← Back
Elevator apt, semi-fireproof with stores
Triumph Real Estate
69-01 NORTHERN BOULEVARD · Jackson Heights · BIN 4026292
💬 Discuss this project
1962Year Built
6Stories
D7Building Class
R4Zoning
79,338 sfGross Floor Area
84Units
LL97 CoveredRent Stabilized2 Open Violations ▸FISP: SAFE
Elevator apt, semi-fireproof with stores · Owner of record: 69-70 ASSOCIATES LLC · 21,000 sf lot · 3.78 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralPlumbingGeneral
Roof2p · 3 filings · 20 docs
Bulkhead1p · 1 filing · 20 docs
Floor 11p · 1 filing · 20 docs
Cellar1p · 1 filing · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
69-70 ASSOCIATES8507/08/2026
J N H CONSTRUCTION607/08/2026
69-70 ASSOCIATES,LLC TRIU503/22/2026
69-70 ASSO. LLC103/22/2026
PIONEER GENERAL CONSTR.CO103/22/2026
69-70 ASSOCI403/21/2026
UK2 CONSTRUCTION203/21/2026
6903 NORTHERN303/21/2026
60-70_ASSOCIATES203/21/2026
ICON REALTY103/21/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
M.B.MANSOURI, ARCHITECT, P.C.706/21/2023
PACE ENGINEERING P.C.104/13/2022
ASHRAF CORP102/28/2022
COM-EX ENGINEERING OF NY, PLLC101/19/2021
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
DANICO SERVICES203/21/2026
CCM CONSULTING GROUP, INC.103/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
J.N.H. CONSTRUCTION CORPGeneral Contractor407/08/2026
UNIQUE FIRE SYSTEMS INCGeneral Contractor203/21/2026
JOHN FITZGERALD PLBG &HTGPlumbing207/08/2026
AGL DEVELOPMENT LLCGeneral Contractor107/08/2026
C.T.C. ELEC'L CONTRS INCElectrical103/22/2026
JJK BUILDING CONSULTINGGeneral Contractor107/08/2026
IRVING BAPTISTEElectrical103/21/2026
TIMOTHY COLEMANElectrical103/21/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
MB MANSOURI ARCHITECT PC8573706/21/2023
PACE ENGINEERING P.C.1679104/13/2022
Building Lifecycle
All (115)Filed (10)Permit Issued (7)Signed Off (2)Facade (FISP) (18)Violation (60)Inspection (4)Special Inspection (14)
02/11/2026
Cycle 10 facade report signed — SAFE
12/30/2025
Cycle 10 facade report submitted
12/29/2025
Cycle 10 facade inspection completed
02/20/2024
Violation issued (HPD, closed)
B
02/20/2024
Violation issued (HPD, closed)
A
02/20/2024
Violation issued (HPD, closed)
C
02/20/2024
Violation issued (HPD, closed)
A
02/20/2024
Violation issued (HPD, closed)
B
02/20/2024
Violation issued (HPD, closed)
B
02/20/2024
Violation issued (HPD, closed)
B
02/20/2024
Violation issued (HPD, closed)
B
02/20/2024
Violation issued (HPD, closed)
B
02/20/2024
Violation issued (HPD, closed)
A
02/20/2024
Violation issued (HPD, closed)
C
02/20/2024
Violation issued (HPD, closed)
B
02/20/2024
Violation issued (HPD, closed)
B
02/20/2024
Violation issued (HPD, closed)
B
02/20/2024
Violation issued (HPD, closed)
B
02/20/2024
Violation issued (HPD, closed)
A
12/19/2023
Violation issued (HPD, closed)
C
12/19/2023
Violation issued (HPD, closed)
C
11/16/2023
Violation issued (HPD, closed)
B
11/16/2023
Violation issued (HPD, closed)
A
11/16/2023
Violation issued (HPD, closed)
B
11/16/2023
Violation issued (HPD, closed)
C
08/22/2023
Signed off — Alteration
FACADE REPAIR TO COMPLY WITH LOCAL LAW 11/1998. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
Q00693505-I1
08/21/2023
Cycle 9 facade report submitted
