← Back
Two stories - detached, small or mid-size
69-86 182 STREET
QUEENS · BIN 4153573
💬 Discuss this project
1940Year Built
2Stories
A1Building Class
R2AZoning
1,350 sfGross Floor Area
1Units
Two stories - detached, small or mid-size · 4,600 sf lot · 0.29 FAR built · Flood zone X
Locations of Work
ArchitectureGeneral
Roof1p · 1 filing · 20 docs
Floor 27p · 2 filings · 20 docs
Floor 11p · 1 filing · 20 docs
Cellar1p · 1 filing · 20 docs
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
TRINITY SOLAR LLC305/13/2026
GERALD CALIENDO ARCHITECTS512/19/2025
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
ACA ASSOCIATES103/21/2026
GERALD J. CALIENDO R.A., P.C.503/21/2026
GERALD J CALIENDO R A P C503/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
KHAIT, SElectrical103/21/2026
LACLAIR, KEVINElectrical103/21/2026
N Y WATER MAIN & SEWER SEElectrical103/21/2026
SB RENOVATION & MODELINGGeneral Contractor104/09/2026
TJAR GROUP CORPGeneral Contractor107/08/2026
TRINITY SOLAR LLCGeneral Contractor107/08/2026
DPH PLUMBING & HTG CORPPlumbing107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
IKRA CONSULTING LLC7032305/13/2026
AA BUILDING & INSPECTION1519612/19/2025
Building Lifecycle
All (63)Filed (8)Permit Issued (4)Signed Off (4)Inspection (5)Objection (12)Special Inspection (30)
05/15/2026
Signed off — Alteration
Installation of solar system on the roof as per plan. No change in use, egress or occupancy
Q01260904-I1
05/14/2026
Special inspection requirement — Air barrier - visual inspection
Ayracon Almaraz
05/14/2026
Special inspection requirement — Final
Ayracon Almaraz
05/14/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
MD MOSTAFA
05/14/2026
Special inspection requirement — Energy Code Compliance Inspections
Ayracon Almaraz
05/13/2026
Filed — Alteration
Installation of solar system on the roof as per plan. No change in use, egress or occupancy
Q01260904-P3
05/13/2026
Special inspection requirement — Energy Code Compliance Inspections
Ayracon Almaraz
05/13/2026
Special inspection requirement — Air barrier - visual inspection
Ayracon Almaraz
05/13/2026
Special inspection requirement — Final
Ayracon Almaraz
05/13/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
MD MOSTAFA
05/06/2026
Filed — Alteration
Installation of solar system on the roof as per plan. No change in use, egress or occupancy
Q01260904-P2
05/06/2026
Special inspection requirement — Air barrier - visual inspection
Ayracon Almaraz
05/06/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
MD MOSTAFA
05/06/2026
Special inspection requirement — Energy Code Compliance Inspections
Ayracon Almaraz
05/06/2026
Special inspection requirement — Final
Ayracon Almaraz
03/18/2026
Signed off — Alteration
HEREWITH FILING ALTERATION IN CONJUNCTION WITH ALT #Q01126319-I1 FOR PLUMBING WORK IN CELLAR, FIRST, SECOND & OSP AS PER PLANS FILED.
Q01126319-S1
02/11/2026
Signed off — Alteration
HEREWITH FILING ALTERATION IN CONJUNCTION WITH ALT #Q01126319-I1 FOR PLUMBING WORK IN CELLAR, FIRST, SECOND & OSP AS PER PLANS FILED.
Q01126319-I1
02/06/2026
Signed off — Alteration
HEREWITH FILE ALTERATION IN ORDER TO ERECT TEMPORARY CONSTRUCTION PLYWOOD FENCE.
Q01118260-I1
01/29/2026
Inspection — Certified Storm Drainage-ST-Fixtures-Finish
Certified
View inspection ↗
12/19/2025
Filed — Alteration
HEREWITH FILING ALTERATION IN CONJUNCTION WITH ALT #Q01126319-I1 FOR PLUMBING WORK IN CELLAR, FIRST, SECOND & OSP AS PER PLANS FILED.
