| Owner | Filings | Most Recent |
|---|---|---|
| JS 1953 | 41 | 09/20/2026 |
| EMAS ESTATE LLC | 2 | 03/22/2026 |
| BFI WASTE SERVICES | 1 | 03/22/2026 |
| FOREM ASSOCIATES | 1 | 03/21/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 11/19/2018 | $5.0M | — | — → — | $320/sf building |
| 06/10/2014 | $3.0M | — | EMAS ESTATE LLC → 358 GROVE LLC | $192/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| INCA ARCHITECTURE PLLC | 8 | 08/19/2026 |
| KINETIC SERVICES ENGINEERING PC | 4 | 04/28/2026 |
| GASBARRO STRUCTURAL ENGINEERING | 2 | 11/05/2024 |
| RIP CONSTRUCTION CONSULTANTS | 8 | 02/05/2024 |
| GUTH DECONZO CONSULTING ENGINEERS, | 1 | 07/19/2023 |
| STEEL CORE ENGINEERING PLLC | 1 | 03/03/2023 |
| Representative | Filings | Most Recent |
|---|---|---|
| RIP CC | 32 | 03/21/2026 |
| ADVANCED BUILDERS SERVICES | 3 | 03/21/2026 |
| CONVERSANO ASSOCIATES, INC. | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| C&M DRYWALL & ACOUSTIC CO | General Contractor | 11 | 07/08/2026 |
| EZ RUNER CONSTRUCTION COR | General Contractor | 4 | 03/21/2026 |
| ARMON MECHANICAL INC | Fire Protection | 1 | 07/08/2026 |
| ARMON MECHANICAL INC | Plumbing | 1 | 07/08/2026 |
| RIGID PLUMBING CONT INC | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| STEEL CORE ENGINEERING PL | 1098 | 7 | 08/19/2026 |
| KINETIC SERVICES ENGINEER | 5807 | 3 | 04/28/2026 |
| ALPHA ENGINEERING LLC | 3448 | 2 | 11/05/2024 |
| GASBARRO STRUCTURAL ENGIN | 5919 | 2 | 11/05/2024 |
| GUTH DECONZO CONSULTING E | 1210 | 1 | 07/19/2023 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Structural | Signed-off | C&M DRYWALL & ACOUSTIC CO | 09/15/2025 |
| DOB NOW | Sprinklers | Signed-off | ARMON MECHANICAL INC | 07/28/2025 |
| DOB NOW | Plumbing | Signed-off | ARMON MECHANICAL INC | 07/28/2025 |
| DOB NOW | Mechanical Systems | Signed-off | C&M DRYWALL & ACOUSTIC CO | 07/23/2025 |
| DOB NOW | Mechanical Systems | Signed-off | C&M DRYWALL & ACOUSTIC CO | 10/20/2023 |
| DOB NOW | General Construction | Signed-off | C&M DRYWALL & ACOUSTIC CO | 10/18/2023 |
| DOB NOW | Structural | Signed-off | C&M DRYWALL & ACOUSTIC CO | 09/06/2023 |
| DOB NOW | General Construction | Permit Issued | EZ RUNER CONSTRUCTION COR | 06/30/2023 |
| DOB NOW | Sprinklers | Signed-off | RIGID PLUMBING CONT INC | 03/08/2023 |
| DOB NOW | General Construction | Permit Issued | EZ RUNER CONSTRUCTION COR | 07/26/2022 |
| BIS | PL | ISSUED | EZ RUNER CONSTRUCTION CORP | 11/23/2022 |
| BIS | SP | ISSUED | RIGID PLBG CONTRACTORS IN | 12/22/2021 |
| BIS | OT | ISSUED | P.S.R. CONSTRUCTION/REN | 11/24/2021 |
| BIS | PL | ISSUED | EZ RUNER CONSTRUCTION CORP | 11/23/2021 |
| BIS | OT | ISSUED | P.S.R. CONSTRUCTION/REN | 08/26/2021 |
| BIS | OT | ISSUED | P.S.R. CONSTRUCTION/REN | 08/26/2021 |
| BIS | MH | ISSUED | P.S.R. CONSTRUCTION/REN | 08/26/2021 |
| BIS | SP | ISSUED | PHOENIX PLMBG & MECH CORP | 03/24/2021 |
| BIS | SP | ISSUED | PHOENIX PLMBG & MECH CORP | 11/01/2019 |
| BIS | OT | ISSUED | AVERSA BROS INDUST C0ONTRACTRS I | 10/02/2002 |
| BIS | FP | ISSUED | LUND FIRE PRODUCTS CO INC | 05/19/1999 |
| BIS | PL | ISSUED | PIEPER & SPROTTE, INC. | 03/01/1991 |
| BIS | OT | ISSUED | INDUSTRIAL REFRIGERATION INC. | 02/26/1991 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/28/2026 | Signed-off | ARMON MECHANICAL INC | 2 heads |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/05/2022 | Complete | RM ELECTRIC CO., INC. | General Wiring |
| Date | Type | Result | Report |
|---|---|---|---|
| 11/25/2025 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 11/20/2025 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 11/20/2025 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 10/21/2025 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 08/13/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 08/08/2025 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 08/06/2025 | Pass-Final House Connection | Pass | View ↗ |
| 09/06/2024 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 03/13/2024 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 10/18/2023 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 04/05/2023 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 04/03/2023 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 06/12/2026 | Public Assembly Emergency Lighting | david bench | progress |
| 06/03/2026 | Public Assembly Emergency Lighting | david bench | progress |
| 05/22/2026 | Sprinkler Systems | Joseph Weinschreider | special |
| 05/21/2026 | Fire-Resistance Rated Construction | david bench | progress |
| 05/21/2026 | Fenestration air leakage | david bench | energy_progress |
| 05/21/2026 | Energy Code Compliance Inspections | david bench | progress |
| 05/21/2026 | Fire-Resistant Penetrations and Joints | Alexander Sheyman | special |
| 05/21/2026 | Interior lighting power | david bench | energy_progress |
| 05/21/2026 | Fenestration areas | david bench | energy_progress |
| 05/21/2026 | Insulation placement and R values | david bench | energy_progress |
| 05/21/2026 | Fenestration and door U-factor and product ratings | david bench | energy_progress |
| 04/23/2026 | Sprinkler Systems | Joseph Weinschreider | special |
| 03/19/2025 | Energy Code Compliance Inspections | Joseph Weinschreider | progress |
| 03/19/2025 | HVAC-R and service water piping design and insulation | Joseph Weinschreider | energy_progress |
| 10/31/2024 | Structural Steel - Welding | AHMED ISA | special |
| 10/31/2024 | Structural Cold-Formed Steel | Thomas Gasbarro | special |
| 10/31/2024 | Structural Steel - Details | Thomas Gasbarro | special |
| 10/31/2024 | Structural Stability – Alterations of existing buildings | Thomas Gasbarro | special |
| 10/31/2024 | Post-installed Anchors | Thomas Gasbarro | special |
| 10/09/2024 | Final | Thomas Gasbarro | progress |
| 07/18/2023 | Fire-Resistance Rated Construction | david bench | progress |
| 07/18/2023 | Interior lighting power | david bench | energy_progress |
| 07/18/2023 | Lighting controls | david bench | energy_progress |
| 07/18/2023 | Energy Code Compliance Inspections | david bench | progress |
| 07/18/2023 | Fire-Resistant Penetrations and Joints | Alexander Sheyman | special |