1950Year Built
2Stories
B2Building Class
R3XZoning
2,320 sfGross Floor Area
2Units
0 Open ViolationsFDNY Report ↗
Two family frame · 4,000 sf lot · 0.58 FAR built · Flood zone X
Locations of Work
ArchitectureMechanical
Floor 21 filing · 20 docs
Floor 11 filing · 20 docs
Cellar1p · 1 filing · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
TABRIZ GROUP DESIGN1107/08/2026
FOXY GROUP LLC103/22/2026
J J DESIGNS203/22/2026
AYYUB ELECTRIC CORP103/22/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
11/15/2023$1.9M—FOXY GROUP LLC → Private party$841/sf building
12/06/2021$1.1M—Private party → FOXY GROUP LLC$453/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
TABRIZ DESIGN GROUP401/27/2023
TABRIZ GROUP ENTERPRISES210/27/2022
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
J&J DESIGNS INCGeneral Contractor407/08/2026
BT'S PLUMBING AND HEATINGPlumbing107/08/2026
INFINITI ESC PLUMBING CORPlumbing107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
TABRIZ GROUP ENTERPRISES3275210/27/2022
Building Lifecycle
All (53)Filed (6)Permit Issued (4)Signed Off (2)Violation (5)Inspection (7)Objection (6)Special Inspection (23)
03/11/2023
Violation issued (ECB, closed)
Construction
02/21/2023
Signed off — Alteration
PLUMBING WORK IN CONJUNCTION WITH ALTERATION APPLICATION #Q00667985
Q00714594-I1
01/27/2023
Filed — Alteration
PLUMBING WORK IN CONJUNCTION WITH ALTERATION APPLICATION #Q00667985
Q00714594-P2
01/24/2023
Inspection — Certified Sprinkler-SP-Fixtures-Finish
Certified
View inspection ↗
01/18/2023
Inspection — Certified Storm Drainage-ST-Fixtures-Finish
Certified
View inspection ↗
01/18/2023
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
12/28/2022
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
12/27/2022
Filed — Alteration
PLUMBING WORK IN CONJUNCTION WITH ALTERATION APPLICATION #Q00667985
Q00714594-P1
12/16/2022
Inspection — Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test
Certified
View inspection ↗
12/12/2022
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
12/06/2022
Permit issued — Mechanical Systems
Q00667985-I1-GC-CX
12/05/2022
Permit issued — Plumbing
Q00714594-I1-PL
11/21/2022
Objection resolved — Addressed
11/21/2022
Objection resolved — Addressed
11/21/2022
Objection resolved — Addressed
11/03/2022
Objection raised — Fire_Protection
11/03/2022
Objection raised — Fire_Protection
10/31/2022
Objection raised — Other
10/27/2022
Filed — Alteration CO
PROPOSED VERTICAL ENLARGEMENT, FULL INTERIOR & EXTERIOR RENOVATION, AND CONVERSION TO TWO-FAMILY.
Q00667985-P1
10/27/2022
Special inspection requirement — Fire-Resistant Penetrations and Joints
BAKHTIAR SHAMLOO
10/27/2022
Special inspection requirement — Masonry
BAKHTIAR SHAMLOO
10/27/2022
Special inspection requirement — Mechanical Systems
BAKHTIAR SHAMLOO
10/27/2022
Special inspection requirement — Structural Stability – Alterations of existing buildings
BAKHTIAR SHAMLOO
10/27/2022
Special inspection requirement — Energy Code Compliance Inspections
BAKHTIAR SHAMLOO
10/27/2022
Special inspection requirement — Final
HARI SONI
10/27/2022
Special inspection requirement — Fire-Resistance Rated Construction
BAKHTIAR SHAMLOO
10/27/2022
Special inspection requirement — Electric vehicle service equipment requirements
BAKHTIAR SHAMLOO
10/27/2022
Special inspection requirement — Air barrier — testing