08/21/2023
Cycle 9 facade report signed — SAFE
08/05/2023
Violation issued (DOB, closed)
VW*-VIOLATION - WORK W/O PERMIT DISMISSED
07/31/2023
Violation issued (ECB, closed)
Construction
07/18/2023
Inspection — Pass-Final General Construction Non-Directive 14
Pass
View inspection ↗
06/30/2023
Cycle 9 facade inspection completed
06/22/2023
Special inspection requirement — Fire-Resistant Penetrations and Joints
MAHMOUD MANSOURI
06/21/2023
Filed — Alteration
Install bathroom , kitchen sinks & gas line for cooking equipment
Q08048595-P4
06/19/2023
Special inspection requirement — Fire-Resistant Penetrations and Joints
MAHMOUD MANSOURI
06/14/2023
Permit issued — Plumbing
Q08048595-S1-PL
05/30/2023
Filed — Alteration
Install bathroom , kitchen sinks & gas line for cooking equipment
Q08048595-P3
05/22/2023
Filed — Alteration
Install bathroom , kitchen sinks & gas line for cooking equipment
Q08048595-P2
05/19/2023
Special inspection requirement — Fire-Resistant Penetrations and Joints
MAHMOUD MANSOURI
05/05/2023
Inspection — Fail-Final PL - Up to 3 Requested Floors
Fail
View inspection ↗
04/26/2023
Filed — Alteration
Install bathroom , kitchen sinks & gas line for cooking equipment
Q08048595-P1
04/26/2023
Special inspection requirement — Fire-Resistant Penetrations and Joints
MAHMOUD MANSOURI
04/22/2023
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
03/24/2023
Violation issued (ECB, closed)
Elevators
03/15/2023
Permit issued — Mechanical Systems
Q08048595-S2-MS
03/08/2023
Inspection — Certified Gas-Gas-Piping-Roughing
Certified
View inspection ↗
03/08/2023
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
03/07/2023
Violation issued (HPD, closed)
B
03/07/2023
Violation issued (HPD, closed)
B
02/17/2023
Permit issued — General Construction
Q08048595-I1-GC
02/13/2023
Permit issued — Plumbing
Q08048595-S1-PL
01/27/2023
Filed — Alteration
Install bathroom , kitchen sinks & gas line for cooking equipment
Q08048595-S2
01/27/2023
Filed — Alteration
Install bathroom , kitchen sinks & gas line for cooking equipment
Q08048595-S1
01/26/2023
Special inspection requirement — Interior lighting power
MAHMOUD MANSOURI
01/24/2023
Special inspection requirement — Fenestration and door U-factor and product ratings
MAHMOUD MANSOURI
01/24/2023
Special inspection requirement — Fenestration air leakage
MAHMOUD MANSOURI
01/24/2023
Special inspection requirement — Fire-Resistant Penetrations and Joints
MAHMOUD MANSOURI
01/24/2023
Special inspection requirement — Insulation placement and R values
MAHMOUD MANSOURI
01/24/2023
Special inspection requirement — Interior lighting power
MAHMOUD MANSOURI
01/24/2023
Special inspection requirement — Air barrier - visual inspection
MAHMOUD MANSOURI
Latest 60 of 115 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWPlumbingSigned-offJOHN FITZGERALD PLBG &HTG06/14/2023
DOB NOWMechanical SystemsPermit IssuedJJK BUILDING CONSULTING03/15/2023
DOB NOWGeneral ConstructionSigned-offJJK BUILDING CONSULTING02/17/2023
DOB NOWPlumbingSigned-offJOHN FITZGERALD PLBG &HTG02/13/2023
DOB NOWGeneral ConstructionSigned-offJ.N.H. CONSTRUCTION CORP05/13/2022
DOB NOWSidewalk ShedPermit IssuedJ.N.H. CONSTRUCTION CORP03/02/2022