Q01126319-P2
11/28/2025
Special inspection requirement — HVAC-R and service water heating equipment
Younes Abouyaala
11/28/2025
Special inspection requirement — Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation
Younes Abouyaala
11/28/2025
Special inspection requirement — Subsurface Investigations (Borings/Test Pits)
FAHAD FATEH
11/28/2025
Special inspection requirement — Energy Code Compliance Inspections
Younes Abouyaala
11/28/2025
Special inspection requirement — Maintenance information
Younes Abouyaala
11/28/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
Younes Abouyaala
11/28/2025
Special inspection requirement — HVAC-R and service water piping design and insulation
Younes Abouyaala
11/28/2025
Special inspection requirement — Permanent certificate
Younes Abouyaala
08/01/2025
Permit issued — Solar
Q01260904-I1-SL
07/30/2025
Filed — Alteration
Installation of solar system on the roof as per plan. No change in use, egress or occupancy
Q01260904-I1
04/15/2025
Inspection — Certified Gas-Gas-Piping-Roughing
Certified
View inspection ↗
04/15/2025
Inspection — Certified Storm Drainage-ST-Piping-Underground
Certified
View inspection ↗
04/15/2025
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
03/26/2025
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Underground
Certified
View inspection ↗
03/19/2025
Permit issued — Plumbing
Q01126319-S1-PL
01/27/2025
Objection raised — Other
01/27/2025
Objection resolved — Addressed
01/17/2025
Objection resolved — Addressed
01/09/2025
Objection raised — Other
12/29/2024
Filed — Alteration
HEREWITH FILING ALTERATION IN CONJUNCTION WITH ALT #Q01126319-I1 FOR PLUMBING WORK IN CELLAR, FIRST, SECOND & OSP AS PER PLANS FILED.
Q01126319-P1
12/27/2024
Special inspection requirement — Final
NAVEEN KUMAR
12/27/2024
Special inspection requirement — Footing and Foundation
Younes Abouyaala
12/27/2024
Special inspection requirement — Structural Wood Frame
Younes Abouyaala
12/27/2024
Special inspection requirement — Air barrier - visual inspection
Younes Abouyaala
12/27/2024
Special inspection requirement — Fenestration air leakage
Younes Abouyaala
12/27/2024
Special inspection requirement — Lighting controls
Younes Abouyaala
12/27/2024
Special inspection requirement — Air barrier continuity plan testing
Younes Abouyaala
12/27/2024
Special inspection requirement — Fenestration and door U-factor and product ratings
Younes Abouyaala
12/27/2024
Special inspection requirement — Fenestration areas
Younes Abouyaala
12/27/2024
Special inspection requirement — Duct leakage testing, insulation and design
Younes Abouyaala
12/09/2024
Permit issued — General Construction
Q01126319-I1-GC-CX
12/03/2024
Filed — Alteration
HEREWITH FILING ALTERATION IN CONJUNCTION WITH ALT #Q01126319-I1 FOR PLUMBING WORK IN CELLAR, FIRST, SECOND & OSP AS PER PLANS FILED.
