| Owner | Filings | Most Recent |
|---|---|---|
| Woodrow Wilson Owners | 25 | 03/22/2026 |
| John B. Lovett & Associates | 4 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| Aminov Design Engineering | 2 | 03/24/2026 |
| A2 Architect | 4 | 09/09/2025 |
| Mago Architecture | 2 | 04/04/2022 |
| Edward C. Hicks RA | 1 | 07/07/2021 |
| Syed Engineering | 2 | 06/16/2021 |
| Representative | Filings | Most Recent |
|---|---|---|
| J A Expediting | 8 | 03/21/2026 |
| Expediting | 2 | 03/21/2026 |
| Kataria Builders | 2 | 03/21/2026 |
| A D Building Solutions | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| Topline NYC Contracting | Scaffold | 5 | 07/08/2026 |
| Dfe Contractor | General Contractor | 3 | 03/21/2026 |
| Aha Interiors | General Contractor | 3 | 03/21/2026 |
| Reliable Renovations USA | General Contractor | 3 | 03/21/2026 |
| Preference Painting & Wal | specialty_contractor | 2 | 04/09/2026 |
| Triple D Electric | Electrical | 1 | 03/22/2026 |
| Valentis Electric | Electrical | 1 | 03/22/2026 |
| Belgium Properties | General Contractor | 1 | 07/08/2026 |
| Ice Age Mechanical | specialty_contractor | 1 | 07/08/2026 |
| V.P. Construction | General Contractor | 1 | 04/09/2026 |
| Delta-Sigma Mechanical | Plumbing | 1 | 07/08/2026 |
| John Fitzgerald Plumbing & Heating | Plumbing | 1 | 07/08/2026 |
| Forest Hills Electrical Cont | Electrical | 1 | 03/22/2026 |
| Protocol Plumbing & Heating | Plumbing | 1 | 07/08/2026 |
| Dynamic Electrical | Electrical | 1 | 03/21/2026 |
| Joseph Weinstein Electric | Electrical | 1 | 03/22/2026 |
| Rem & Sons Lic Electric Cont | Electrical | 1 | 03/22/2026 |
| Todaro Joseph | Electrical | 1 | 03/21/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| Aminov Design Engineer, P | 9365 | 2 | 03/24/2026 |
| A2 Architect | 2504 | 4 | 09/09/2025 |
| International Geotehcnica | 1795 | 2 | 04/04/2022 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Mechanical Systems | Permit Issued | Ice Age Mechanical | 05/15/2026 |
| DOB NOW | General Construction | Signed-off | Preference Painting & Wal | 02/25/2026 |
| DOB NOW | General Construction | Permit Issued | V.P. Construction | 01/12/2026 |
| DOB NOW | Plumbing | Signed-off | John Fitzgerald Plumbing & Heating | 01/09/2026 |
| DOB NOW | General Construction | Signed-off | Preference Painting & Wal | 10/30/2025 |
| DOB NOW | General Construction | Signed-off | Reliable Renovations USA | 11/21/2024 |
| DOB NOW | Plumbing | Signed-off | Protocol Plumbing & Heating | 10/30/2024 |
| DOB NOW | General Construction | Signed-off | Aha Interiors | 04/21/2022 |
| DOB NOW | Plumbing | Signed-off | Delta-Sigma Mechanical | 04/20/2022 |
| DOB NOW | General Construction | Signed-off | Belgium Properties | 11/24/2021 |
| DOB NOW | General Construction | Signed-off | Dfe Contractor | 10/01/2021 |
| DOB NOW | Sidewalk Shed | Signed-off | Topline NYC Contracting | 07/27/2021 |
| DOB NOW | Supported Scaffold | Signed-off | Topline NYC Contracting | 06/18/2021 |
| DOB NOW | Sidewalk Shed | Signed-off | Topline NYC Contracting | 06/22/2020 |
| BIS | OT | ISSUED | American Builders & Contracting | 05/10/2022 |
| BIS | OT | ISSUED | American Builders & Contracting | 04/28/2021 |
| BIS | OT | ISSUED | American Builders & Contracting | 11/02/2020 |
| BIS | OT | ISSUED | American Builders & Contracting | 10/26/2020 |
| BIS | OT | ISSUED | American Builders & Contracting | 09/27/2019 |
| BIS | PL | ISSUED | Prime Piping & Heating | 11/20/2017 |
| BIS | OT | ISSUED | American Builders & Contracting | 08/17/2016 |
| BIS | PL | ISSUED | Aljer Plumbing & Heating | 07/15/2016 |
| BIS | OT | ISSUED | Kristopher Suarez | 06/22/2016 |
| BIS | PL | ISSUED | Forward Mechanical | 01/27/2016 |
| BIS | OT | ISSUED | Indian Head Contracting | 01/27/2016 |
| BIS | OT | ISSUED | Arteco and Design Restoration | 01/31/2011 |
| BIS | PL | ISSUED | Safety Plumbing & Heating | 01/11/2011 |
| BIS | OT | ISSUED | Arteco and Design Restoration | 11/19/2010 |
| BIS | PL | RE-ISSUED | Senid PL & Heating | 04/01/2010 |
| BIS | OT | ISSUED | Wilman Custom Design | 03/30/2010 |
| BIS | OT | ISSUED | Skyline Restoration | 03/28/2007 |
| BIS | EQ | ISSUED | Everest Scaffolding | 01/09/2007 |
| BIS | EQ | ISSUED | Everest Scaffolding | 08/09/2006 |
