← Back
Office with commercial, 7-19 stories
310 HUDSON STREET
MANHATTAN · BIN 1091643
💬 Discuss this project
2021Year Built
19Stories
O6Building Class
M1-6Zoning
972,820 sfGross Floor Area
4Units
LL97 Covered0 Open Violations
Office with commercial, 7-19 stories · Owner of record: HUDSON SQUARE REALTY, LLC · 86,198 sf lot · 11.29 FAR built · Flood zone X500
Locations of Work
ArchitectureStructuralElectricalMechanicalPlumbingFire ProtectionCivilGeneralOther
Permit Issued — active, not yet Signed-off
Roof50p · 10 filings · 20 docs
Bulkhead4p · 2 filings · 20 docs
Floor 321p · 1 filing · 20 docs
Floor 312p · 1 filing · 20 docs
Floor 30
Floor 29
Floor 28
Floor 27
Floor 26
Floor 25
Floor 24
Floor 233p · 2 filings · 20 docs
Floor 227p · 4 filings · 20 docs
Floor 2111p · 6 filings · 20 docs
Floor 2014p · 7 filings · 20 docs
Floor 1913p · 12 filings · 20 docs
Floor 1821p · 9 filings · 20 docs
Floor 1726p · 9 filings · 20 docs
Floor 1626p · 9 filings · 20 docs
Floor 1527p · 9 filings · 20 docs
Floor 1426p · 9 filings · 20 docs
Floor 1334p · 9 filings · 20 docs
Floor 1235p · 9 filings · 20 docs
Floor 1173p · 11 filings · 20 docs
Floor 10123p · 37 filings · 20 docs
Floor 985p · 13 filings · 20 docs
Floor 848p · 9 filings · 20 docs
Floor 733p · 9 filings · 20 docs
Floor 653p · 12 filings · 20 docs
Floor 570p · 10 filings · 20 docs
Floor 473p · 15 filings · 20 docs
Floor 364p · 11 filings · 20 docs
Floor 237p · 13 filings · 20 docs
Floor 1Under Construction58p · 7 filings · 20 docs
Mezzanine1p · 1 filing · 4 docs
Cellar53p · 13 filings · 20 docs
Sub-Cellar70p · 12 filings · 20 docs
Sub-Basement1 filing · 2 docs
7 jobs · most recent 10/08/2025
Air Conditioning Systems Associated Ducts and Piping Heating and Air Conditioning Systems Ventilation Systems
FiledStatusContractorScopeMake / Model / Capacity
10/08/2025Permit IssuedCAS EQUIPMENT LLCHeating and Air Conditioning Systems—
04/01/2024Permit IssuedSTRUCTURE TONE, LLCAir Conditioning Systems
Cooling
Nortek ITF-DH50 23,000 CFM · Ahu ×15
AHU-MIXING-10E-3 12,000 CFM · Ahu ×5
ITF-DH31 14,000 CFM · Ahu ×5
ITF-DH41 18,000 CFM · Ahu ×5
ITF-DH42 18,500 CFM · Ahu ×5
02/15/2024Signed-offSTRUCTURE TONE, LLCAir Conditioning Systems
Cooling
Vertiv CW041U 5,850 CFM · Crac Unit ×8
02/15/2024Signed-offSTRUCTURE TONE, LLCAir Conditioning Systems, Associated Ducts and Piping
Cooling
Ventrol ITF-DH34 20,000 CFM ×1
11/15/2023Signed-offSTRUCTURE TONE, LLCAir Conditioning Systems, Associated Ducts and Piping
Cooling
Vertiv PW029UC1A2S9FF 4,300 CFM · Ahu ×8
Ducts & Piping
Titus ×1
N/A N/A 1 BTU ×1
05/09/2023——Associated Ducts and Piping
Ducts & Piping
N/A ×1
02/25/2022Signed-offSTRUCTURE TONE, LLCVentilation Systems
Ventilation
N/A N/A 1 BTU · Ahu ×1
8 jobs · most recent 06/11/2026
Sprinkler System
FiledStatusContractorScope
06/11/2026Permit IssuedSIRINA FIRE PROT CORP—
05/27/2026Permit IssuedABCO-PEERLESS SPRKLR CORPSprinkler System
10/14/2025Signed-offSIRINA FIRE PROT CORPSprinkler System
10/08/2025Permit IssuedSIRINA FIRE PROT CORPSprinkler System
02/15/2024Signed-offRAEL AUTOMATIC SPR.CO INCSprinkler System
02/15/2024Signed-offABCO-PEERLESS SPRKLR CORPSprinkler System
11/15/2023Signed-offRAEL AUTOMATIC SPR.CO INCSprinkler System
10/19/2021———
10 jobs · most recent 05/27/2026
Water/Sanitary Storm
FiledStatusContractorScope
05/27/2026Permit IssuedPREFERRED MECHANICAL INCWater/Sanitary
10/14/2025Signed-offAARON PLBG AND MECH SYSTWater/Sanitary
10/08/2025Signed-offMACCARONE PLUMBING INCWater/Sanitary
