| Owner | Filings | Most Recent |
|---|---|---|
| BEEKMAN TOWERS HOLDINGS | 51 | 09/13/2026 |
| NUVO DEVELOPMENT | 1 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| ASHRAF CORP | 7 | 12/09/2025 |
| STRUCTURAL ENGINEERING TECHNOLOGIES | 4 | 09/10/2025 |
| A&D ENGINEERING, PLLC | 6 | 08/26/2025 |
| ISSAC & STERN ARCHITECTS, P.C | 3 | 08/20/2025 |
| RICHARD WAINER ARCHITECT, PLLC | 1 | 01/24/2019 |
| Representative | Filings | Most Recent |
|---|---|---|
| NUAN DESIGN | 2 | 03/21/2026 |
| JM ZONING, LLC. | 13 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| DEXTERA CONSTRUCTION LLC | General Contractor | 17 | 07/08/2026 |
| DYNAMIX SCAFFOLD GROUP LL | General Contractor | 9 | 07/25/2026 |
| B&B MECH PLBG & HTG LLC | Plumbing | 2 | 07/08/2026 |
| WCK ELECTRIC CORP. | Electrical | 1 | 03/22/2026 |
| TARGET PIPING NY LLC | Fire Protection | 1 | 07/08/2026 |
| GAVASK INC | General Contractor | 1 | 04/09/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| KZ ENGINEERING, P.C. | 4665 | 1 | 04/23/2026 |
| DOMANI INSPECTION SERVICE | 843 | 12 | 09/10/2025 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Sidewalk Shed | Permit Issued | DYNAMIX SCAFFOLD GROUP LL | 07/23/2026 |
| DOB NOW | Construction Fence | Permit Issued | DYNAMIX SCAFFOLD GROUP LL | 07/13/2026 |
| DOB NOW | Suspended Scaffold | Permit Issued | SHR3 CONSTRUCTION CORP | 05/05/2026 |
| DOB NOW | Plumbing | Permit Issued | B&B MECH PLBG & HTG LLC | 04/29/2026 |
| DOB NOW | Structural | Permit Issued | DEXTERA CONSTRUCTION LLC | 04/20/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | DEXTERA CONSTRUCTION LLC | 04/20/2026 |
| DOB NOW | Support of Excavation | Permit Issued | DEXTERA CONSTRUCTION LLC | 04/20/2026 |
| DOB NOW | Foundation | Permit Issued | DEXTERA CONSTRUCTION LLC | 04/20/2026 |
| DOB NOW | Construction Fence | Permit Issued | DEXTERA CONSTRUCTION LLC | 03/24/2026 |
| DOB NOW | General Construction | Permit Issued | DEXTERA CONSTRUCTION LLC | 12/24/2025 |
| DOB NOW | Supported Scaffold | Permit Issued | DYNAMIX SCAFFOLD GROUP LL | 12/10/2025 |
| DOB NOW | Protection and Mechanical Methods | Permit Issued | DYNAMIX SCAFFOLD GROUP LL | 09/22/2025 |
| DOB NOW | Sprinklers | Permit Issued | TARGET PIPING NY LLC | 09/12/2025 |
| DOB NOW | General Construction | Permit Issued | DEXTERA CONSTRUCTION LLC | 07/17/2025 |
| DOB NOW | Construction Fence | Permit Issued | DYNAMIX SCAFFOLD GROUP LL | 07/07/2025 |
| DOB NOW | Sidewalk Shed | Permit Issued | DYNAMIX SCAFFOLD GROUP LL | 07/07/2025 |
| DOB NOW | Mechanical Systems | Permit Issued | DEXTERA CONSTRUCTION LLC | 05/06/2025 |
| DOB NOW | Foundation | Permit Issued | DEXTERA CONSTRUCTION LLC | 05/06/2025 |
| DOB NOW | Structural | Permit Issued | DEXTERA CONSTRUCTION LLC | 05/05/2025 |
| DOB NOW | Plumbing | Permit Issued | TARGET PIPING NY LLC | 05/02/2025 |
| DOB NOW | Support of Excavation | Permit Issued | DEXTERA CONSTRUCTION LLC | 04/02/2025 |
| DOB NOW | Construction Fence | Permit Issued | DEXTERA CONSTRUCTION LLC | 04/02/2025 |
| DOB NOW | General Construction | Permit Issued | DEXTERA CONSTRUCTION LLC | 03/31/2025 |
| DOB NOW | Construction Fence | Permit Issued | GAVASK INC | 02/06/2019 |
| BIS | — | ISSUED | VINALE MANAGEMENT & CONSU | 02/21/2019 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 09/10/2025 | Permit Issued | DEXTERA CONSTRUCTION LLC | Air Conditioning Systems, Heating and Air Conditioning Systems, Ventilation Systems |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/10/2025 | Permit Issued | TARGET PIPING NY LLC | Sprinkler System |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/10/2025 | Permit Issued | TARGET PIPING NY LLC | Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 12/18/2025 | Permit Issued | WCK ELECTRIC CORP. | General Wiring |
