| Owner | Filings | Most Recent |
|---|---|---|
| 69-61 180TH STREET | 22 | 07/08/2026 |
| TRENDZ CONTRACTING | 1 | 03/22/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| JLS DESIGNS | 11 | 04/14/2026 |
| Representative | Filings | Most Recent |
|---|---|---|
| LS EXPEDITOR | 5 | 03/21/2026 |
| JLS DESIGNS | 3 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| DFE CONTRACTOR LLC | General Contractor | 5 | 07/08/2026 |
| FLINT MECHANICAL CORP | Plumbing | 2 | 07/08/2026 |
| WCK ELECTRIC CORP. | Electrical | 1 | 03/22/2026 |
| DIESEL CONTRACTING OF N.Y | General Contractor | 1 | 07/08/2026 |
| TRENDZ CONTRACTING CORP | General Contractor | 1 | 03/21/2026 |
| ROCK E SMALL PLBG&HTG INC | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| JLS DESIGNS | 1377 | 7 | 04/14/2026 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Earth Work | Signed-off | DFE CONTRACTOR LLC | 11/06/2025 |
| DOB NOW | Mechanical Systems | Signed-off | DFE CONTRACTOR LLC | 11/06/2025 |
| DOB NOW | Mechanical Systems | Signed-off | CENTRAL CONSTRUCTION MAN* | 03/20/2025 |
| DOB NOW | Foundation | Signed-off | DFE CONTRACTOR LLC | 03/10/2025 |
| DOB NOW | Plumbing | Signed-off | FLINT MECHANICAL CORP | 02/04/2025 |
| DOB NOW | Plumbing | Signed-off | FLINT MECHANICAL CORP | 01/29/2024 |
| DOB NOW | Foundation | Signed-off | DFE CONTRACTOR LLC | 01/29/2024 |
| DOB NOW | Construction Fence | Signed-off | DFE CONTRACTOR LLC | 01/24/2024 |
| DOB NOW | Plumbing | Signed-off | ROCK E SMALL PLBG&HTG INC | 09/01/2023 |
| DOB NOW | Foundation | Signed-off | TRENDZ CONTRACTING CORP | 08/11/2023 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 04/14/2026 | Signed-off | DFE CONTRACTOR LLC | Heating and Air Conditioning Systems | Heat / Cool Mitsubishi Electric MXZ-SM36NAMH-Z-U1 42,000 BTU · Vrf Outdoor ×4 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/14/2026 | Signed-off | FLINT MECHANICAL CORP | Gas, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/14/2026 | Permit Issued | WCK ELECTRIC CORP. | General Wiring |
| 09/14/2026 | Permit Issued | WCK ELECTRIC CORP. | General Wiring |
| 07/24/2024 | Permit Issued | WCK ELECTRIC CORP. | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/14/2026 | Signed-off | DFE CONTRACTOR LLC | 7 scope_items |
| Date | Type | Result | Report |
|---|---|---|---|
| 07/20/2026 | Pass-Final PL - Up to 9 Requested Floors | Pass | View ↗ |
| 04/07/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 02/18/2026 | Fail-Final General Construction Non-Directive 14 | Fail | View ↗ |
| 02/09/2026 | Fail-Final General Construction Non-Directive 14 | Fail | View ↗ |
| 07/31/2024 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 07/31/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 04/03/2024 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 04/03/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 05/14/2026 | Mechanical Systems | JOSEPH SULTANA, JR | special |
| 05/14/2026 | Final | JOSEPH SULTANA, JR | progress |
| 05/14/2026 | Ventilation and air distribution system | JOSEPH SULTANA, JR | energy_progress |
| 05/14/2026 | HVAC-R and service water heating equipment | JOSEPH SULTANA, JR | energy_progress |
| 05/14/2026 | Maintenance information | JOSEPH SULTANA, JR | energy_progress |
| 05/14/2026 | HVAC-R and service water piping design and insulation | JOSEPH SULTANA, JR | energy_progress |
| 05/14/2026 | Duct leakage testing, insulation and design | JOSEPH SULTANA, JR | energy_progress |
| 05/14/2026 | HVAC-R and service water heating system controls | JOSEPH SULTANA, JR | energy_progress |
| 04/22/2026 | Fenestration air leakage | JOSEPH SULTANA, JR | energy_progress |
| 04/22/2026 | Fenestration areas | JOSEPH SULTANA, JR | energy_progress |
| 04/22/2026 | Interior lighting power | JOSEPH SULTANA, JR | energy_progress |
| 04/22/2026 | Insulation placement and R values | JOSEPH SULTANA, JR | energy_progress |
| 04/22/2026 | Preliminary | JOSEPH SULTANA, JR | progress |
| 04/22/2026 | Final | JOSEPH SULTANA, JR | progress |
| 04/22/2026 | Footing and Foundation | JOSEPH SULTANA, JR | progress |
| 04/22/2026 | Fire-Resistant Penetrations and Joints | JOSEPH SULTANA, JR | special |
| 04/22/2026 | Concrete - Cast-In-Place | JOSEPH SULTANA, JR | special |
| 04/22/2026 | Masonry | JOSEPH SULTANA, JR | special |
| 04/22/2026 | Fenestration and door U-factor and product ratings | JOSEPH SULTANA, JR | energy_progress |
| 04/22/2026 | Energy Code Compliance Inspections | JOSEPH SULTANA, JR | progress |
| 04/22/2026 | Fire-Resistance Rated Construction | JOSEPH SULTANA, JR | progress |
| 04/09/2026 | Fenestration and door U-factor and product ratings | — | energy_progress |
| 04/09/2026 | Fenestration areas | — | energy_progress |
| 04/09/2026 | Insulation placement and R values | — | energy_progress |
| 04/09/2026 | Fenestration air leakage | — | energy_progress |