02/15/2024Signed-offPACE PLUMBING CORPWater/Sanitary
02/15/2024Signed-offPREFERRED MECHANICAL INCWater/Sanitary
11/15/2023Signed-offPREFERRED MECHANICAL INCWater/Sanitary
05/09/2023——Water/Sanitary
02/25/2022Permit IssuedPACE PLUMBING CORPWater/Sanitary
10/19/2021Permit IssuedPREFERRED MECHANICAL INCWater/Sanitary
09/30/2020Permit IssuedALMAR PLUMBING & HTG CORPStorm, Water/Sanitary
25 jobs · most recent 08/14/2026
General Wiring Lighting
FiledStatusContractorScope
08/14/2026CompleteH. & L. ELECTRIC INC4 meters, 1 new_meters
08/10/2026Permit IssuedH. & L. ELECTRIC INCGeneral Wiring
06/10/2026CompleteCORPORATE ELEC. GROUP INC—
06/10/2026CompleteCORPORATE ELEC. GROUP INC—
06/10/2026CompleteCORPORATE ELEC. GROUP INC—
05/15/2026Permit IssuedNEAD ELECTRIC INC.General Wiring
04/23/2026CompletePOWERONE ELECT'L CONTRGGeneral Wiring
02/25/2026CompleteNEAD ELECTRIC INC.General Wiring
01/20/2026CompleteH. & L. ELECTRIC INC3 meters, 1 new_meters
01/02/2026Permit IssuedH. & L. ELECTRIC INCGeneral Wiring
12/02/2025CompleteNEAD ELECTRIC INC.1 meters, 1 new_meters
11/20/2025CompleteABC, INC.—
11/18/2025Permit IssuedABC, INC.General Wiring
08/25/2025CompleteEGG ELECTRIC INC.General Wiring, Lighting
04/30/2025CompleteH. & L. ELECTRIC INCGeneral Wiring
1 job · most recent 05/27/2026
Concrete
FiledStatusContractorScope
05/27/2026Permit IssuedSTRUCTURE TONE, LLCConcrete
1 job · most recent 03/29/2021
Scaffold
FiledStatusContractorScope
03/29/2021Permit IssuedLENDLEASE(US)CONSTRUCTIONScaffold
1 job · most recent 03/12/2024
Suspended Scaffold (SC)
FiledStatusContractorScope
03/12/2024Permit IssuedVIK XS SERVICES INCSuspended Scaffold (SC)
Building Lifecycle
All (300)Filed (58)Permit Issued (41)Signed Off (36)Violation (8)Inspection (60)Objection (67)Special Inspection (30)
08/28/2026
Permit issued — Structural
M01391978-S4-ST
08/26/2026
Inspection — Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test
Certified
View inspection ↗
08/11/2026
Signed off — Alteration
Plumbing work on 1st floor as per plans filed herewith. No Change in Use, Egress or Occupancy.
M01218193-S2
07/24/2026
Inspection — Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test
Certified
View inspection ↗
07/24/2026
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
07/11/2026
Signed off — Alteration
INSTALLATION OF NEW INTERIOR NON-BEARING PARTITIONS AND ARCHITECTURAL FINISHES. NO CHANGE TO EGRESS, USE, OR OCCUPANCY.
M01189773-S2
07/01/2026
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Underground
Certified
View inspection ↗
06/24/2026
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
06/16/2026
Filed — No Work
M01416382-I1
06/16/2026
Filed — No Work
M01416395-I1
06/15/2026
Permit issued — Sprinklers
M01398759-I1-EW-SP
06/11/2026
Filed — Alteration
Sprinkler work filed to show PRV sizes and locations as per plans filed herewith. No change in use, egress, or occupancy.
M01398759-I1
06/11/2026
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
06/01/2026
Permit issued — Sprinklers
M01391978-S3-EW-SP
06/01/2026
Permit issued — Mechanical Systems
M01391978-S1-MS
06/01/2026
Inspection — Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test
Certified
View inspection ↗
06/01/2026
Special inspection requirement — Post-installed Anchors
MARISA HARTE
05/29/2026
Permit issued — Plumbing
M01391978-S2-PL
05/27/2026
Filed — Alteration
MODIFICATION OF EXISTING PLUMBING SYSTEM. NO CHANGE TO EGRESS, USE, OR OCCUPANCY.
