| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 07/01/2022 | $2.3M | — | Private party → 760 ELVIRA LLC | — not available |
| Firm | Filings | Most Recent |
|---|---|---|
| SHMUEL D. FLAUM, ARCHITECT | 11 | 08/04/2026 |
| NARESH MAHANGU | 1 | 09/18/2025 |
| ENGINEERING PROFESSIONAL SERVICE P. | 2 | 11/19/2024 |
| ARNOLD MONTAG ARCHITECT AM/PM DESI | 1 | 11/18/2022 |
| Representative | Filings | Most Recent |
|---|---|---|
| DEMOWORKS EXPEDITING | 2 | 03/21/2026 |
| MEP DESIGNS | 4 | 03/21/2026 |
| S R SOLAR DESIGN | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| ALL-BORO REHAB CONSTRCT C | General Contractor | 6 | 07/08/2026 |
| ALL-BORO REHAB CONST CORP | Plumbing | 2 | 07/08/2026 |
| SAFETY FIRE SPRINKLER CORP | Fire Protection | 1 | 07/08/2026 |
| J SYNERGY GREEN INC | General Contractor | 1 | 04/09/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| DAVID KATZ, P.E. | 6087 | 9 | 08/04/2026 |
| SHMUEL D. FLAUM, ARCHITEC | 4278 | 9 | 08/04/2026 |
| NKM ENGINEERING PLLC | 6244 | 1 | 09/18/2025 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Solar | Signed-off | J SYNERGY GREEN | 10/07/2025 |
| DOB NOW | Sprinklers | Signed-off | ALL-BORO REHAB CONST CORP | 08/12/2025 |
| DOB NOW | Plumbing | Signed-off | SAFETY FIRE SPRINKLER CORP | 04/25/2025 |
| DOB NOW | Curb Cut | Signed-off | ALL-BORO REHAB CONSTRCT C | 04/22/2025 |
| DOB NOW | Plumbing | Signed-off | ALL-BORO REHAB CONST CORP | 01/25/2024 |
| DOB NOW | Foundation | Permit Issued | ALL-BORO REHAB CONSTRCT C | 06/10/2023 |
| DOB NOW | Construction Fence | Signed-off | ALL-BORO REHAB CONSTRCT C | 05/09/2023 |
| DOB NOW | Construction Fence | Signed-off | ALL-BORO REHAB CONSTRCT C | 01/05/2023 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 08/04/2026 | Signed-off | ALL-BORO REHAB CONSTRCT C | Heating and Air Conditioning Systems | Heat / Cool Rheem RH1V3617STANJA 18,000 BTU · Ahu ×9 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/04/2026 | Signed-off | ALL-BORO REHAB CONST CORP | Gas, Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/27/2025 | Complete | GREEN LIGHT ELECL & MECH | — |
| 05/22/2025 | Complete | HIRSCHEL ELECTRICAL INC. | General Wiring |
| 11/28/2022 | Complete | HIRSCHEL ELECTRICAL INC. | 1 meters |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/04/2026 | Signed-off | ALL-BORO REHAB CONSTRCT C | Steel |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/04/2026 | Signed-off | ALL-BORO REHAB CONSTRCT C | Fence |
| Date | Type | Result | Report |
|---|---|---|---|
| 08/14/2025 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 06/10/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 05/27/2025 | Fail-Final CND-Occupancy Inspection | Fail | View ↗ |
| 05/19/2025 | Pass-Final Curb Cut Non-Directive 14 | Pass | View ↗ |
| 05/16/2025 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 05/01/2025 | Fail-Final Curb Cut Non-Directive 14 | Fail | View ↗ |
| 04/28/2025 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 11/08/2024 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 07/03/2024 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 04/09/2024 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 04/09/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 02/06/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 08/05/2026 | Ventilation and air distribution system | Shmuel Flaum | energy_progress |
| 08/05/2026 | Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation | Shmuel Flaum | special |
| 08/05/2026 | Subsurface Investigations (Borings/Test Pits) | ESHWAR KOSURI | special |
| 08/05/2026 | Subgrade Inspections | David Katz | special |
| 08/05/2026 | Mechanical Systems | Shmuel Flaum | special |
| 08/05/2026 | Fire-Resistant Penetrations and Joints | Shmuel Flaum | special |
| 08/05/2026 | Excavations - Sheeting, Shoring, and Bracing | David Katz | special |
| 08/05/2026 | Concrete - Cast-In-Place | Shmuel Flaum | special |
| 08/05/2026 | Structural Steel - Details | David Katz | special |
| 08/05/2026 | Final | David Katz | progress |
| 08/05/2026 | Fire-Resistance Rated Construction | Shmuel Flaum | progress |
| 08/05/2026 | Lowest Floor Elevation | Shmuel Flaum | progress |
| 08/05/2026 | Energy Code Compliance Inspections | Shmuel Flaum | progress |
| 08/05/2026 | Footing and Foundation | Shmuel Flaum | progress |
| 08/05/2026 | Structural Wood Frame | Shmuel Flaum | progress |
| 08/05/2026 | Preliminary | Shmuel Flaum | progress |
| 08/05/2026 | Air barrier — testing | Shmuel Flaum | energy_progress |
| 08/05/2026 | Insulation placement and R values | Shmuel Flaum | energy_progress |
| 08/05/2026 | Fenestration air leakage | Shmuel Flaum | energy_progress |
| 08/05/2026 | Electric vehicle service equipment requirements | Shmuel Flaum | energy_progress |
| 08/05/2026 | Permanent certificate | Shmuel Flaum | energy_progress |
| 08/05/2026 | Maintenance information | Shmuel Flaum | energy_progress |
| 08/05/2026 | HVAC-R and service water heating system controls | Shmuel Flaum | energy_progress |
| 08/05/2026 | Fenestration and door U-factor and product ratings | Shmuel Flaum | energy_progress |
| 08/05/2026 | HVAC-R and service water piping design and insulation | Shmuel Flaum | energy_progress |