← Back
Two stories - detached, small or mid-size
70-17 NANSEN STREET
QUEENS · BIN 4077179
💬 Discuss this project
1930Year Built
2.5Stories
A1Building Class
R3AZoning
1,590 sfGross Floor Area
1Units
Two stories - detached, small or mid-size · 3,000 sf lot · 0.53 FAR built · Flood zone X
Locations of Work
Electrical
Roof1 filing · 3 docs
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
05/15/2024$1.2M—Private party → Private party$753/sf building
04/11/2022$1.3M—— → —$805/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
MOMENTUM SOLAR205/20/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
MXV SIA LLC9281205/20/2026
Building Lifecycle
All (10)Filed (2)Permit Issued (1)Special Inspection (7)
05/20/2026
Filed — Alteration
Installation of solar panels, rooftop, grid tied, railed, 23 modules, 9.43 KW
Q01405136-I1
05/20/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
Mina Makar
05/20/2026
Special inspection requirement — Adhesive-Based Solar Pedestal Bonding Systems
Mina Makar
05/20/2026
Special inspection requirement — Post-installed Anchors
Mina Makar
05/20/2026
Special inspection requirement — Structural Stability – Alterations of existing buildings
Mina Makar
05/20/2026
Special inspection requirement — Energy Code Compliance Inspections
Mina Makar
05/20/2026
Special inspection requirement — Final
Mina Makar
05/20/2026
Special inspection requirement — Air barrier - visual inspection
Mina Makar
05/07/2026
Permit issued — Solar
Q01392420-I1-SL
04/24/2026
Filed — Alteration
Installation of solar panels, rooftop, grid tied, railed, 14 modules, 5.74 KW
Q01392420-I1
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSolarPermit IssuedMOMENTUM SOLAR05/07/2026
3 projects · most recent 04/24/2026
General Wiring
FiledStatusContractorScope
04/24/2026Permit IssuedISLAND ELECTRIC CORP—
04/24/2026Permit IssuedISLAND ELECTRIC CORP—
04/03/2023CompleteINWOOD ELECTRIC CORPGeneral Wiring
2 projects · most recent 05/20/2026
FiledStatusContractorScope
05/20/2026——23 panels, 9.43 kw, 405 roof_area_sqft
04/24/2026Permit IssuedMOMENTUM SOLAR28 panels, 11.48 kw, 246 roof_area_sqft
▾Special Inspection Requirements (DOB NOW) — 7
DateRequirementInspectorRole
05/20/2026Fire-Resistant Penetrations and JointsMina Makarspecial
05/20/2026Adhesive-Based Solar Pedestal Bonding SystemsMina Makarspecial
05/20/2026Post-installed AnchorsMina Makarspecial
05/20/2026Structural Stability – Alterations of existing buildingsMina Makarspecial
05/20/2026Energy Code Compliance InspectionsMina Makarprogress
05/20/2026FinalMina Makarprogress
05/20/2026Air barrier - visual inspectionMina Makarenergy_progress
▾Documents — 10 on file (BIS + DOB NOW)
▸Plans & Drawings2
▸DOB NOWPlans/Sketch2
08/29/2026Q01392420-I1Request digital key ↗
08/16/2026Q01405136-I1Request digital key ↗
▸Seals & Professional Certifications6
▸DOB NOWDPL-1: Design Professional Seal & Signature2
08/29/2026Q01392420-I1Open ↗
08/16/2026Q01405136-I1Open ↗
▸DOB NOWProgress Inspector Seal & Signature2
08/24/2026Q01405136-I1Open ↗
08/24/2026Q01405136-I1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature2
08/24/2026Q01405136-I1Open ↗
08/24/2026Q01405136-I1Open ↗
▸Environmental & Asbestos2
▸DOB NOWDEP ACP-5: Asbestos Assessment Report2
08/29/2026Q01392420-I1Open ↗
08/16/2026Q01405136-I1Open ↗