M01391978-S1
05/26/2026
Filed — No Work
M01406319-I1
05/21/2026
Filed — Alteration
MODIFICATION OF EXISTING PLUMBING SYSTEM. NO CHANGE TO EGRESS, USE, OR OCCUPANCY.
M01391978-S4
05/20/2026
Permit issued — General Construction
M01391978-I1-GC
05/13/2026
Filed — Alteration
MODIFICATION OF EXISTING PLUMBING SYSTEM. NO CHANGE TO EGRESS, USE, OR OCCUPANCY.
M01391978-S2
05/13/2026
Filed — Alteration
MODIFICATION OF EXISTING PLUMBING SYSTEM. NO CHANGE TO EGRESS, USE, OR OCCUPANCY.
M01391978-S3
05/13/2026
Filed — Alteration
MODIFICATION OF EXISTING PLUMBING SYSTEM. NO CHANGE TO EGRESS, USE, OR OCCUPANCY.
M01391978-I1
05/08/2026
Signed off — Alteration
Plumbing work on 1st floor as per plans filed herewith. No Change in Use, Egress or Occupancy.
M01218193-S1
05/07/2026
Signed off — Alteration
Plumbing work on 1st floor as per plans filed herewith. No Change in Use, Egress or Occupancy.
M01218193-S3
05/07/2026
Inspection — Pass-Final PL - Underground
Pass
View inspection ↗
05/07/2026
Special inspection requirement — Sprinkler Systems
MARISA HARTE
05/06/2026
Filed — No Work
M01397306-I1
05/06/2026
Signed off — Alteration
Plumbing work on 1st floor as per plans filed herewith. No Change in Use, Egress or Occupancy.
M01218193-I1
05/06/2026
Signed off — Alteration
M00178469-I1
05/06/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
MARISA HARTE
05/06/2026
Special inspection requirement — Post-installed Anchors
MARISA HARTE
05/06/2026
Special inspection requirement — Post-installed Anchors
MARISA HARTE
05/06/2026
Special inspection requirement — Energy Code Compliance Inspections
Edward Shalat
05/06/2026
Special inspection requirement — Interior lighting power
Edward Shalat
05/06/2026
Special inspection requirement — Lighting controls
Edward Shalat
05/06/2026
Special inspection requirement — Energy Code Compliance Inspections
MARISA HARTE
05/06/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
Edward Shalat
04/30/2026
Objection resolved — Addressed
04/29/2026
Objection raised — Other
04/28/2026
Filed — No Work
M01391855-I1
04/28/2026
Inspection — Pass-Final Curb Cut Non-Directive 14
Pass
View inspection ↗
04/23/2026
Special inspection requirement — Sprinkler Systems
MARISA HARTE
04/23/2026
Special inspection requirement — Mechanical Systems
MARISA HARTE
04/23/2026
Special inspection requirement — Final
MARISA HARTE
04/23/2026
Special inspection requirement — Final
Edward Shalat
04/17/2026
Inspection — Pass-Final General Construction Non-Directive 14
Pass
View inspection ↗
04/14/2026
Signed off — Alteration
Installation Design and Usage of Supported Scaffold as per Drawings. The Supported Scaffold Shall Comply with Work on Level 10S (Terrace). No Change in Use, Occupancy, or Egress Under This Application.
M00997412-I1
04/09/2026
Signed off — Alteration
INSTALLATION AND USE OF A VALLA 25E MINI CRANE TO ERECT FACADE PANELS FOR NEW BUILDING AS PER PLANS SUBMITTED. VALLA 25E MINI CRANE SHALL COMPLY WITH CHAPTER #33 OF NYC BUILDING CODE. THIS APPLICATION INVOLVES NO CHANGE INOCCUPANCY, USE OR EGRESS.
M00683332-I1
04/09/2026
Signed off — Alteration
M00698579-I1
04/09/2026
Signed off — Alteration
INSTALLATION AND USE OF JEKKO MPK20 MINI CRANE TO ERECT FACADE PANELS AS PER PLANS SUBMITTED. JEKKO MPK20 MINI CRANE SHALL COMPLY WITH CHAPTER #33 OF NYC BUILDING CODE. THIS APPLICATION INVOLVES NO CHANGE IN OCCUPANCY, USE OR EGRESS.