BAKHTIAR SHAMLOO
10/27/2022
Special inspection requirement — Fenestration air leakage
BAKHTIAR SHAMLOO
10/27/2022
Special inspection requirement — Air barrier - visual inspection
BAKHTIAR SHAMLOO
10/27/2022
Special inspection requirement — HVAC-R and service water piping design and insulation
BAKHTIAR SHAMLOO
10/27/2022
Special inspection requirement — Fenestration and door U-factor and product ratings
BAKHTIAR SHAMLOO
10/27/2022
Special inspection requirement — Insulation placement and R values
BAKHTIAR SHAMLOO
10/27/2022
Special inspection requirement — HVAC-R and service water heating equipment
BAKHTIAR SHAMLOO
10/27/2022
Special inspection requirement — Duct leakage testing, insulation and design
BAKHTIAR SHAMLOO
10/27/2022
Special inspection requirement — HVAC-R and service water heating system controls
BAKHTIAR SHAMLOO
10/27/2022
Special inspection requirement — Interior lighting power
BAKHTIAR SHAMLOO
10/27/2022
Special inspection requirement — Maintenance information
BAKHTIAR SHAMLOO
10/27/2022
Special inspection requirement — Fenestration areas
BAKHTIAR SHAMLOO
10/27/2022
Special inspection requirement — Metering
BAKHTIAR SHAMLOO
10/27/2022
Special inspection requirement — Permanent certificate
BAKHTIAR SHAMLOO
08/25/2022
Signed off — Alteration
Q00648524-I1
07/27/2022
Violation issued (ECB, closed)
Construction
07/27/2022
Violation issued (ECB, closed)
Unknown
07/27/2022
Violation issued (ECB, closed)
Construction
06/16/2022
Inspection — Pass-Final PL - Up to 9 Requested Floors
Pass
View inspection ↗
05/04/2022
Violation issued (ECB, closed)
Construction
04/20/2022
Permit issued — Plumbing
Q00714594-I1-PL
04/07/2022
Filed — Alteration
PLUMBING WORK IN CONJUNCTION WITH ALTERATION APPLICATION #Q00667985
Q00714594-I1
02/03/2022
Filed — Alteration CO
PROPOSED VERTICAL ENLARGEMENT, FULL INTERIOR & EXTERIOR RENOVATION, AND CONVERSION TO TWO-FAMILY.
Q00667985-I1
12/17/2021
Permit issued — Construction Fence
Q00648524-I1-FN
12/15/2021
Filed — Alteration
Q00648524-I1
12/15/2021
Special inspection requirement — Final
HARI SONI
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWMechanical SystemsPermit IssuedJ&J DESIGNS INC12/06/2022
DOB NOWPlumbingSigned-offINFINITI ESC PLUMBING COR12/05/2022
DOB NOWPlumbingSigned-offBT'S PLUMBING AND HEATING04/20/2022
DOB NOWConstruction FenceSigned-offJ&J DESIGNS INC12/17/2021
1 project · most recent 10/27/2022
Air Conditioning Systems
FiledStatusContractorScopeMake / Model / Capacity
10/27/2022Permit IssuedJ&J DESIGNS INCAir Conditioning Systems
Cooling
Comfort Aire RSG1448S1P, GUH955A 60,000 BTU · Furnace ×2
2 projects · most recent 02/17/2023
General Wiring
FiledStatusContractorScope
02/17/2023CompleteAYYUB ELECTRIC CORPGeneral Wiring
06/02/2022CancelledAYYUB ELECTRIC CORPGeneral Wiring
▾Field Inspections (DOB CAP) — 7
DateTypeResultReport
01/24/2023Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
01/18/2023Certified Storm Drainage-ST-Fixtures-FinishCertifiedView ↗
01/18/2023Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
12/28/2022Pass-Final PL - Up to 3 Requested FloorsPassView ↗
12/16/2022Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
12/12/2022Pass-Final CND-Occupancy InspectionPassView ↗
06/16/2022Pass-Final PL - Up to 9 Requested FloorsPassView ↗
▾Special Inspection Requirements (DOB NOW) — 23