| BIS | PL | ISSUED | D. Diaz PLG & Heating Co | 09/23/2004 |
| BIS | OT | ISSUED | D.N.A. Construction | 05/03/1996 |
| BIS | EQ | ISSUED | Spring Int | 04/11/1996 |
| BIS | OT | ISSUED | D.N.A. Construction | 11/09/1995 |
| BIS | FB | ISSUED | Abilene | 10/15/1992 |
| BIS | PL | ISSUED | BMC Plumbing | 10/15/1992 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 03/24/2026 | Permit Issued | Ice Age Mechanical | Air Conditioning Systems | Cooling Mitsubishi Electric SUZ-AA36NL 33,000 BTU · Heat Pump Outdoor ×1 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/09/2025 | Signed-off | John Fitzgerald Plumbing & Heating | Gas, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 02/18/2026 | Permit Issued | Tempest Electrical Contracting | General Wiring |
| 09/01/2024 | Complete | Triple D Electric | General Wiring |
| 11/05/2023 | Complete | Amp Power Electric Service | General Wiring |
| 11/03/2023 | Complete | Argon Electrical | General Wiring |
| 03/16/2023 | Complete | Valentis Electric | General Wiring |
| 06/21/2022 | Permit Issued | Forest Hills Electrical Cont | General Wiring |
| 10/25/2021 | Complete | Asset Electric | General Wiring |
| 10/13/2021 | Complete | Joseph Weinstein Electric | General Wiring |
| 08/04/2021 | Permit Issued | Richard Neu | — |
| 07/23/2020 | Complete | Argon Electrical | — |
| 03/09/2020 | Permit Issued | Rem & Sons Lic Electric Cont | General Wiring |
| 01/15/2020 | Permit Issued | Sammy Electrical | General Wiring |
| 01/10/2020 | Complete | All-Rite Electric Corp of NY | — |
| 03/31/2019 | Complete | Jam Electrical | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/09/2025 | Signed-off | Preference Painting & Wal | Tenant Protection Plan 72 Hour |
| Date | Type | Result | Report |
|---|---|---|---|
| 03/26/2026 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 03/26/2026 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 03/24/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 02/03/2025 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 01/23/2025 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 12/13/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 12/11/2024 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 09/19/2022 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 09/19/2022 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 06/21/2022 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 01/08/2026 | Fire-Resistant Penetrations and Joints | MARK AMINOV | special |
| 10/13/2025 | HVAC-R and service water piping design and insulation | MARK AMINOV | energy_progress |
| 10/13/2025 | HVAC-R and service water heating system controls | MARK AMINOV | energy_progress |
| 10/13/2025 | Energy Code Compliance Inspections | MARK AMINOV | progress |
| 10/13/2025 | Final | MARK AMINOV | progress |
| 10/13/2025 | Maintenance information | MARK AMINOV | energy_progress |
| 10/13/2025 | HVAC-R and service water heating equipment | MARK AMINOV | energy_progress |
| 10/13/2025 | Mechanical Systems | MARK AMINOV | special |
| 08/29/2025 | Energy Code Compliance Inspections | MARK AMINOV | progress |
| 08/29/2025 | Maintenance information | MARK AMINOV | energy_progress |
| 08/29/2025 | Interior lighting power | MARK AMINOV | energy_progress |
| 08/29/2025 | Tenant Protection Plan Compliance | MARK AMINOV | special |
| 08/22/2025 | Fire-Resistant Penetrations and Joints | Ann Macklin | special |
| 06/28/2024 | Fire-Resistant Penetrations and Joints | Ann Macklin | special |
| 04/04/2022 | Lighting in dwelling units | MICHAEL KARANTINIDIS, P.E. | energy_progress |
| 04/03/2022 | Energy Code Compliance Inspections | MICHAEL KARANTINIDIS, P.E. | progress |
| 04/03/2022 | Fire-Resistance Rated Construction | MICHAEL KARANTINIDIS, P.E. | progress |
| 04/03/2022 | Fire-Resistant Penetrations and Joints | MICHAEL KARANTINIDIS, P.E. | special |
| 03/28/2022 | Fire-Resistant Penetrations and Joints | MICHAEL KARANTINIDIS, P.E. | special |
| 03/28/2022 | Final | Hannibal Newsom | progress |
| 07/28/2021 | Energy Code Compliance Inspections | EDWARD HICKS | progress |
| 07/02/2021 | Final | EDWARD HICKS | progress |
| 07/02/2021 | Lighting in dwelling units | EDWARD HICKS | energy_progress |