M00698521-I1
04/09/2026
Signed off — Alteration
INSTALLATION AND USE OF JEKKO MPK20 MINI CRANE TO ERECT FACADE PANELS AS PER PLANS SUBMITTED. JEKKO MPK20 MINI CRANE SHALL COMPLY WITH CHAPTER #33 OF NYC BUILDING CODE. THIS APPLICATION INVOLVES NO CHANGE IN OCCUPANCY, USE OR EGRESS.
M00698551-I1
04/09/2026
Signed off — Alteration
INSTALLATION AND USE OF VALLA 25E MINI CRANE TO ERECT FACADE PANELS AS PER PLANS SUBMITTED. VALLA 25E MINI CRANE SHALL COMPLY WITH CHAPTER #33 OF NYC BUILDING CODE. THIS APPLICATION INVOLVES NO CHANGE IN OCCUPANCY, USE OR EGRESS.
M00692459-I1
04/09/2026
Signed off — Alteration
INSTALLATION AND USE OF A SPYDER CRANE URW506 AS PER PLANS SUBMITTED. SPYDER CRANE URW506 SHALL COMPLY WITH CHAPTER #33 OF NYC BUILDING CODE. THIS APPLICATION INVOLVES NO CHANGE IN OCCUPANCY, USE OR EGRESS.
M00729711-I1
04/02/2026
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
03/27/2026
Inspection — Certified Sprinkler-SP-Fixtures-Finish
Certified
View inspection ↗
03/20/2026
Inspection — Certified Remove/Cap - work done in accordance with code
Certified
View inspection ↗
03/20/2026
Inspection — Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test
Certified
View inspection ↗
Latest 60 of 300 events.
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
HUDSON SQUARE REALTY58207/08/2026
VIK XS SERVICES INC703/22/2026
LENDLEASEUSCONSTRUCTION4103/22/2026
STONEBRIDGE403/22/2026
PATTI AND SONS INC203/22/2026
GRAMERCY GROUP303/22/2026
EPIC MECHANICAL CONTRACT103/22/2026
RECTOR CHURCH WARDENS103/22/2026
CONSTRUCTION LENDLEASE US103/22/2026
CORP OF TRINITY CHURCH TR103/22/2026
▾Filing Representatives (Expediters)
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
STRUCTURE TONE, LLCGeneral Contractor6008/30/2026
SAFWAY ATLANTIC, LLCGeneral Contractor5007/08/2026
LENDLEASE(US)CONSTRUCTIONGeneral Contractor2707/08/2026
SIRINA FIRE PROT CORPFire Protection1707/08/2026
ABCO-PEERLESS SPRKLR CORPFire Protection1507/08/2026
CORE ERECTORS,LLCGeneral Contractor1307/08/2026
PACE PLUMBING CORPPlumbing907/08/2026
ALMAR PLUMBING & HTG CORPPlumbing907/08/2026
PREFERRED MECHANICAL INCPlumbing707/08/2026
AARON PLBG AND MECH SYSTPlumbing407/08/2026
PAR FIRE PROTECTION LLCFire Protection407/08/2026
HORIZON RETAIL CONSTRUCTIGeneral Contractor304/09/2026
RAEL AUTOMATIC SPR.CO INCFire Protection307/08/2026
ADVENT INDUSTRIAL CORPGeneral Contractor307/08/2026
ANTHONY RANIERIElectrical203/21/2026
CAS EQUIPMENT LLCGeneral Contractor203/21/2026
A.S.R. ELEC'L CONTR'G INCElectrical203/22/2026
WINICK PRODUCTIONS, LLCGeneral Contractor207/08/2026
PAUL BOCCIAElectrical203/21/2026
A & E PLUMBING CORPPlumbing207/08/2026
A M A HOLDINGSScaffold107/08/2026
ARTHUR GROSSMANElectrical103/21/2026
BIGMAN BROS., INC.Electrical103/22/2026
CHRIS RICHEYElectrical103/21/2026
LEVIN ALEXANDERElectrical103/21/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
SOCOTEC ENGINEERING49831006/11/2026
SHALAT ARCHITECTS P.C.2036405/13/2026
JOSEPH MARTINES PE, PLLC1428310/08/2025
FUTURE TECH CONSULTANTS O58910206/05/2025
GILSANZ MURRAY STEFICEK240105/20/2025
SHAHRISH SHUVO ENGINEERIN8524405/20/2025
TSF ENGINEERING, PC1274102/01/2025
TECNO OBRAS CONSULTING GR6498101/30/2024
CLARKE ENGINEERING SERVIC3795104/18/2022
PSI AGENCY INC.254102/25/2022
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWStructuralPermit IssuedSTRUCTURE TONE, LLC08/28/2026
DOB NOWSprinklersPermit IssuedSIRINA FIRE PROT CORP06/15/2026
DOB NOWMechanical SystemsPermit IssuedSTRUCTURE TONE, LLC06/01/2026
DOB NOWSprinklersPermit IssuedABCO-PEERLESS SPRKLR CORP06/01/2026
DOB NOWPlumbingPermit IssuedPREFERRED MECHANICAL INC05/29/2026
DOB NOWGeneral ConstructionPermit IssuedSTRUCTURE TONE, LLC05/20/2026
DOB NOWPlumbingSigned-offMACCARONE PLUMBING INC03/05/2026
