← Back
One family attached or semi-detached
69-13 198 STREET
QUEENS · Fresh Meadows-Utopia · BIN 4153824
💬 Discuss this project
1940Year Built
2Stories
A5Building Class
R3-2Zoning
1,828 sfGross Floor Area
1Units
One family attached or semi-detached · 1,695 sf lot · 1.08 FAR built · Flood zone X
Locations of Work
ArchitectureElectrical
Roof2p · 1 filing · 11 docs
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
SQUARE ARCH, LLC211/10/2025
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
KAMTECH RESTORATION CORP403/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
KAMTECH RESTORATION CORPGeneral Contractor107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
SQ. ARCH, LLC4802211/10/2025
Building Lifecycle
All (14)Filed (2)Permit Issued (1)Signed Off (1)Objection (6)Special Inspection (4)
12/15/2025
Signed off — Alteration
ROOFTOP SOLAR INSTALLATION. NO CHANGE TO USE, OCCUPANCY OR EGRESS.
Q01283308-I1
11/26/2025
Objection resolved — Addressed
11/26/2025
Objection resolved — Addressed
11/24/2025
Objection raised — Other
11/24/2025
Objection raised — Other
11/10/2025
Filed — Alteration
ROOFTOP SOLAR INSTALLATION. NO CHANGE TO USE, OCCUPANCY OR EGRESS.
Q01283308-P1
11/10/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
Kaijin Liang
11/10/2025
Special inspection requirement — Energy Code Compliance Inspections
Kaijin Liang
11/10/2025
Special inspection requirement — Final
Kaijin Liang
11/10/2025
Special inspection requirement — Air barrier - visual inspection
Kaijin Liang
10/07/2025
Permit issued — Solar
Q01283308-I1-SL
10/02/2025
Objection resolved — Addressed
09/24/2025
Objection raised — Structural
09/08/2025
Filed — Alteration
ROOFTOP SOLAR INSTALLATION. NO CHANGE TO USE, OCCUPANCY OR EGRESS.
Q01283308-I1
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSolarSigned-offKAMTECH RESTORATION CORP10/07/2025
1 project · most recent 09/03/2025
FiledStatusContractorScope
09/03/2025CompleteBERGER QUALITY ELEC'L CON—
▾Special Inspection Requirements (DOB NOW) — 4
DateRequirementInspectorRole
11/10/2025Fire-Resistant Penetrations and JointsKaijin Liangspecial
11/10/2025Energy Code Compliance InspectionsKaijin Liangprogress
11/10/2025FinalKaijin Liangprogress
11/10/2025Air barrier - visual inspectionKaijin Liangenergy_progress
▾Documents — 11 on file (BIS + DOB NOW)
▸Plans & Drawings2
▸DOB NOWPlans/Sketch2
08/19/2026Q01283308-P1Request digital key ↗
08/19/2026Q01283308-I1Request digital key ↗
▸Seals & Professional Certifications6
▸DOB NOWProgress Inspector Seal & Signature3
08/27/2026Q01283308-P1Open ↗
08/27/2026Q01283308-P1Open ↗
08/27/2026Q01283308-P1Open ↗
▸DOB NOWDPL-1: Design Professional Seal & Signature2
08/19/2026Q01283308-I1Open ↗
08/13/2026Q01283308-P1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature1
08/27/2026Q01283308-P1Open ↗
▸Environmental & Asbestos2
▸DOB NOWDEP ACP-5: Asbestos Assessment Report2
08/19/2026Q01283308-I1Open ↗
08/13/2026Q01283308-P1Open ↗
▸Approvals, Objections & Sign-offs1
▸DOB NOWUtility Company Final Acceptance Letter1
08/13/2026Q01283308-I1Open ↗