1896Year Built
5Stories
C4Building Class
R7-2Zoning
7,810 sfGross Floor Area
10Units
Rent Stabilized2 Active Violations ▸FDNY Report ↗
Old law tenement · Owner of record: Thompson 69 · 2,150 sf lot · 3.63 FAR built · Flood zone X500
Locations of Work
ArchitecturePlumbing
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
Floor 2Unit 210p · 1 filing · 20 docs
Floor 15p · 1 filing · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
NY Reop2507/08/2026
Thompson 69703/22/2026
▾Design Consultants (Architect / Engineer of Record)
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
HTX Building Consulting403/21/2026
Youber Design803/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
AMC Plumbing, Heating & CLNGPlumbing407/08/2026
Meridian Construction GroupGeneral Contractor303/21/2026
Kings Builders GroupGeneral Contractor103/21/2026
KTC Design GroupGeneral Contractor103/21/2026
Sing ConstructionGeneral Contractor107/08/2026
Chinatown Plumbing & HeatingPlumbing103/21/2026
G & L PlumbingPlumbing107/08/2026
Master Fire Prevention SystemFire Protection103/21/2026
A-1 Ewater Main and SewerPlumbing104/13/1995
Ava PLG & HeatingPlumbing112/16/1994
H&M ContractorsGeneral Contractor107/06/2015
KC Plumbing & Heating ContractingPlumbing111/01/1999
K.C. Plumbing & HeatingPlumbing211/29/1999
Mainland Plumbing & HeatingPlumbing110/28/1996
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
Indetail Design Architect4828408/14/2023
Sustainable Design Engineering1404104/12/2021
Building Lifecycle
10/16/2026
Boiler inspection report filed
Initial · no defects · Accepted
08/08/2025
Boiler inspection report filed
Initial · no defects · Accepted
11/22/2024
§27-2107 ADM code owner failed to file a valid registration statement with the department as required by ADM code §27-2097 and is therefore subject…
HPD violation · closed
11/01/2024
Boiler inspection report filed
Initial · no defects · Accepted
11/10/2023
Boiler inspection report filed
Initial · no defects · Accepted
82 history events on file for this building. Sign in free to see the full history. Sign in · Create account
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWPlumbingSigned-offAMC Plumbing, Heating & CLNG05/24/2023
DOB NOWGeneral ConstructionSigned-offSing Construction05/12/2023
DOB NOWPlumbingSigned-offG & L Plumbing05/25/2021
DOB NOWGeneral ConstructionPermit IssuedMeridian Construction Group05/14/2021
BISPLISSUEDChinatown Plumbing & Heating04/19/2019
BISOTISSUEDKTC Design Group04/12/2019
BISOTISSUEDH&M Contractors07/06/2015
BISOTISSUEDKings Builders Group07/26/2013
BISOTISSUEDKings Builders Group02/21/2013
BISPLISSUEDK & BH Plumbing & Heating11/29/1999
BISBLISSUEDK & BH Plumbing & Heating11/29/1999
BISOTISSUEDKC Plumbing & Heating Contracting11/03/1999
BISPLISSUEDK & BH Plumbing & Heating11/01/1999
BISPLISSUEDMainland Plumbing & Heating10/28/1996
BISOTISSUEDYellow Dragon Construction09/18/1996
BISPLISSUEDA-1 Ewater Main and Sewer04/13/1995
BISFPISSUEDMaster Fire Systems01/13/1995
BISPLISSUEDAccess Plumbing & Heating12/16/1994
BISOTISSUEDD.b.a.country Cafe12/07/1994
BISOTISSUEDYellow Dragon Construction11/29/1991
1 project · most recent 07/20/2021
Gas Water/Sanitary
FiledStatusContractorScope
07/20/2021Signed-offG & L PlumbingGas, Water/Sanitary
5 projects · most recent 10/13/2026
General Wiring
FiledStatusContractorScope
10/13/2026Permit IssuedControl Spec Electrical SystemGeneral Wiring
05/22/2023CompleteA.C. Morgan ElectricGeneral Wiring
04/29/2021Permit IssuedElpo Electrical ContgGeneral Wiring
03/05/2020CompleteA Electrical Main ServiceGeneral Wiring
05/20/2019CompleteP.L. Electrical Contracting—
▾Field Inspections (DOB CAP) — 10
DateTypeResultReport
08/16/2023Pass-Final General Construction Non-Directive 14PassView ↗
07/31/2023Fail-Final General Construction Non-Directive 14FailView ↗
07/24/2023Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
07/24/2023Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
06/09/2023Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
07/26/2021Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
07/26/2021Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
06/15/2021Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
06/15/2021Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
06/04/2021Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 25
DateRequirementInspectorRole
08/14/2023Fire-Resistance Rated ConstructionJonathan Chinprogress
08/14/2023Energy Code Compliance InspectionsJonathan Chinprogress
08/14/2023Insulation placement and R valuesJonathan Chinenergy_progress
08/14/2023Lighting in dwelling unitsJonathan Chinenergy_progress
08/14/2023Tenant Protection Plan ComplianceJonathan Chinspecial
08/14/2023Fire-Resistant Penetrations and JointsJonathan Chinspecial
08/11/2023Tenant Protection Plan Compliance—special
08/11/2023Lighting in dwelling unitsJonathan Chinenergy_progress
08/11/2023Insulation placement and R valuesJonathan Chinenergy_progress
08/11/2023Fire-Resistance Rated ConstructionJonathan Chinprogress
08/11/2023Fire-Resistant Penetrations and JointsJonathan Chinspecial
08/11/2023Energy Code Compliance InspectionsJonathan Chinprogress
07/26/2023Tenant Protection Plan Compliance—special
07/25/2023Energy Code Compliance InspectionsJonathan Chinprogress
07/25/2023Fire-Resistance Rated ConstructionJonathan Chinprogress
07/25/2023Insulation placement and R valuesJonathan Chinenergy_progress
07/25/2023Lighting in dwelling unitsJonathan Chinenergy_progress
07/25/2023Fire-Resistant Penetrations and JointsJonathan Chinspecial
05/09/2023Energy Code Compliance InspectionsJonathan Chinprogress
05/09/2023Tenant Protection Plan ComplianceJonathan Chinspecial
05/09/2023Fire-Resistant Penetrations and JointsJonathan Chinspecial
03/02/2021Fire-Resistant Penetrations and JointsKenny Makspecial
03/02/2021Interior lighting powerKenny Makenergy_progress
03/02/2021FinalKenny Makprogress
03/02/2021Energy Code Compliance InspectionsKenny Makprogress