| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/24/2026 | Permit Issued | JADA PLUMBING & HTG LLC | Gas, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/11/2021 | Permit Issued | TRIANGLE ELECTRIC INC. | 2 meters |
| 02/11/2020 | Permit Issued | LEKTRIC INSTALLATIONS COR | 2 meters, 2 new_meters |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 03/13/2017 | $1.1M | — | — → — | $379/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| AUDRA MANZANO ARCHITECT PLLC | 2 | 08/24/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| NY CONSTRUCTION&STONE INC | General Contractor | 1 | 09/12/2026 |
| JADA PLUMBING & HTG LLC | Plumbing | 1 | 09/13/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| ADAL ENGINEERING PLLC | 4205 | 1 | 08/24/2026 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Permit Issued | JADA PLUMBING & HTG LLC | 09/11/2026 |
| DOB NOW | General Construction | Permit Issued | NY CONSTRUCTION&STONE INC | 09/10/2026 |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 08/24/2026 | HVAC-R and service water piping design and insulation | AUDRA MANZANO | energy_progress |
| 08/24/2026 | Fire-Resistant Penetrations and Joints | Dariusz Makara | special |
| 08/24/2026 | Energy Code Compliance Inspections | AUDRA MANZANO | progress |
| 08/23/2026 | Lighting in dwelling units | AUDRA MANZANO | energy_progress |
| 08/23/2026 | Fire-Resistant Penetrations and Joints | Dariusz Makara | special |
| 08/23/2026 | Metering | AUDRA MANZANO | energy_progress |
| 08/23/2026 | Maintenance information | AUDRA MANZANO | energy_progress |
| 08/23/2026 | Energy Code Compliance Inspections | AUDRA MANZANO | progress |
| 08/23/2026 | Fire-Resistance Rated Construction | AUDRA MANZANO | progress |
| 08/21/2026 | Final | AUDRA MANZANO | progress |