| 08/11/2025 | Permit Issued | RICHARD NEU | — |
| 07/23/2025 | Permit Issued | POWER DIRECT ELECTRIC INC | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/10/2025 | Permit Issued | TARGET PIPING NY LLC | Concrete |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 12/09/2025 | Permit Issued | DYNAMIX SCAFFOLD GROUP LL | Fence, Sidewalk Shed |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/23/2026 | Permit Issued | SHR3 CONSTRUCTION CORP | Suspended Scaffold (SC) |
| Date | Type | Result | Report |
|---|---|---|---|
| 09/02/2026 | Fail-Final PL - Up to 3 Requested Floors | Fail | View ↗ |
| 07/07/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 06/12/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 06/09/2026 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 04/23/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 01/27/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 01/22/2026 | Pass-Final PL - Up to 9 Requested Floors | Pass | View ↗ |
| 12/05/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 11/03/2025 | Certified Storm Drainage-ST-Piping-Roughing | Certified | View ↗ |
| 10/17/2025 | Certified Storm Drainage-ST-Piping-Roughing | Certified | View ↗ |
| 10/17/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 07/10/2025 | Pass-Final PL - Underground | Pass | View ↗ |
| 06/26/2025 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 05/22/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 05/19/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 02/24/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 12/11/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 04/22/2026 | Alternative Materials - OTCR Buildings Bulletin Number | Karol Zdancewicz | special |
| 04/22/2026 | Post-installed Anchors | Karol Zdancewicz | special |
| 10/14/2025 | HVAC-R and service water heating equipment | JOHN MCMONAGLE | energy_progress |
| 10/14/2025 | Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation | JOHN MCMONAGLE | special |
| 10/14/2025 | Fire-Resistant Penetrations and Joints | JOHN MCMONAGLE | special |
| 10/14/2025 | Energy Code Compliance Inspections | JOHN MCMONAGLE | progress |
| 10/14/2025 | HVAC-R and service water piping design and insulation | JOHN MCMONAGLE | energy_progress |
| 10/14/2025 | Maintenance information | JOHN MCMONAGLE | energy_progress |
| 10/14/2025 | HVAC-R and service water heating system controls | JOHN MCMONAGLE | energy_progress |
| 09/19/2025 | Concrete - Cast-In-Place | JOHN MCMONAGLE | special |
| 09/19/2025 | Final | JOHN MCMONAGLE | progress |
| 09/17/2025 | Fire-Resistance Rated Construction | JOHN MCMONAGLE | progress |
| 09/17/2025 | Fire-Resistant Penetrations and Joints | JOHN MCMONAGLE | special |
| 09/17/2025 | Heating Systems | JOHN MCMONAGLE | special |
| 09/17/2025 | Mechanical Systems | JOHN MCMONAGLE | special |
| 09/17/2025 | Energy Code Compliance Inspections | JOHN MCMONAGLE | progress |
| 09/17/2025 | Maintenance information | JOHN MCMONAGLE | energy_progress |
| 09/17/2025 | HVAC-R and service water piping design and insulation | JOHN MCMONAGLE | energy_progress |
| 09/17/2025 | Shutoff dampers | JOHN MCMONAGLE | energy_progress |
| 09/17/2025 | Duct leakage testing, insulation and design | JOHN MCMONAGLE | energy_progress |
| 09/17/2025 | HVAC-R and service water heating equipment | JOHN MCMONAGLE | energy_progress |
| 09/17/2025 | HVAC-R and service water heating system controls | JOHN MCMONAGLE | energy_progress |
| 09/17/2025 | Final | JOHN MCMONAGLE | progress |
| 09/16/2025 | Sprinkler Systems | JOHN MCMONAGLE | special |
| 09/16/2025 | Fire-Resistant Penetrations and Joints | JOHN MCMONAGLE | special |