUE703/21/2026
LOT 2103/21/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
LCW ENGINEERING, P.C.504/29/2024
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
H-BUILDER INCGeneral Contractor303/21/2026
MPS PLUMBING & HEATING INCPlumbing207/08/2026
BENJAMIN DREBINElectrical103/21/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
LCW ENGINEERING, PC1103404/29/2024
Building Lifecycle
All (33)Filed (5)Permit Issued (3)Signed Off (3)Violation (1)Inspection (5)Special Inspection (16)
11/21/2025
Violation issued (FDNY_ORDER, closed)
06/04/2024
Signed off — Alteration
Subsequent filing to submit boiler work type for installing (2) residential boilers in the cellar boiler room. No change the use, egress or occupancy.
B00944982-S2
05/24/2024
Signed off — Alteration
Subsequent filing to submit boiler work type for installing (2) residential boilers in the cellar boiler room. No change the use, egress or occupancy.
B00944982-S1
05/23/2024
Signed off — Alteration
Subsequent filing to submit boiler work type for installing (2) residential boilers in the cellar boiler room. No change the use, egress or occupancy.
B00944982-I1
05/16/2024
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
05/06/2024
Inspection — Pass-Final General Construction Non-Directive 14
Pass
View inspection ↗
04/30/2024
Special inspection requirement — Final
luis wong
04/30/2024
Special inspection requirement — Energy Code Compliance Inspections
luis wong
04/30/2024
Special inspection requirement — Tenant Protection Plan Compliance
luis wong
04/30/2024
Special inspection requirement — Mechanical Systems
luis wong
04/30/2024
Special inspection requirement — HVAC-R and service water piping design and insulation
luis wong
04/30/2024
Special inspection requirement — HVAC-R and service water heating equipment
luis wong
04/29/2024
Filed — Alteration
Subsequent filing to submit boiler work type for installing (2) residential boilers in the cellar boiler room. No change the use, egress or occupancy.
B00944982-P2
03/05/2024
Inspection — Pass-Final Boiler Equipment Inspection
Pass
View inspection ↗
03/05/2024
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
02/27/2024
Permit issued — Boiler Equipment
B00944982-S1-BE
01/31/2024
Filed — Alteration
Subsequent filing to submit boiler work type for installing (2) residential boilers in the cellar boiler room. No change the use, egress or occupancy.
B00944982-S1
01/29/2024
Special inspection requirement — Tenant Protection Plan Compliance
luis wong
01/29/2024
Special inspection requirement — Energy Code Compliance Inspections
luis wong
01/29/2024
Special inspection requirement — HVAC-R and service water piping design and insulation
luis wong
01/29/2024
Special inspection requirement — HVAC-R and service water heating equipment
luis wong
01/26/2024
Filed — Alteration
Subsequent filing to submit boiler work type for installing (2) residential boilers in the cellar boiler room. No change the use, egress or occupancy.
B00944982-P1
01/24/2024
Special inspection requirement — HVAC-R and service water piping design and insulation
luis wong
01/24/2024
Special inspection requirement — HVAC-R and service water heating equipment
luis wong
01/24/2024
Special inspection requirement — Energy Code Compliance Inspections
luis wong
01/24/2024
Special inspection requirement — Tenant Protection Plan Compliance
01/17/2024
Inspection — Certified Remove/Cap - work done in accordance with code
Certified
View inspection ↗
11/22/2023
Permit issued — General Construction
B00944982-S2-GC-CX
11/15/2023
Filed — Alteration
Subsequent filing to submit boiler work type for installing (2) residential boilers in the cellar boiler room. No change the use, egress or occupancy.
B00944982-S2
10/24/2023
Permit issued — Plumbing
B00944982-I1-PL
10/10/2023
Filed — Alteration
Subsequent filing to submit boiler work type for installing (2) residential boilers in the cellar boiler room. No change the use, egress or occupancy.