DOB NOWMechanical SystemsSigned-offHORIZON RETAIL CONSTRUCTI02/06/2026
DOB NOWMechanical SystemsPermit IssuedCAS EQUIPMENT01/15/2026
DOB NOWSprinklersPermit IssuedSIRINA FIRE PROT CORP01/08/2026
DOB NOWPlumbingSigned-offAARON PLBG AND MECH SYST11/20/2025
DOB NOWGeneral ConstructionSigned-offHORIZON RETAIL CONSTRUCTI11/03/2025
DOB NOWSprinklersSigned-offSIRINA FIRE PROT CORP10/29/2025
DOB NOWGeneral ConstructionPermit IssuedW.J. NORTHRIDGE CONST COR10/23/2025
DOB NOWGeneral ConstructionSigned-offWINICK PRODUCTIONS, LLC10/07/2025
DOB NOWGeneral ConstructionSigned-offSTRUCTURE TONE, LLC10/02/2025
DOB NOWStructuralSigned-offADVENT INDUSTRIAL06/16/2025
DOB NOWPlumbingSigned-offPREFERRED MECHANICAL INC04/23/2025
DOB NOWMechanical SystemsSigned-offSTRUCTURE TONE, LLC04/08/2025
DOB NOWSprinklersSigned-offABCO-PEERLESS SPRKLR CORP04/08/2025
DOB NOWStandpipeSigned-offSIRINA FIRE PROT CORP04/04/2025
DOB NOWGeneral ConstructionSigned-offSTRUCTURE TONE, LLC03/21/2025
DOB NOWSprinklersSigned-offSIRINA FIRE PROT CORP03/18/2025
DOB NOWStructuralSigned-offWINICK PRODUCTIONS, LLC02/19/2025
DOB NOWSprinklersSigned-offSIRINA FIRE PROT CORP02/05/2025
DOB NOWSignSigned-offA.M.A HOLDINGS INC12/20/2024
DOB NOWStructuralSigned-offADVENT INDUSTRIAL10/25/2024
DOB NOWGeneral ConstructionSigned-offSTRUCTURE TONE, LLC07/24/2024
DOB NOWStandpipeSigned-offPACE PLUMBING CORP04/23/2024
DOB NOWGeneral ConstructionSigned-offSTRUCTURE TONE, LLC04/03/2024
DOB NOWStandpipeSigned-offSIRINA FIRE PROT CORP04/01/2024
DOB NOWStandpipeSigned-offSIRINA FIRE PROT CORP04/01/2024
DOB NOWPlumbingSigned-offALMAR PLUMBING & HTG CORP03/15/2024
DOB NOWSprinklersSigned-offSIRINA FIRE PROT CORP03/08/2024
DOB NOWSupported ScaffoldSigned-offCORE ERECTORS02/01/2024
DOB NOWSuspended ScaffoldPermit IssuedVIK XS SERVICES INC01/31/2024
DOB NOWStructuralSigned-offLENDLEASE(US)CONSTRUCTION01/25/2024
DOB NOWSprinklersSigned-offLAWRENCE J. LEVINE12/13/2023
DOB NOWSprinklersSigned-offLAWRENCE J. LEVINE12/13/2023
DOB NOWMechanical SystemsSigned-offSTRUCTURE TONE, LLC12/12/2023
+ 60 more permits on file
▾Field Inspections (DOB CAP) — 97
DateTypeResultReport
08/26/2026Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
07/24/2026Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
07/24/2026Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
07/01/2026Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
06/24/2026Pass-Final PL - Up to 3 Requested FloorsPassView ↗
06/11/2026Pass-Final PL - Up to 3 Requested FloorsPassView ↗
06/01/2026Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
05/07/2026Pass-Final PL - UndergroundPassView ↗
04/28/2026Pass-Final Curb Cut Non-Directive 14PassView ↗
04/17/2026Pass-Final General Construction Non-Directive 14PassView ↗
04/02/2026Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
03/27/2026Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
03/20/2026Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
03/20/2026Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
03/16/2026Pass-Final PL - UndergroundPassView ↗
03/13/2026Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
03/09/2026Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
02/18/2026Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
01/14/2026Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
10/23/2025Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
10/15/2025Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
10/15/2025Pass-Final PL - Up to 3 Requested FloorsPassView ↗
09/30/2025Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
09/30/2025Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
08/12/2025Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
Latest 25 of 97.