DateRequirementInspectorRole
10/27/2022Fire-Resistant Penetrations and JointsBAKHTIAR SHAMLOOspecial
10/27/2022MasonryBAKHTIAR SHAMLOOspecial
10/27/2022Mechanical SystemsBAKHTIAR SHAMLOOspecial
10/27/2022Structural Stability – Alterations of existing buildingsBAKHTIAR SHAMLOOspecial
10/27/2022Energy Code Compliance InspectionsBAKHTIAR SHAMLOOprogress
10/27/2022FinalHARI SONIprogress
10/27/2022Fire-Resistance Rated ConstructionBAKHTIAR SHAMLOOprogress
10/27/2022Electric vehicle service equipment requirementsBAKHTIAR SHAMLOOenergy_progress
10/27/2022Air barrier — testing BAKHTIAR SHAMLOOenergy_progress
10/27/2022Fenestration air leakageBAKHTIAR SHAMLOOenergy_progress
10/27/2022Air barrier - visual inspectionBAKHTIAR SHAMLOOenergy_progress
10/27/2022HVAC-R and service water piping design and insulationBAKHTIAR SHAMLOOenergy_progress
10/27/2022Fenestration and door U-factor and product ratingsBAKHTIAR SHAMLOOenergy_progress
10/27/2022Insulation placement and R valuesBAKHTIAR SHAMLOOenergy_progress
10/27/2022HVAC-R and service water heating equipmentBAKHTIAR SHAMLOOenergy_progress
10/27/2022Duct leakage testing, insulation and designBAKHTIAR SHAMLOOenergy_progress
10/27/2022HVAC-R and service water heating system controlsBAKHTIAR SHAMLOOenergy_progress
10/27/2022Interior lighting powerBAKHTIAR SHAMLOOenergy_progress
10/27/2022Maintenance informationBAKHTIAR SHAMLOOenergy_progress
10/27/2022Fenestration areasBAKHTIAR SHAMLOOenergy_progress
10/27/2022MeteringBAKHTIAR SHAMLOOenergy_progress
10/27/2022Permanent certificateBAKHTIAR SHAMLOOenergy_progress
12/15/2021FinalHARI SONIprogress
▾Documents — 35 on file (BIS + DOB NOW)
▸Plans & Drawings5
▸DOB NOWPlans/Sketch5
08/25/2026Q00667985-I1Request digital key ↗
08/25/2026Q00714594-I1Request digital key ↗
08/25/2026Q00714594-P2Request digital key ↗
Showing 3 of 5 on file for this type
▸Zoning, Tax Lot & Property Records3
▸DOB NOWZD1: DOB Zoning Diagram2
08/13/2026Q00667985-I1Open ↗
08/13/2026Q00667985-P1Open ↗
▸DOB NOWHouse Number Verification: TOPO Stamp1
08/13/2026Q00667985-I1Open ↗
▸Seals & Professional Certifications13
▸DOB NOWDPL-1: Design Professional Seal & Signature6
08/25/2026Q00667985-P1Open ↗
08/25/2026Q00667985-I1Open ↗
08/25/2026Q00714594-I1Open ↗
Showing 3 of 6 on file for this type
▸DOB NOWProgress Inspector Seal & Signature5
09/29/2026Q00667985-P1Open ↗
09/29/2026Q00667985-P1Open ↗
09/29/2026Q00667985-P1Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature2
09/29/2026Q00667985-P1Open ↗
09/29/2026Q00667985-P1Open ↗
▸Safety & Tenant Protection2
▸DOB NOWStreet Tree Checklist2
08/13/2026Q00667985-I1Open ↗
08/13/2026Q00667985-P1Open ↗
▸Environmental & Asbestos2
▸DOB NOWDEP ACP-5: Asbestos Assessment Report2
08/25/2026Q00667985-I1Open ↗
08/15/2026Q00667985-P1Open ↗
▸Energy Compliance1
▸DOB NOWEN2: As Built Energy Analysis1
08/13/2026Q00667985-I1Open ↗
▸Other Documents9
▸DOB NOWPlot Diagram2
08/13/2026Q00667985-I1Open ↗
08/13/2026Q00667985-P1Open ↗
▸DOB NOWProperty Ownership Certification2
08/25/2026Q00667985-I1Open ↗
08/15/2026Q00667985-P1Open ↗
▸DOB NOWSite Survey: Initial2
08/13/2026Q00667985-I1Open ↗
08/13/2026Q00667985-P1Open ↗
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone2
08/13/2026Q00667985-I1Open ↗
08/13/2026Q00667985-P1Open ↗
▸DOB NOWFinal Survey1
08/13/2026Q00667985-I1Open ↗