B00944982-I1
10/09/2023
Special inspection requirement — Tenant Protection Plan Compliance
luis wong
10/09/2023
Special inspection requirement — Heating Systems
luis wong
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWBoiler EquipmentSigned-offMPS PLUMBING & HEATING IN02/27/2024
DOB NOWGeneral ConstructionSigned-offH-BUILDER INC11/22/2023
DOB NOWPlumbingSigned-offMPS PLUMBING & HEATING IN10/24/2023
BISFPISSUEDNY FIRE LLC06/09/2011
BISPLISSUEDPETER MICELI PLUMBING02/27/2006
BISFPISSUEDNEW YORK BUSINESS FIRE SYSTEM02/09/2006
BISPLISSUEDPETER MICELI PLUMBING11/01/2005
Nothing on file for this building.
▾Field Inspections (DOB CAP) — 5
DateTypeResultReport
05/16/2024Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
05/06/2024Pass-Final General Construction Non-Directive 14PassView ↗
03/05/2024Pass-Final Boiler Equipment InspectionPassView ↗
03/05/2024Pass-Final PL - Up to 3 Requested FloorsPassView ↗
01/17/2024Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 16
DateRequirementInspectorRole
04/30/2024Finalluis wongprogress
04/30/2024Energy Code Compliance Inspectionsluis wongprogress
04/30/2024Tenant Protection Plan Complianceluis wongspecial
04/30/2024Mechanical Systemsluis wongspecial
04/30/2024HVAC-R and service water piping design and insulationluis wongenergy_progress
04/30/2024HVAC-R and service water heating equipmentluis wongenergy_progress
01/29/2024Tenant Protection Plan Complianceluis wongspecial
01/29/2024Energy Code Compliance Inspectionsluis wongprogress
01/29/2024HVAC-R and service water piping design and insulationluis wongenergy_progress
01/29/2024HVAC-R and service water heating equipmentluis wongenergy_progress
01/24/2024HVAC-R and service water piping design and insulationluis wongenergy_progress
01/24/2024HVAC-R and service water heating equipmentluis wongenergy_progress
01/24/2024Energy Code Compliance Inspectionsluis wongprogress
01/24/2024Tenant Protection Plan Compliance—special
10/09/2023Tenant Protection Plan Complianceluis wongspecial
10/09/2023Heating Systemsluis wongspecial
▾Documents — 38 on file (BIS + DOB NOW)
▸Plans & Drawings5
▸DOB NOWPlans/Sketch5
08/26/2026B00944982-P2Request digital key ↗
08/26/2026B00944982-S2Request digital key ↗
08/26/2026B00944982-I1Request digital key ↗
Showing 3 of 5 on file for this type
▸Applications & Permits2
▸BISWORK PERMIT APPLICATION1
06/10/2011320317304Open ↗
▸BISPLAN / WORK APPROVAL APPLICATION1
06/09/2011320317304Open ↗
▸Seals & Professional Certifications20
▸DOB NOWProgress Inspector Seal & Signature10
08/27/2026B00944982-S2Open ↗
08/27/2026B00944982-S2Open ↗
08/27/2026B00944982-S2Open ↗
Showing 3 of 10 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature5
08/26/2026B00944982-S2Open ↗
08/26/2026B00944982-I1Open ↗
08/13/2026B00944982-P1Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature5
09/23/2026B00944982-S1Open ↗
09/23/2026B00944982-S1Open ↗
08/27/2026B00944982-S2Open ↗
Showing 3 of 5 on file for this type
▸Environmental & Asbestos5
▸DOB NOWDEP ACP-5: Asbestos Assessment Report5
08/26/2026B00944982-S2Open ↗
08/26/2026B00944982-I1Open ↗
08/13/2026B00944982-S1Open ↗
Showing 3 of 5 on file for this type
▸Approvals, Objections & Sign-offs2
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST1
11/02/2011320317304Open ↗
▸BISADMINISTRATIVE OBJECTIONS1
06/09/2011320317304Open ↗
▸Cost, Insurance & Ownership2
▸BISCOST AFFIDAVIT2
11/02/2011320317304Open ↗
06/09/2011320317304Open ↗
▸Filing & Intake Forms1
▸BISEFILING COVER SHEET1
06/09/2011320317304Open ↗
▸Other Documents1
▸BISFIRE SUPP ANSUL APPROVL- FD-FSS1
11/02/2011320317304Open ↗