| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 02/26/2025 | Complete | TEMPEST ELEC'L CONTRG, IN | General Wiring |
| 12/11/2024 | Complete | TEMPEST ELEC'L CONTRG, IN | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/18/2025 | Permit Issued | NILCOMAT INC | Wood |
| Owner | Filings | Most Recent |
|---|---|---|
| COOPER 19 LLC | 1 | 03/22/2026 |
| NILCOMAT | 1 | 03/22/2026 |
| C POINT REALTY CORP | 2 | 03/21/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 11/07/2019 | $2.6M | — | — → — | $260/sf building |
| 11/20/2013 | $1.3M | — | Private party → Private party | $130/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| FRANK J QUATELA ARCHITECT P.C | 4 | 06/18/2025 |
| SIDERIS KEFALAS ENGINEERS PC | 5 | 09/05/2024 |
| Representative | Filings | Most Recent |
|---|---|---|
| Manetta architecture design pllc | 8 | 03/21/2026 |
| FRANK J QUATELA ARCHITECT P C | 4 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| NILCOMAT INC | General Contractor | 4 | 07/08/2026 |
| TEMPEST ELEC'L CONTRG, IN | Electrical | 1 | 03/22/2026 |
| PLUMBING NYC, INC | Fire Protection | 1 | 07/08/2026 |
| YAFE MEOD CORP | General Contractor | 1 | 07/08/2026 |
| PLUMBING NYC INC | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| CITY-WIDE TESTING INC | 416 | 8 | 06/18/2025 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Mechanical Systems | Signed-off | NILCOMAT INC | 06/12/2024 |
| DOB NOW | Construction Fence | Signed-off | YAFE MEOD CORP | 01/10/2024 |
| DOB NOW | Plumbing | Signed-off | PLUMBING WORKS NYC INC | 01/02/2024 |
| DOB NOW | Sprinklers | Signed-off | PLUMBING NYC, INC | 11/21/2023 |
| DOB NOW | Structural | Permit Issued | NILCOMAT INC | 11/15/2023 |
| Date | Type | Result | Report |
|---|---|---|---|
| 10/16/2024 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 08/28/2024 | Fail-Final CND-Occupancy Inspection | Fail | View ↗ |
| 04/08/2024 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 04/04/2024 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 04/04/2024 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 04/04/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 01/19/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 06/30/2025 | Concrete - Cast-In-Place | ELIAS RASABI | special |
| 06/30/2025 | Structural Stability – Alterations of existing buildings | ELIAS RASABI | special |
| 06/30/2025 | Masonry | ELIAS RASABI | special |
| 06/30/2025 | Fire-Resistance Rated Construction | ELIAS RASABI | progress |
| 06/30/2025 | Final | ELIAS RASABI | progress |
| 06/30/2025 | Energy Code Compliance Inspections | ELIAS RASABI | progress |
| 06/30/2025 | Air barrier - visual inspection | ELIAS RASABI | energy_progress |
| 06/30/2025 | Interior lighting power | ELIAS RASABI | energy_progress |
| 06/30/2025 | Lighting controls | ELIAS RASABI | energy_progress |
| 06/30/2025 | Fenestration and door U-factor and product ratings | ELIAS RASABI | energy_progress |
| 06/30/2025 | Fenestration air leakage | ELIAS RASABI | energy_progress |
| 06/30/2025 | Fenestration areas | ELIAS RASABI | energy_progress |
| 06/30/2025 | Fire-Resistant Penetrations and Joints | ELIAS RASABI | special |
| 09/05/2024 | Concrete - Cast-In-Place | ELIAS RASABI | special |
| 09/05/2024 | Masonry | ELIAS RASABI | special |
| 09/05/2024 | Structural Stability – Alterations of existing buildings | ELIAS RASABI | special |
| 09/05/2024 | Energy Code Compliance Inspections | ELIAS RASABI | progress |
| 09/05/2024 | Final | ELIAS RASABI | progress |
| 09/05/2024 | Fire-Resistance Rated Construction | ELIAS RASABI | progress |
| 09/05/2024 | Fenestration and door U-factor and product ratings | ELIAS RASABI | energy_progress |
| 09/05/2024 | Fenestration air leakage | ELIAS RASABI | energy_progress |
| 09/05/2024 | Air barrier - visual inspection | ELIAS RASABI | energy_progress |
| 09/05/2024 | Fenestration areas | ELIAS RASABI | energy_progress |
| 09/05/2024 | Interior lighting power | ELIAS RASABI | energy_progress |
| 09/05/2024 | Lighting controls | ELIAS RASABI | energy_progress |