▾Special Inspection Requirements (DOB NOW) — 150
DateRequirementInspectorRole
06/01/2026Post-installed AnchorsMARISA HARTEspecial
05/07/2026Sprinkler SystemsMARISA HARTEspecial
05/06/2026Post-installed AnchorsMARISA HARTEspecial
05/06/2026Fire-Resistant Penetrations and JointsEdward Shalatspecial
05/06/2026Fire-Resistant Penetrations and JointsMARISA HARTEspecial
05/06/2026Post-installed AnchorsMARISA HARTEspecial
05/06/2026Lighting controlsEdward Shalatenergy_progress
05/06/2026Energy Code Compliance InspectionsEdward Shalatprogress
05/06/2026Interior lighting powerEdward Shalatenergy_progress
05/06/2026Energy Code Compliance InspectionsMARISA HARTEprogress
04/23/2026Mechanical SystemsMARISA HARTEspecial
04/23/2026FinalMARISA HARTEprogress
04/23/2026Sprinkler SystemsMARISA HARTEspecial
04/23/2026FinalEdward Shalatprogress
10/15/2025Fire-Resistant Penetrations and JointsShahrish Shuvospecial
10/01/2025Lighting controlsEdward Shalatenergy_progress
10/01/2025Interior lighting powerEdward Shalatenergy_progress
10/01/2025FinalEdward Shalatprogress
09/05/2025HVAC-R and service water piping design and insulationJOSEPH MARTINESenergy_progress
09/05/2025Duct leakage testing, insulation and designJOSEPH MARTINESenergy_progress
09/05/2025Energy Code Compliance InspectionsJOSEPH MARTINESprogress
09/05/2025HVAC-R and service water heating equipmentJOSEPH MARTINESenergy_progress
09/05/2025Fire-Resistant Penetrations and JointsJOSEPH MARTINESspecial
09/05/2025Shutoff dampersJOSEPH MARTINESenergy_progress
09/05/2025Maintenance informationJOSEPH MARTINESenergy_progress
Latest 25 of 150.
▾Documents — 1,798 on file (BIS + DOB NOW)
▸Plans & Drawings272
▸DOB NOWPlans/Sketch169
09/03/2026M00489981-I1Request digital key ↗
09/03/2026M00565016-I1Request digital key ↗
09/03/2026M00570964-I1Request digital key ↗
Showing 3 of 169 on file for this type
▸DOB NOWPlans/Sketch - Temporary Place of Assembly23
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 23 on file for this type
▸DOB NOWPlans/Sketch - Place of Assembly22
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 22 on file for this type
▸DOB NOWPlans/Sketch - Plumbing15
09/04/2026M00207773-P4Request digital key ↗
09/04/2026M00207773-A1Request digital key ↗
09/04/2026M00207773-A3Request digital key ↗
Showing 3 of 15 on file for this type
▸DOB NOWPlans/Sketch - Standpipe10
09/05/2026M00254772-I1Request digital key ↗
Showing 1 of 10 on file for this type
▸DOB NOWPlans/Sketch - Mechanical Systems9
09/05/2026M00207758-P5Request digital key ↗
09/05/2026M00207758-P8Request digital key ↗
09/05/2026M00207758-P6Request digital key ↗
Showing 3 of 9 on file for this type
▸DOB NOWPlans/Sketch - Sprinkler8
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 8 on file for this type
▸DOB NOWPlans/Sketch - Construction Fence4
09/05/2026M00178469-I1Request digital key ↗
09/05/2026M00281275-P1Request digital key ↗
09/05/2026M00281275-I1Request digital key ↗
Showing 3 of 4 on file for this type
▸DOB NOWPlans/Sketch - Curb Cut4
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 4 on file for this type
▸DOB NOWPlans/Sketch - Boiler Equipment4
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 4 on file for this type
▸DOB NOWPlans/Sketch - Structural2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸DOB NOWPlans/Sketch - Sidewalk Shed2
09/05/2026M00178465-I1Request digital key ↗
Showing 1 of 2 on file for this type
▸Applications & Permits175
▸BISPLAN / WORK APPROVAL APPLICATION113
01/29/2026141028894Open ↗
01/29/2026141028929Open ↗
11/10/2025140863652Open ↗
Showing 3 of 113 on file for this type
▸BISWORK PERMIT APPLICATION58
10/18/2024121205864Open ↗
10/18/2024121205864Open ↗
10/18/2024121205864Open ↗
Showing 3 of 58 on file for this type
▸BISBPP-5 - Authorization to the Department of Transportation2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISPLAN - WORK & PERMITS - SUPPPORTING DOCUMENTATION2
02/13/2025121205864Open ↗
10/12/2023121205864Open ↗
▸Zoning, Tax Lot & Property Records3
▸BISZONING DIAGRAM3
11/16/2023121205864Open ↗
05/03/2023121205864Open ↗
Showing 2 of 3 on file for this type
▸Seals & Professional Certifications681
▸DOB NOWDPL-1: Design Professional Seal & Signature269
09/05/2026M00178469-I1Open ↗
09/05/2026M00178465-I1Open ↗