Q01126319-S1
11/22/2024
Permit issued — Construction Fence
Q01118260-I1-FN
11/20/2024
Objection resolved — Addressed
11/04/2024
Objection resolved — Addressed
11/04/2024
Objection resolved — Addressed
11/01/2024
Objection resolved — Addressed
10/31/2024
Objection raised — Zoning
10/31/2024
Objection raised — Other
10/31/2024
Objection raised — Admin
Latest 60 of 63 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSolarSigned-offTRINITY SOLAR LLC08/01/2025
DOB NOWPlumbingSigned-offDPH PLUMBING & HTG CORP03/19/2025
DOB NOWGeneral ConstructionSigned-offSB RENOVATION & MODELING12/09/2024
DOB NOWConstruction FenceSigned-offTJAR GROUP CORP11/22/2024
BISOTISSUEDTRINITY SOLAR LLC08/02/2022
3 projects · most recent 10/16/2025
General Wiring
FiledStatusContractorScope
10/16/2025CompleteREDLINE ELECTRIC INC—
03/05/2025CompleteNAS ELECTRIC CORPGeneral Wiring
08/08/2022CompleteREDLINE ELECTRIC INC—
▾Field Inspections (DOB CAP) — 5
DateTypeResultReport
01/29/2026Certified Storm Drainage-ST-Fixtures-FinishCertifiedView ↗
04/15/2025Certified Gas-Gas-Piping-RoughingCertifiedView ↗
04/15/2025Certified Storm Drainage-ST-Piping-UndergroundCertifiedView ↗
04/15/2025Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
03/26/2025Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 45
DateRequirementInspectorRole
05/14/2026Air barrier - visual inspectionAyracon Almarazenergy_progress
05/14/2026FinalAyracon Almarazprogress
05/14/2026Fire-Resistant Penetrations and JointsMD MOSTAFAspecial
05/14/2026Energy Code Compliance InspectionsAyracon Almarazprogress
05/13/2026Energy Code Compliance InspectionsAyracon Almarazprogress
05/13/2026Air barrier - visual inspectionAyracon Almarazenergy_progress
05/13/2026FinalAyracon Almarazprogress
05/13/2026Fire-Resistant Penetrations and JointsMD MOSTAFAspecial
05/06/2026Air barrier - visual inspectionAyracon Almarazenergy_progress
05/06/2026Fire-Resistant Penetrations and JointsMD MOSTAFAspecial
05/06/2026Energy Code Compliance InspectionsAyracon Almarazprogress
05/06/2026FinalAyracon Almarazprogress
11/28/2025HVAC-R and service water heating equipmentYounes Abouyaalaenergy_progress
11/28/2025Private On-Site Storm Water Disposal Systems-, and Detention Facilities, InstallationYounes Abouyaalaspecial
11/28/2025Subsurface Investigations (Borings/Test Pits)FAHAD FATEHspecial
11/28/2025Energy Code Compliance InspectionsYounes Abouyaalaprogress
11/28/2025Maintenance informationYounes Abouyaalaenergy_progress
11/28/2025Fire-Resistant Penetrations and JointsYounes Abouyaalaspecial
11/28/2025HVAC-R and service water piping design and insulationYounes Abouyaalaenergy_progress
11/28/2025Permanent certificateYounes Abouyaalaenergy_progress
12/27/2024FinalNAVEEN KUMARprogress
12/27/2024Footing and FoundationYounes Abouyaalaprogress
12/27/2024Structural Wood FrameYounes Abouyaalaprogress
12/27/2024Air barrier - visual inspectionYounes Abouyaalaenergy_progress
12/27/2024Fenestration air leakageYounes Abouyaalaenergy_progress
Latest 25 of 45.
▾Documents — 94 on file (BIS + DOB NOW)
▸Plans & Drawings8
▸DOB NOWPlans/Sketch8
08/21/2026Q01118260-I1Request digital key ↗
08/18/2026Q01126319-I1Request digital key ↗
08/18/2026Q01126319-P2Request digital key ↗
Showing 3 of 8 on file for this type
▸Applications & Permits6
▸BISPLAN / WORK APPROVAL APPLICATION5
05/02/2023440737767Open ↗
04/21/2023440737767Open ↗
03/07/2023440737767Open ↗
Showing 3 of 5 on file for this type