DOB NOWAntennaSigned-offAGL DEVELOPMENT LLC03/11/2021
BISOTISSUEDVEMA GROUP LLC11/13/2018
BISOTISSUEDVEMA GROUP LLC10/17/2018
BISOTISSUEDSQUAN CONSTRUCTION SERVIC04/07/2017
BISOTISSUEDVEMA GROUP LLC03/24/2017
BISOTISSUEDUK 2 CONSTRUCTION CORP10/17/2016
BISEQISSUEDGUL & G CONSTR. CORP08/17/2016
BISEQISSUEDGUL & G CONSTR. CORP08/15/2016
BISOTISSUEDVEMA GROUP LLC03/28/2016
BISEQISSUEDHV DRAFTING & DESIGN ASSO01/30/2016
BISMHISSUEDHV DRAFTING & DESIGN ASSO01/30/2016
BISOTISSUEDVEMA GROUP LLC03/25/2015
BISOTISSUEDVEMA GROUP LLC10/14/2014
BISMHISSUEDMETRO MECHANICAL LLC01/29/2013
BISOTISSUEDBEST ENERGY POWER LLC11/07/2011
BISOTISSUEDFEDCO CONSTR & PAINTING I07/26/2011
BISEQISSUEDSKYRISE GENERAL CONTRACTO06/28/2011
BISFBISSUEDSTEPHEN BRAUN11/01/2007
BISFPISSUEDMASTER FIRE SYSTEMS, INC09/07/2006
BISOTISSUEDRS CONSTRUCTION08/30/2006
BISFPISSUEDNEW YORK BUSINESS FIRE SYSTEM IN02/10/2006
BISPLISSUEDALAN E. ROSENBERG, INC.08/22/2005
BISFBISSUEDG BAUER INC08/15/2005
BIS—ISSUEDUNITECH DESIGN INC05/01/2003
BIS—ISSUEDNEW YORK SIGN CITY CO04/24/2003
BISOTISSUEDSPACE SIGN CO.INC08/16/2002
BISOTISSUEDSPACE SIGN CO08/16/2002
BISOTISSUEDSPACE SIGN CO INC08/13/2002
BISOTISSUEDG. BAUER, INC08/07/2002
BISOTISSUEDSING TAI PRODUCTION INC05/29/2002
BISOTISSUEDSPACE SIGN CO INC04/25/2002
BISOTISSUEDDAEDO SIGN INC03/08/2002
BISOTISSUEDCROSS-STATE CONSTRUCTION CO04/24/2001
BIS—ISSUEDBERGER SIGN F INC10/27/1999
+ 7 more permits on file
1 project · most recent 06/21/2023
Gas Water/Sanitary
FiledStatusContractorScope
06/21/2023Signed-offJOHN FITZGERALD PLBG &HTGGas, Water/Sanitary
12 projects · most recent 02/01/2023
General Wiring
FiledStatusContractorScope
02/01/2023CompleteTESTA ELECTRIC CO., INCGeneral Wiring
04/04/2022CompleteFIBERTEK DATA & ELEC CORPGeneral Wiring
01/25/2022CompleteGREEN SOURCE ELECL CORP—
12/31/2020Permit IssuedC.T.C. ELEC'L CONTRS INC1 meters, 1 new_meters
11/09/2020CompleteC.T.C. ELEC'L CONTRS INCGeneral Wiring
10/19/2020CompleteC.T.C. ELEC'L CONTRS INCGeneral Wiring
10/07/2020CompleteC.T.C. ELEC'L CONTRS INCGeneral Wiring
08/05/2020CompleteC.T.C. ELEC'L CONTRS INCGeneral Wiring
02/05/2020CompleteC.T.C. ELEC'L CONTRS INCGeneral Wiring
04/08/2019CompleteC.T.C. ELEC'L CONTRS INCGeneral Wiring
01/31/2019CompleteC.T.C. ELEC'L CONTRS INCGeneral Wiring
02/08/2018Permit IssuedC.T.C. ELEC'L CONTRS INC—
1 project · most recent 02/28/2022
Sidewalk Shed
FiledStatusContractorScope
02/28/2022Permit IssuedJ.N.H. CONSTRUCTION CORPSidewalk Shed
▾Field Inspections (DOB CAP) — 4
DateTypeResultReport
07/18/2023Pass-Final General Construction Non-Directive 14PassView ↗
05/05/2023Fail-Final PL - Up to 3 Requested FloorsFailView ↗
03/08/2023Certified Gas-Gas-Piping-RoughingCertifiedView ↗
03/08/2023Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 14
DateRequirementInspectorRole
06/22/2023Fire-Resistant Penetrations and JointsMAHMOUD MANSOURIspecial
06/19/2023Fire-Resistant Penetrations and JointsMAHMOUD MANSOURIspecial
05/19/2023Fire-Resistant Penetrations and JointsMAHMOUD MANSOURIspecial
04/26/2023Fire-Resistant Penetrations and JointsMAHMOUD MANSOURIspecial
01/26/2023Interior lighting powerMAHMOUD MANSOURIenergy_progress
01/24/2023Fenestration and door U-factor and product ratingsMAHMOUD MANSOURIenergy_progress