09/05/2026M00178465-P1Open ↗
Showing 3 of 269 on file for this type
▸DOB NOWProgress Inspector Seal & Signature176
09/26/2026M00818024-I1Open ↗
09/26/2026M00818024-I1Open ↗
09/23/2026M01277196-S1Open ↗
Showing 3 of 176 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature159
09/29/2026M01391978-S3Open ↗
09/26/2026M00818024-I1Open ↗
09/23/2026M00818017-S1Open ↗
Showing 3 of 159 on file for this type
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION28
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 28 on file for this type
▸BISPROFESSIONAL CERTIFIED CHECKLIST12
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 12 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM12
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 12 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT9
02/15/2023141021463Open ↗
02/15/2023141021463Open ↗
Showing 2 of 9 on file for this type
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY6
01/29/2026141028894Open ↗
02/15/2023141021463Open ↗
Showing 2 of 6 on file for this type
▸BISAPPLICANT OWNER SIGNATURE6
01/30/2026141028901Open ↗
01/29/2026141028894Open ↗
01/29/2026141028929Open ↗
Showing 3 of 6 on file for this type
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION4
02/15/2023141021463Open ↗
Showing 1 of 4 on file for this type
▸Trade Schedules & Equipment35
▸BISSELF-CERT PLUMBING NOTICE11
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 11 on file for this type
▸BISSCHEDULE B - PLUMBING10
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 10 on file for this type
▸BISEQUIPMENT USE PERMITS4
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 4 on file for this type
▸BISEQUIPMENT USE APPLICATION-PERMIT3
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 3 on file for this type
▸BISFA - FDNY APPROVAL : FD-FAA2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISSPRINKLER INSP REPORT : FP-852
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸DOB NOWStandpipe Alarms Drawings1
09/03/2026M00645089-I1—
▸Safety & Tenant Protection6
▸BISSTREET TREE CHECKLIST4
11/16/2023121205864Open ↗
Showing 1 of 4 on file for this type
▸BISST-1 Street Tree Checklist2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸Environmental & Asbestos177
▸DOB NOWOER: Notice to Proceed97
09/05/2026M00207758-P7Open ↗
09/05/2026M00207758-I1Open ↗
09/05/2026M00207758-I1Open ↗
Showing 3 of 97 on file for this type
▸DOB NOWOER: Notice of Satisfaction40
09/03/2026M00572078-I1Open ↗
09/03/2026M00645089-I1Open ↗
09/02/2026M00572055-I1Open ↗
Showing 3 of 40 on file for this type
▸BISTHIS IS 'NOT AN ASBESTOS PROJECT'17
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 17 on file for this type
▸BISENVIRONMENTAL RESTRICTIONS - OER NOTICE TO PROCEED11
01/29/2026141028894Open ↗
01/29/2026141028929Open ↗
02/15/2023141021463Open ↗
Showing 3 of 11 on file for this type
▸BISASBESTOS: CERTIFICATION (DEP ACP5)3
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 3 on file for this type
▸BISENVIRONMENTAL RESTRICTIONS - OER NOTICE OF SATISFACTION3
02/28/2024141021463Open ↗
01/17/2024121205864Open ↗
Showing 2 of 3 on file for this type
▸BISASBESTOS: EXEMPTION (ASB4)2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISACP5 ASBESTOS: CERTIFICATION (DEP ACP5)2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸DOB NOWDEP ACP-5: Asbestos Assessment Report2
09/05/2026M00178465-I1Open ↗
09/05/2026M00178465-P1Open ↗
▸Energy Compliance32
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY14
01/29/2026141028894Open ↗
01/29/2026141028929Open ↗
03/13/2024141021463Open ↗
Showing 3 of 14 on file for this type
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS5
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 5 on file for this type
▸DOB NOWPreliminary Commissioning Report Certification4
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 4 on file for this type
▸DOB NOWEN2: As Built Energy Analysis.4
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 4 on file for this type
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY FOR ENERGY CODE PROGRESS INSPECTIONS2
01/29/2026141028894Open ↗
02/15/2023141021463Open ↗
▸BISTR8: Energy Code Progress Inspections2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISLIGHTING CONTROLS1