▸BISWORK PERMIT APPLICATION1
08/02/2022440737767Open ↗
▸Zoning, Tax Lot & Property Records2
▸DOB NOWZD1: DOB Zoning Diagram2
08/18/2026Q01126319-I1Open ↗
08/13/2026Q01126319-P1Open ↗
▸Seals & Professional Certifications34
▸DOB NOWProgress Inspector Seal & Signature14
09/02/2026Q01126319-P2Open ↗
09/02/2026Q01126319-P2Open ↗
08/29/2026Q01126319-P1Open ↗
Showing 3 of 14 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature9
09/02/2026Q01126319-P2Open ↗
09/02/2026Q01126319-P2Open ↗
09/02/2026Q01126319-P2Open ↗
Showing 3 of 9 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature8
08/21/2026Q01118260-I1Open ↗
08/18/2026Q01126319-I1Open ↗
08/18/2026Q01126319-S1Open ↗
Showing 3 of 8 on file for this type
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION1
07/31/2022440737767Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT1
07/31/2022440737767Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY1
07/31/2022440737767Open ↗
▸Safety & Tenant Protection1
▸BISTPP1: TENANT PROTECTION PLAN1
08/02/2022440737767Open ↗
▸Environmental & Asbestos8
▸DOB NOWDEP ACP-5: Asbestos Assessment Report7
08/18/2026Q01126319-S1Open ↗
08/18/2026Q01126319-I1Open ↗
08/16/2026Q01260904-P3Open ↗
Showing 3 of 7 on file for this type
▸BISASBESTOS: CERTIFICATION (DEP ACP5)1
07/31/2022440737767Open ↗
▸Energy Compliance9
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY2
06/06/2023440737767Open ↗
07/31/2022440737767Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY FOR ENERGY CODE PROGRESS INSPECTIONS1
07/31/2022440737767Open ↗
▸BISAIR SEALING AND INSULATION - VISUAL1
06/06/2023440737767Open ↗
▸BISNYCECC ANALYSIS1
07/31/2022440737767Open ↗
▸BISPTA4: SOLAR TAX ABATEMENT APPLICATION (PRELIMINARY)1
07/31/2022440737767Open ↗
▸BISPTA4: SOLAR TAX ABATEMENT APPLICATION (FINAL)1
06/06/2023440737767Open ↗
▸BISAS-BUILT ENERGY ANALYSIS (EN2)1
06/06/2023440737767Open ↗
▸BISENERGY CODE COMPLIANCE INSPECTIONS1
06/06/2023440737767Open ↗
▸Inspections & Test Reports9
▸DOB NOWSOIL REPORT4
08/18/2026Q01126319-S1Open ↗
08/18/2026Q01126319-I1Open ↗
08/13/2026Q01126319-P1Open ↗
Showing 3 of 4 on file for this type
▸BISTECHNICAL REPORT: RESPONSIBILITY2
06/06/2023440737767Open ↗
08/02/2022440737767Open ↗
▸DOB NOWTR4 Test Report and Plot Diagram2
08/13/2026Q01126319-S1Open ↗
08/13/2026Q01126319-I1Open ↗
▸BISFIRE-RESISTIVE RATED CONSTRUCTION1
06/06/2023440737767Open ↗
▸Approvals, Objections & Sign-offs4
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST1
06/07/2023440737767Open ↗
▸BISPTA4: TAX ABATEMENT ELIGIBILITY APPROVAL1
06/06/2023440737767Open ↗
▸BISFINAL1
06/06/2023440737767Open ↗
▸DOB NOWUtility Company Final Acceptance Letter1
08/16/2026Q01260904-I1Open ↗
▸Cost, Insurance & Ownership2
▸BISCOST AFFIDAVIT1
07/31/2022440737767Open ↗
▸BISCOST AFFIDAVIT (FINAL): PW31
06/06/2023440737767Open ↗
▸Filing & Intake Forms3
▸BISADDITIONAL INFORMATION2
05/02/2023440737767Open ↗
03/07/2023440737767Open ↗
▸BISEFILING JOB APPLICATION COVER SHEET1
07/31/2022440737767Open ↗
▸Other Documents8
▸DOB NOWSite Survey: Initial2
08/18/2026Q01126319-I1Open ↗
08/13/2026Q01126319-P1Open ↗
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone2
08/18/2026Q01126319-I1Open ↗
08/13/2026Q01126319-P1Open ↗
▸DOB NOWPlot Diagram2
08/18/2026Q01126319-I1Open ↗
08/13/2026Q01126319-P1Open ↗
▸BISEXTERNAL FORMS - SUPPORTING DOCUMENTATION1
06/07/2023440737767Open ↗
▸DOB NOWAdjoining Owners Notification1
08/13/2026Q01126319-I1Open ↗