01/24/2023Fenestration air leakageMAHMOUD MANSOURIenergy_progress
01/24/2023Fire-Resistant Penetrations and JointsMAHMOUD MANSOURIspecial
01/24/2023Insulation placement and R valuesMAHMOUD MANSOURIenergy_progress
01/24/2023Interior lighting powerMAHMOUD MANSOURIenergy_progress
01/24/2023Air barrier - visual inspectionMAHMOUD MANSOURIenergy_progress
01/24/2023Fenestration areasMAHMOUD MANSOURIenergy_progress
01/20/2023FinalMAHMOUD MANSOURIprogress
01/20/2023Mechanical SystemsMAHMOUD MANSOURIspecial
▾Documents — 223 on file (BIS + DOB NOW)
▸Plans & Drawings10
▸DOB NOWPlans/Sketch9
08/26/2026Q00681528-I1Request digital key ↗
08/26/2026Q00693505-I1Request digital key ↗
08/24/2026Q08048595-P3Request digital key ↗
Showing 3 of 9 on file for this type
▸DOB NOWPlans/Sketch - Antenna1
08/27/2026Q00436781-I1Request digital key ↗
▸Applications & Permits31
▸BISPLAN / WORK APPROVAL APPLICATION16
07/16/2018421480579Open ↗
05/11/2018440241711Open ↗
04/24/2018440241711Open ↗
Showing 3 of 16 on file for this type
▸BISWORK PERMIT APPLICATION13
11/27/2018421480579Open ↗
11/10/2018421480579Open ↗
04/07/2017440241711Open ↗
Showing 3 of 13 on file for this type
▸BISNon-Directive 14 Construction Sign Off Including Sign Applications2
02/16/2017440353564Open ↗
10/25/2013420462671Open ↗
▸Seals & Professional Certifications71
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION25
07/26/2019421480579Open ↗
07/26/2019421480579Open ↗
07/26/2019421480579Open ↗
Showing 3 of 25 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature10
08/27/2026Q00436781-I1Open ↗
08/26/2026Q00681528-I1Open ↗
08/24/2026Q08048595-S1Open ↗
Showing 3 of 10 on file for this type
▸DOB NOWProgress Inspector Seal & Signature8
08/31/2026Q08048595-I1Open ↗
08/31/2026Q08048595-I1Open ↗
08/31/2026Q08048595-I1Open ↗
Showing 3 of 8 on file for this type
▸BISPROFESSIONAL CERTIFIED CHECKLIST6
08/29/2016421363063Open ↗
08/22/2016421338305Open ↗
11/09/2011420501754Open ↗
Showing 3 of 6 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM6
11/10/2011420501754Open ↗
11/10/2011420501754Open ↗
11/09/2011420501754Open ↗
Showing 3 of 6 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature6
08/31/2026Q08048595-P2Open ↗
08/31/2026Q08048595-I1Open ↗
08/28/2026Q08048595-P1Open ↗
Showing 3 of 6 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT4
10/13/2016440353564Open ↗
08/29/2016421363063Open ↗
08/22/2016421338305Open ↗
Showing 3 of 4 on file for this type
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY2
10/13/2016440353564Open ↗
01/28/2016440285148Open ↗
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION2
10/13/2016440353564Open ↗
01/28/2016440285148Open ↗
▸BISPC FULL REPORT1
11/01/2007410025565Open ↗
▸BISAPPLICANT OWNER SIGNATURE1
12/15/2015440241711Open ↗
▸Trade Schedules & Equipment5
▸BISEQUIPMENT USE PERMITS2
05/20/2013420787811Open ↗
05/20/2013420787811Open ↗
▸BISEQUIPMENT USE APPLICATION/PERMIT1
04/18/2013420787811Open ↗
▸BISSCHEDULE B - PLUMBING1
01/28/2016440285148Open ↗
▸BISFA - FDNY APPROVAL : FD-FAA1
03/30/2017440241711Open ↗
▸Safety & Tenant Protection5
▸BISTenant Protection Plan and Notes4
07/16/2018421480579Open ↗
03/30/2017440241711Open ↗