11/30/2023121205864Open ↗
▸Inspections & Test Reports67
▸BISTECHNICAL REPORT: RESPONSIBILITY30
02/13/2026140930429Open ↗
01/29/2026141028894Open ↗
01/29/2026141028929Open ↗
Showing 3 of 30 on file for this type
▸BISTECHNICAL REPORT: CONCRETE DESIGN MIX16
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 16 on file for this type
▸DOB NOWHydrant Flow Test Letter16
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 16 on file for this type
▸BISTECHNICAL REPORT: CONCRETE/TEST CYLINDER3
05/31/2024121205864Open ↗
Showing 1 of 3 on file for this type
▸BISSOIL REPORT1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸DOB NOWConcrete Testing Exception Report1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Approvals, Objections & Sign-offs73
▸BISSCHEDULE A - OCCUPANCY / USE28
07/08/2025121205864Open ↗
08/06/2024121205864Open ↗
06/06/2024121205864Open ↗
Showing 3 of 28 on file for this type
▸BISADMINISTRATIVE OBJECTIONS16
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 16 on file for this type
▸BISLETTERS - SUPPORTING DOCUMENTATION7
12/23/2022121205864Open ↗
Showing 1 of 7 on file for this type
▸BISSUPERSEDING LETTER7
10/18/2024121205864Open ↗
03/18/2024121205864Open ↗
Showing 2 of 7 on file for this type
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST7
01/12/2024141021392Open ↗
Showing 1 of 7 on file for this type
▸BISTRANSIT AUTHORITY/MTA/PANYNJ APPROVAL3
01/23/2023140863652Open ↗
Showing 1 of 3 on file for this type
▸BISLETTERS - APPRVD FAB CERT-INTENT2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISFINAL2
01/09/2024141021392Open ↗
Showing 1 of 2 on file for this type
▸BISSHED LETTER1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Cost, Insurance & Ownership52
▸BISCOST AFFIDAVIT40
01/29/2026141028894Open ↗
01/29/2026141028929Open ↗
02/28/2024141021463Open ↗
Showing 3 of 40 on file for this type
▸BISPROJECT-SPECIFIC GL INSURANCE8
10/18/2024121205864Open ↗
03/18/2024121205864Open ↗
11/15/2023121205864Open ↗
Showing 3 of 8 on file for this type
▸BISAcord 25 (Acord Certificate of Liability Insurance)2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISCOST AFFIDAVIT (FINAL): PW32
01/09/2024141021392Open ↗
Showing 1 of 2 on file for this type
▸Filing & Intake Forms76
▸BISADDITIONAL INFORMATION41
01/06/2026140863652Open ↗
10/03/2025140863652Open ↗
09/12/2025140863652Open ↗
Showing 3 of 41 on file for this type
▸BISEFILING COVER SHEET21
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 21 on file for this type
▸BISEFILING JOB APPLICATION COVER SHEET10
01/30/2026141028901Open ↗
01/29/2026141028894Open ↗
01/29/2026141028929Open ↗
Showing 3 of 10 on file for this type
▸BISBOROUGH INTAKE FORM2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸DOB NOWAI1 Form (from plan PDF)2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸Other Documents90
▸DOB NOWHydraulic Calculations16
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 16 on file for this type
▸DOB NOWAlternate Plan 213
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 13 on file for this type
▸DOB NOWAlternate Plan 113
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 13 on file for this type
▸BISEXTERNAL FORMS - SUPPORTING DOCUMENTATION12
10/03/2025140863652Open ↗
10/03/2025140863652Open ↗
03/18/2024121205864Open ↗
Showing 3 of 12 on file for this type
▸DOB NOWAlternate Plan 311
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 11 on file for this type
▸BISCONSTRUCTION - SUPPORTING DOCUMENTATION10
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 10 on file for this type
▸BISENVIRONMENTAL 'E' DEP NOTICE TO PROCEED2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸DOB NOWAlternate Plan 42
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸DOB NOWManufacturer's Specifications2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸DOB NOWAlternate Plan 62
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸DOB NOWStructural Peer Review Report2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸DOB NOWAlternate Plan 52
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸DOB NOWCalculations2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISEGRESS CAPACITY MUST BE COMPLY PRIOR TO ANY TCO ISSUE FOR SUB-CELLAR1
01/16/2026121205864Open ↗