← Back
Two family frame
69 PILLING STREET
BROOKLYN · Bushwick (East) · BIN 3080275
💬 Discuss this project
1905Year Built
2Stories
B2Building Class
R6Zoning
3,000 sfGross Floor Area
2Units
Rent Stabilized33 Open Violations ▸FDNY Report ↗
Two family frame · Owner of record: 69 PILLING STREET LLC · 2,000 sf lot · 1.5 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralPlumbing
Roof4p · 1 filing · 20 docs
Floor 32p · 1 filing · 20 docs
Floor 2
Floor 1
Cellar12p · 1 filing · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
NEW YORK VISTA REALTY2207/08/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
10/12/2022$850K—Private party → Private party$283/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
A&B ENGINEERING AND LAND SURVEYING601/06/2024
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
DISTINCT ENTERPRISES1203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
BADINI CONSTRUCTION CORPGeneral Contractor903/21/2026
M & M PIPING AND HEATINGPlumbing207/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
JIAN ENGINEERING PLLC7397601/06/2024
Building Lifecycle
All (106)Filed (6)Permit Issued (5)Signed Off (4)Violation (37)Inspection (6)Objection (32)Special Inspection (16)
12/03/2024
Violation issued (HPD, closed)
I
04/15/2024
Signed off — Alteration
Plumbing work at exist. 2-fmly. dwell. as per plans, filed in conjunction w/appl. Job# B00844820-S3. Prop. work includes capping/removal/addition of plumbing fixtures, relocation/replacement of radiators, and installation of gas boiler & gas water heater.
B00844820-S3
04/15/2024
Signed off — Alteration
Plumbing work at exist. 2-fmly. dwell. as per plans, filed in conjunction w/appl. Job# B00844820-S3. Prop. work includes capping/removal/addition of plumbing fixtures, relocation/replacement of radiators, and installation of gas boiler & gas water heater.
B00844820-I1
04/15/2024
Signed off — Alteration
Plumbing work at exist. 2-fmly. dwell. as per plans, filed in conjunction w/appl. Job# B00844820-S3. Prop. work includes capping/removal/addition of plumbing fixtures, relocation/replacement of radiators, and installation of gas boiler & gas water heater.
B00844820-S1
04/15/2024
Signed off — Alteration
Plumbing work at exist. 2-fmly. dwell. as per plans, filed in conjunction w/appl. Job# B00844820-S3. Prop. work includes capping/removal/addition of plumbing fixtures, relocation/replacement of radiators, and installation of gas boiler & gas water heater.
B00844820-S4
04/11/2024
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
03/01/2024
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
01/25/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
JIAN DENG
01/23/2024
Objection resolved — Addressed
01/17/2024
Objection resolved — Addressed
01/12/2024
Objection raised — Scope
01/11/2024
Objection raised — Scope
01/06/2024
Filed — Alteration
Plumbing work at exist. 2-fmly. dwell. as per plans, filed in conjunction w/appl. Job# B00844820-S3. Prop. work includes capping/removal/addition of plumbing fixtures, relocation/replacement of radiators, and installation of gas boiler & gas water heater.
B00844820-P2
01/06/2024
Filed — Alteration
Plumbing work at exist. 2-fmly. dwell. as per plans, filed in conjunction w/appl. Job# B00844820-S3. Prop. work includes capping/removal/addition of plumbing fixtures, relocation/replacement of radiators, and installation of gas boiler & gas water heater.
B00844820-P1
01/02/2024
Special inspection requirement — Structural Stability – Alterations of existing buildings
JIAN DENG
01/02/2024
Special inspection requirement — Energy Code Compliance Inspections
JIAN DENG
01/02/2024
Special inspection requirement — Final
JIAN DENG
01/02/2024
Special inspection requirement — Fire-Resistance Rated Construction
JIAN DENG
01/02/2024
Special inspection requirement — Fenestration air leakage
JIAN DENG
01/02/2024
Special inspection requirement — Fenestration areas
JIAN DENG
01/02/2024
Special inspection requirement — Air barrier - visual inspection
JIAN DENG
01/02/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
JIAN DENG
01/02/2024
Special inspection requirement — Insulation placement and R values
JIAN DENG
01/02/2024
Special inspection requirement — Interior lighting power
JIAN DENG
01/02/2024
Special inspection requirement — Lighting in dwelling units
JIAN DENG
01/02/2024
Special inspection requirement — Fenestration and door U-factor and product ratings
JIAN DENG
12/22/2023
Inspection — No Access-Final PL - Up to 3 Requested Floors
No Access
View inspection ↗
12/21/2023
Special inspection requirement — Fire-Resistant Penetrations and Joints
JIAN DENG
11/28/2023
Violation issued (HPD, closed)
I
09/05/2023
Inspection — Certified Gas-Gas-Piping-Roughing
Certified
View inspection ↗
09/05/2023
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
09/05/2023
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Underground
Certified
View inspection ↗
08/08/2023
Permit issued — Plumbing
B00844820-S4-PL
07/14/2023
Permit issued — Structural
B00844820-S3-GC-CX
07/07/2023
Objection resolved — Addressed
06/28/2023
Permit issued — Structural
B00844820-S3-GC-CX
06/20/2023
Objection resolved — Addressed
06/16/2023
Objection resolved — Addressed
06/13/2023
Objection resolved — Addressed
06/07/2023
Objection raised — Energy
06/06/2023
Objection resolved — Addressed
06/06/2023
Objection resolved — Addressed
06/06/2023
Objection resolved — Addressed
06/06/2023
Objection resolved — Addressed
06/06/2023
Objection resolved — Addressed
06/05/2023
Objection raised — Scope
06/04/2023
Filed — Alteration
Plumbing work at exist. 2-fmly. dwell. as per plans, filed in conjunction w/appl. Job# B00844820-S3. Prop. work includes capping/removal/addition of plumbing fixtures, relocation/replacement of radiators, and installation of gas boiler & gas water heater.
