← Back
Two stories - detached, small or mid-size
69-66 180 STREET
QUEENS · Fresh Meadows-Utopia · BIN 4153488
💬 Discuss this project
1935Year Built
2Stories
A1Building Class
R2AZoning
1,288 sfGross Floor Area
1Units
Two stories - detached, small or mid-size · 4,000 sf lot · 0.32 FAR built · Flood zone X
Locations of Work
ArchitecturePlumbing
Roof1p · 1 filing · 10 docs
Floor 11p · 1 filing · 10 docs
Cellar3p · 1 filing · 10 docs
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
AMINOV DESIGN ENGINEER, PC105/31/2024
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
A D BUILDING SOLUTIONS203/21/2026
Building Lifecycle
All (40)Filed (1)Objection (18)Special Inspection (21)
10/15/2024
Special inspection requirement — Duct leakage testing, insulation and design
09/10/2024
Objection raised — Zoning
09/10/2024
Objection resolved — Addressed
06/10/2024
Objection raised — Zoning
06/10/2024
Objection resolved — Addressed
06/10/2024
Objection raised — Scope
06/10/2024
Objection resolved — Addressed
06/10/2024
Objection raised — Admin
06/10/2024
Objection resolved — Addressed
06/10/2024
Objection raised — Zoning
06/10/2024
Objection resolved — Addressed
06/10/2024
Objection raised — Other
06/10/2024
Objection resolved — Addressed
06/10/2024
Objection raised — Zoning
06/10/2024
Objection resolved — Addressed
06/10/2024
Objection raised — Current Topo verification requ
06/10/2024
Objection resolved — Addressed
06/10/2024
Objection raised — Zoning
06/10/2024
Objection resolved — Addressed
05/31/2024
Filed — Alteration CO
Q01058879-I1
05/30/2024
Special inspection requirement — Structural Stability – Alterations of existing buildings
05/30/2024
Special inspection requirement — Mechanical Systems
05/30/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
05/30/2024
Special inspection requirement — Fire-Resistance Rated Construction
05/30/2024
Special inspection requirement — Final
05/30/2024
Special inspection requirement — Air barrier - visual inspection
05/30/2024
Special inspection requirement — Fenestration areas
05/30/2024
Special inspection requirement — Electric vehicle service equipment requirements
05/30/2024
Special inspection requirement — HVAC-R and service water heating equipment
05/30/2024
Special inspection requirement — Permanent certificate
05/30/2024
Special inspection requirement — HVAC-R and service water heating system controls
05/30/2024
Special inspection requirement — Insulation placement and R values
05/30/2024
Special inspection requirement — HVAC-R and service water piping design and insulation
05/30/2024
Special inspection requirement — Fenestration air leakage
05/30/2024
Special inspection requirement — Maintenance information
05/30/2024
Special inspection requirement — Air barrier — testing
05/30/2024
Special inspection requirement — Fenestration and door U-factor and product ratings
05/30/2024
Special inspection requirement — Interior lighting power
05/30/2024
Special inspection requirement — Energy Code Compliance Inspections
05/30/2024
Special inspection requirement — Ventilation and air distribution system
Nothing on file for this building.
1 project · most recent 05/08/2026
General Wiring
FiledStatusContractorScope
05/08/2026Permit IssuedALL BALANCED ELECTRICAL INC.General Wiring
▾Special Inspection Requirements (DOB NOW) — 21
DateRequirementInspectorRole
10/15/2024Duct leakage testing, insulation and design—energy_progress
05/30/2024Structural Stability – Alterations of existing buildings—special
05/30/2024Mechanical Systems—special
05/30/2024Fire-Resistant Penetrations and Joints—special
05/30/2024Fire-Resistance Rated Construction—progress
05/30/2024Final—progress
05/30/2024Air barrier - visual inspection—energy_progress
05/30/2024Fenestration areas—energy_progress
05/30/2024Electric vehicle service equipment requirements—energy_progress
05/30/2024HVAC-R and service water heating equipment—energy_progress
05/30/2024Permanent certificate—energy_progress
05/30/2024HVAC-R and service water heating system controls—energy_progress
05/30/2024Insulation placement and R values—energy_progress
05/30/2024HVAC-R and service water piping design and insulation—energy_progress
05/30/2024Fenestration air leakage—energy_progress
05/30/2024Maintenance information—energy_progress
05/30/2024Air barrier — testing —energy_progress
05/30/2024Fenestration and door U-factor and product ratings—energy_progress
05/30/2024Interior lighting power—energy_progress
05/30/2024Energy Code Compliance Inspections—progress
05/30/2024Ventilation and air distribution system—energy_progress
▾Documents — 12 on file (BIS + DOB NOW)
▸Plans & Drawings2
▸DOB NOWPlans/Sketch2
08/22/2026Q01058879-S1Request digital key ↗
08/22/2026Q01058879-I1Request digital key ↗
▸Zoning, Tax Lot & Property Records2
▸DOB NOWZD1: DOB Zoning Diagram1
08/13/2026Q01058879-I1Open ↗
▸DOB NOWHouse Number Verification: TOPO Stamp1
08/13/2026Q01058879-I1Open ↗
▸Seals & Professional Certifications1
▸DOB NOWDPL-1: Design Professional Seal & Signature1
08/13/2026Q01058879-I1Open ↗
▸Safety & Tenant Protection1
▸DOB NOWStreet Tree Checklist1
08/13/2026Q01058879-I1Open ↗
▸Environmental & Asbestos2
▸DOB NOWDEP ACP-5: Asbestos Assessment Report2
08/13/2026Q01058879-S1Open ↗
08/13/2026Q01058879-I1Open ↗
▸Other Documents4
▸DOB NOWPlot Diagram1
08/13/2026Q01058879-I1Open ↗
▸DOB NOWProperty Ownership Certification1
08/13/2026Q01058879-I1Open ↗
▸DOB NOWSite Survey: Initial1
08/13/2026Q01058879-I1Open ↗
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone1
08/13/2026Q01058879-I1Open ↗