08/29/2016421363063Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWTenant Protection Plan1
08/13/2026Q00436781-I1Open ↗
▸Environmental & Asbestos18
▸DOB NOWDEP ACP-5: Asbestos Assessment Report9
08/27/2026Q00436781-I1Open ↗
08/24/2026Q08048595-P3Open ↗
08/24/2026Q08048595-P2Open ↗
Showing 3 of 9 on file for this type
▸BISASBESTOS: CERTIFICATION (DEP ACP5)4
10/13/2016440353564Open ↗
01/28/2016440285148Open ↗
08/12/2014420983742Open ↗
Showing 3 of 4 on file for this type
▸BISTHIS IS 'NOT AN ASBESTOS PROJECT'3
11/09/2011420501754Open ↗
07/26/2011420462671Open ↗
11/01/2007410025565Open ↗
▸BISDEP ASBESTOS PROJECT COMPLETION FORM2
01/19/2019421480579Open ↗
07/16/2018421480579Open ↗
▸Energy Compliance24
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS8
06/14/2019421480579Open ↗
07/16/2018421480579Open ↗
06/21/2018440241711Open ↗
Showing 3 of 8 on file for this type
▸BISAS-BUILT ENERGY ANALYSIS5
06/14/2019421480579Open ↗
06/21/2018440241711Open ↗
02/16/2017440353564Open ↗
Showing 3 of 5 on file for this type
▸BISSOLAR TAX ABATEMENT APPLICATION (PTA4)2
02/06/2013420501754Open ↗
01/14/2013420501754Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY FOR ENERGY CODE PROGRESS INSPECTIONS2
10/13/2016440353564Open ↗
01/28/2016440285148Open ↗
▸BISTECHNICAL REPORT: ENERGY2
11/09/2011420501754Open ↗
07/26/2011420462671Open ↗
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY2
01/28/2016440285148Open ↗
12/15/2015440241711Open ↗
▸BISPTA4: SOLAR TAX ABATEMENT APPLICATION (FINAL)2
05/03/2013420501754Open ↗
03/08/2013420501754Open ↗
▸BISTR8: Energy Code Progress Inspections1
02/06/2013420501754Open ↗
▸Inspections & Test Reports4
▸BISTECHNICAL REPORT: RESPONSIBILITY3
10/13/2016440353564Open ↗
01/28/2016440285148Open ↗
12/15/2015440241711Open ↗
▸BISNOTIF.-PROPOSED STEAM/HOT WATER INSPECTION1
11/01/2007410025565Open ↗
▸Approvals, Objections & Sign-offs19
▸BISADMINISTRATIVE OBJECTIONS8
08/29/2016421363063Open ↗
08/22/2016421338305Open ↗
08/12/2014420983742Open ↗
Showing 3 of 8 on file for this type
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST7
07/26/2019421480579Open ↗
07/08/2019421480579Open ↗
06/21/2018440241711Open ↗
Showing 3 of 7 on file for this type
▸BISLETTERS - SUPPORTING DOCUMENTATION3
10/25/2013420462671Open ↗
04/19/2013420787811Open ↗
02/06/2013420501754Open ↗
▸BISUtility Company PV System Interconnection Acknowledgement Letter1
02/06/2013420501754Open ↗
▸Cost, Insurance & Ownership17
▸BISCOST AFFIDAVIT16
06/14/2019421480579Open ↗
07/16/2018421480579Open ↗
06/21/2018440241711Open ↗
Showing 3 of 16 on file for this type
▸BISSTEEL AFFIDAVIT- FINAL1
10/22/2014420983742Open ↗
▸Filing & Intake Forms17
▸BISEFILING COVER SHEET8
07/16/2018421480579Open ↗
08/29/2016421363063Open ↗
08/22/2016421338305Open ↗
Showing 3 of 8 on file for this type
▸BISADDITIONAL INFORMATION5
05/11/2018440241711Open ↗
05/04/2018440241711Open ↗
03/30/2017440241711Open ↗
Showing 3 of 5 on file for this type
▸BISBOROUGH INTAKE FORM2
05/10/2018440241711Open ↗
04/24/2018440241711Open ↗
▸BISEFILING JOB APPLICATION COVER SHEET2
10/13/2016440353564Open ↗
01/28/2016440285148Open ↗
▸Other Documents2
▸BISTax Abatement Miscellaneous1
02/06/2013420501754Open ↗
▸DOB NOWDHCR Document1
08/13/2026Q00693505-I1Open ↗