B00844820-S4
05/30/2023
Permit issued — Plumbing
B00844820-S1-PL
05/15/2023
Objection raised — Other
05/15/2023
Objection raised — Structural
05/15/2023
Objection raised — Structural
05/15/2023
Objection raised — Scope
05/15/2023
Objection raised — Scope
05/15/2023
Objection raised — Inspections
05/15/2023
Objection raised — Scope
05/11/2023
Filed — Alteration
Plumbing work at exist. 2-fmly. dwell. as per plans, filed in conjunction w/appl. Job# B00844820-S3. Prop. work includes capping/removal/addition of plumbing fixtures, relocation/replacement of radiators, and installation of gas boiler & gas water heater.
B00844820-S3
05/04/2023
Permit issued — Mechanical Systems
B00844820-I1-GC-CX
05/01/2023
Filed — Alteration
Plumbing work at exist. 2-fmly. dwell. as per plans, filed in conjunction w/appl. Job# B00844820-S3. Prop. work includes capping/removal/addition of plumbing fixtures, relocation/replacement of radiators, and installation of gas boiler & gas water heater.
B00844820-S1
04/29/2023
Special inspection requirement — Fire-Resistant Penetrations and Joints
JIAN DENG
04/29/2023
Special inspection requirement — Energy Code Compliance Inspections
JIAN DENG
Latest 60 of 106 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWPlumbingSigned-offM & M PIPING AND HEATING08/08/2023
DOB NOWStructuralSigned-offBADINI CONSTRUCTION CORP07/14/2023
DOB NOWStructuralSigned-offBADINI CONSTRUCTION CORP06/28/2023
DOB NOWPlumbingSigned-offM & M PIPING AND HEATING05/30/2023
DOB NOWMechanical SystemsSigned-offBADINI CONSTRUCTION CORP05/04/2023
2 projects · most recent 06/28/2023
General Wiring
FiledStatusContractorScope
06/28/2023CompleteBEATON ELECTRIC CORPORATIGeneral Wiring
06/05/2023CompleteBEATON ELECTRIC CORPORATI—
▾Field Inspections (DOB CAP) — 6
DateTypeResultReport
04/11/2024Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
03/01/2024Pass-Final PL - Up to 3 Requested FloorsPassView ↗
12/22/2023No Access-Final PL - Up to 3 Requested FloorsNo AccessView ↗
09/05/2023Certified Gas-Gas-Piping-RoughingCertifiedView ↗
09/05/2023Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
09/05/2023Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 16
DateRequirementInspectorRole
01/25/2024Fire-Resistant Penetrations and JointsJIAN DENGspecial
01/02/2024Structural Stability – Alterations of existing buildingsJIAN DENGspecial
01/02/2024Energy Code Compliance InspectionsJIAN DENGprogress
01/02/2024FinalJIAN DENGprogress
01/02/2024Fire-Resistance Rated ConstructionJIAN DENGprogress
01/02/2024Fenestration air leakageJIAN DENGenergy_progress
01/02/2024Fenestration areasJIAN DENGenergy_progress
01/02/2024Air barrier - visual inspectionJIAN DENGenergy_progress
01/02/2024Fire-Resistant Penetrations and JointsJIAN DENGspecial
01/02/2024Insulation placement and R valuesJIAN DENGenergy_progress
01/02/2024Interior lighting powerJIAN DENGenergy_progress
01/02/2024Lighting in dwelling unitsJIAN DENGenergy_progress
01/02/2024Fenestration and door U-factor and product ratingsJIAN DENGenergy_progress
12/21/2023Fire-Resistant Penetrations and JointsJIAN DENGspecial
04/29/2023Fire-Resistant Penetrations and JointsJIAN DENGspecial
04/29/2023Energy Code Compliance InspectionsJIAN DENGprogress
▾Documents — 34 on file (BIS + DOB NOW)
▸Plans & Drawings6
▸DOB NOWPlans/Sketch6
08/27/2026B00844820-I1Request digital key ↗
08/27/2026B00844820-S4Request digital key ↗
08/27/2026B00844820-S3Request digital key ↗
Showing 3 of 6 on file for this type
▸Seals & Professional Certifications22
▸DOB NOWProgress Inspector Seal & Signature11
09/02/2026B00844820-S1Open ↗
08/28/2026B00844820-P2Open ↗
08/28/2026B00844820-P2Open ↗
Showing 3 of 11 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature6
08/27/2026B00844820-P2Open ↗
08/27/2026B00844820-P1Open ↗
08/27/2026B00844820-S4Open ↗
Showing 3 of 6 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature5
09/02/2026B00844820-S1Open ↗
08/28/2026B00844820-S4Open ↗
08/28/2026B00844820-P2Open ↗
Showing 3 of 5 on file for this type
▸Environmental & Asbestos6
▸DOB NOWDEP ACP-5: Asbestos Assessment Report6
08/27/2026B00844820-S4Open ↗
08/27/2026B00844820-S3Open ↗
08/27/2026B00844820-S1Open ↗
Showing 3 of 6 on file for this type