| Owner | Filings | Most Recent |
|---|---|---|
| 695 DEKALB LLC | 1 | 03/22/2026 |
| MJH CONSTRUCTION | 5 | 03/22/2026 |
| IGLESIA AMOR DEDIOS INC | 1 | 03/22/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 12/11/2024 | $1.8M | — | — → — | $379/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| LESTER KATZ, NCARB | 6 | 06/26/2025 |
| VASILIOS ARTEMIOU PE | 8 | 06/09/2025 |
| AG ENGINEERING PLLC | 1 | 04/30/2025 |
| Representative | Filings | Most Recent |
|---|---|---|
| XPDITE GROUP LLC (104) | 14 | 03/21/2026 |
| ZV Drafting | 1 | 03/21/2026 |
| XPDITE GROUP LLC 104 | 5 | 03/21/2026 |
| XPDITE GROUP LLC 105 | 4 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| MJH CONSTRUCTION CORP | General Contractor | 5 | 07/08/2026 |
| TARGET PIPING NY LLC | Fire Protection | 1 | 07/08/2026 |
| BSC SERVICES LLC | General Contractor | 1 | 07/08/2026 |
| B&B MECH PLBG & HTG LLC | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| SHAHRISH SHUVO ENGINEERIN | 8524 | 7 | 06/26/2025 |
| HRF SERVICES CORP | 5616 | 7 | 06/09/2025 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Mechanical Systems | Signed-off | MJH CONSTRUCTION CORP | 06/05/2025 |
| DOB NOW | Construction Fence | Signed-off | MJH CONSTRUCTION CORP | 05/01/2025 |
| DOB NOW | General Construction | Permit Issued | MJH CONSTRUCTION CORP | 04/21/2025 |
| DOB NOW | Sprinklers | Signed-off | TARGET PIPING NY LLC | 02/10/2025 |
| DOB NOW | Plumbing | Signed-off | TARGET PIPING NY LLC | 02/10/2025 |
| DOB NOW | General Construction | Permit Issued | MJH CONSTRUCTION CORP | 12/18/2024 |
| DOB NOW | General Construction | Permit Issued | BSC SERVICES | 09/04/2024 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 06/26/2025 | Signed-off | MJH CONSTRUCTION CORP | Heating and Air Conditioning Systems | Heat / Cool |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/26/2025 | Signed-off | TARGET PIPING NY LLC | Sprinkler System |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/26/2025 | Signed-off | TARGET PIPING NY LLC | Gas, Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 01/06/2025 | Complete | S&R ELECTRICAL & MECHANIC | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/26/2025 | Signed-off | MJH CONSTRUCTION CORP | Fence |
| Date | Type | Result | Report |
|---|---|---|---|
| 07/16/2025 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 07/16/2025 | Pass-Final PL - Up to 9 Requested Floors | Pass | View ↗ |
| 07/09/2025 | Pass-Final SP - Up to 9 Requested Floors | Pass | View ↗ |
| 07/01/2025 | Fail-Final Curb Cut Non-Directive 14 | Fail | View ↗ |
| 06/24/2025 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 06/24/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 03/05/2025 | Pass-Final PL - Up to 9 Requested Floors | Pass | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 07/07/2025 | Fire-Resistance Rated Construction | FAHAD FATEH | progress |
| 07/07/2025 | Energy Code Compliance Inspections | FAHAD FATEH | progress |
| 07/07/2025 | Metering | FAHAD FATEH | energy_progress |
| 07/07/2025 | Exterior lighting power | FAHAD FATEH | energy_progress |
| 07/07/2025 | Fenestration and door U-factor and product ratings | FAHAD FATEH | energy_progress |
| 07/07/2025 | Lighting in dwelling units | FAHAD FATEH | energy_progress |
| 07/07/2025 | Air barrier - visual inspection | FAHAD FATEH | energy_progress |
| 07/07/2025 | Interior lighting power | FAHAD FATEH | energy_progress |
| 07/07/2025 | Lighting controls | FAHAD FATEH | energy_progress |
| 07/07/2025 | Maintenance information | FAHAD FATEH | energy_progress |
| 07/07/2025 | Fenestration air leakage | FAHAD FATEH | energy_progress |
| 07/07/2025 | Fenestration areas | FAHAD FATEH | energy_progress |
| 07/07/2025 | Insulation placement and R values | FAHAD FATEH | energy_progress |
| 07/07/2025 | Fire-Resistant Penetrations and Joints | FAHAD FATEH | special |
| 07/07/2025 | Structural Stability – Alterations of existing buildings | FAHAD FATEH | special |
| 07/01/2025 | Maintenance information | FAHAD FATEH | energy_progress |
| 07/01/2025 | Duct leakage testing, insulation and design | FAHAD FATEH | energy_progress |
| 07/01/2025 | HVAC-R and service water piping design and insulation | FAHAD FATEH | energy_progress |
| 07/01/2025 | Fire-Resistant Penetrations and Joints | FAHAD FATEH | special |
| 07/01/2025 | Heating Systems | FAHAD FATEH | special |
| 07/01/2025 | Structural Stability – Alterations of existing buildings | FAHAD FATEH | special |
| 07/01/2025 | Mechanical Systems | FAHAD FATEH | special |
| 07/01/2025 | Energy Code Compliance Inspections | FAHAD FATEH | progress |
| 07/01/2025 | Final | FAHAD FATEH | progress |
| 07/01/2025 | HVAC-R and service water heating system controls | FAHAD FATEH | energy_progress |