← Back
BuildNYC
Parsonage, rectory
701 49TH STREET
BROOKLYN · BIN 3250700
💬 Discuss this project
1920Year Built
3Stories
M3Building Class
R6BZoning
80,545 sfGross Floor Area
3Units
LL97 Covered3 Active Violations 0 unresolved · 3 paperwork only ▸FDNY Report ↗
Parsonage, rectory · Owner of record: St Agathas Church · 26,625 sf lot · 3.03 FAR built · Flood zone X
Locations of Work
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
Floor 1St Agathas Church2 filings · 16 docs
CellarSt Agathas Church2 filings · 16 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
Rocklyn Asset803/21/2026
St Agathas Church103/22/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
Nelson and Pope406/18/2021
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
Archetype Consultants803/21/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
C.M. Testing Laboratory1352206/18/2021
Building Lifecycle
All (29)Filed (4)Violation (1)Objection (16)Special Inspection (8)
06/25/2021
Objection resolved — Addressed
06/25/2021
Objection resolved — Addressed
06/25/2021
Special inspection requirement — Mechanical Systems
JOHN SEMIOLI
06/25/2021
Special inspection requirement — Heating Systems
JOHN SEMIOLI
06/25/2021
Special inspection requirement — Final
JOHN SEMIOLI
06/25/2021
Special inspection requirement — Energy Code Compliance Inspections
JOHN SEMIOLI
06/25/2021
Special inspection requirement — HVAC and service water heating equipment
JOHN SEMIOLI
06/25/2021
Special inspection requirement — Maintenance information
JOHN SEMIOLI
06/25/2021
Special inspection requirement — HVAC insulation and sealing
JOHN SEMIOLI
06/25/2021
Special inspection requirement — HVAC and service water heating system controls
JOHN SEMIOLI
06/23/2021
Objection raised — Other
06/23/2021
Objection raised — Other
06/18/2021
Filed — Alteration
MECHANICAL CHANGES ON THE CELLAR AND FIRST FLOOR AS INDICATED ON DRAWINGS.
B00364448-P1
06/18/2021
Filed — Alteration
PLUMBING CHANGES ON THE CELLAR AND 1ST FLOOR AS INDICATED ON DRAWINGS.
B00364453-P1
10/28/2020
Objection resolved — Addressed
10/28/2020
Objection resolved — Addressed
10/28/2020
Objection resolved — Addressed
10/28/2020
Objection resolved — Addressed
10/28/2020
Objection resolved — Addressed
10/28/2020
Objection resolved — Addressed
09/17/2020
Objection raised — Scope
09/17/2020
Objection raised — Inspections
09/17/2020
Objection raised — Mechanical
09/17/2020
Objection raised — Fire_Protection
09/17/2020
Objection raised — Structural
09/17/2020
Objection raised — Fire_Protection
09/16/2020
Filed — Alteration
MECHANICAL CHANGES ON THE CELLAR AND FIRST FLOOR AS INDICATED ON DRAWINGS.
B00364448-I1
09/16/2020
Filed — Alteration
PLUMBING CHANGES ON THE CELLAR AND 1ST FLOOR AS INDICATED ON DRAWINGS.
B00364453-I1
01/01/2012
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
Nothing on file for this building.
1 project · most recent 06/18/2021
Heating Systems
FiledStatusContractorScope
06/18/2021——Heating Systems
1 project · most recent 06/18/2021
Water/Sanitary
FiledStatusContractorScope
06/18/2021——Water/Sanitary
▾Special Inspection Requirements (DOB NOW) — 8
DateRequirementInspectorRole
06/25/2021Mechanical SystemsJOHN SEMIOLIspecial
06/25/2021Heating SystemsJOHN SEMIOLIspecial
06/25/2021FinalJOHN SEMIOLIprogress
06/25/2021Energy Code Compliance InspectionsJOHN SEMIOLIprogress
06/25/2021HVAC and service water heating equipment JOHN SEMIOLIenergy_progress
06/25/2021Maintenance informationJOHN SEMIOLIenergy_progress
06/25/2021HVAC insulation and sealing JOHN SEMIOLIenergy_progress
06/25/2021HVAC and service water heating system controls JOHN SEMIOLIenergy_progress
▾Tenants in the building
TenantSpaceFloorsRenovation projects
St Agathas ChurchReligiousCellar, Floor 1
Project B00364448 Alteration · Approved · 09/16/2020
Project B00364453 Alteration · Approved · 09/16/2020
Names are taken automatically from the text of each project’s filed documents (title blocks and cover sheets) and screened to exclude owners, landlords and designers. They may be incomplete or wrong; check the filing.
▾Documents — 32 on file (BIS + DOB NOW)
▸Plans & Drawings4
▸DOB NOWPlans/Sketch - Plumbing2
09/02/2026B00364453-I1Request digital key ↗
08/14/2026B00364453-P1Request digital key ↗
▸DOB NOWPlans/Sketch - Mechanical Systems2
08/15/2026B00364448-P1Request digital key ↗
08/15/2026B00364448-I1Request digital key ↗
▸Applications & Permits1
▸BISPLAN / WORK APPROVAL APPLICATION1
02/23/2021340740229Open ↗
▸Seals & Professional Certifications13
▸DOB NOWProgress Inspector Seal & Signature6
08/28/2026B00364448-I1Open ↗
08/28/2026B00364448-I1Open ↗
08/28/2026B00364448-I1Open ↗
Showing 3 of 6 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature4
08/13/2026B00364453-P1Open ↗
08/13/2026B00364453-I1Open ↗
08/13/2026B00364448-I1Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature2
08/28/2026B00364448-I1Open ↗
08/28/2026B00364448-I1Open ↗
▸BISAPPLICANT OWNER SIGNATURE1
09/16/2020340740229Open ↗
▸Safety & Tenant Protection1
▸BISTENANT PROTECTION PLAN AND NOTES1
03/19/2021340740229Open ↗
▸Energy Compliance2
▸BISTR8: ENERGY CODE PROGRESS INSPS TECHNICAL REPORT1
02/23/2021340740229Open ↗
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY1
02/23/2021340740229Open ↗
▸Inspections & Test Reports5
▸BISTECHNICAL REPORT: RESPONSIBILITY4
07/08/2021340740229Open ↗
03/19/2021340740229Open ↗
03/19/2021340740229Open ↗
Showing 3 of 4 on file for this type
▸BISTECHNICAL REPORT: SOIL INSPECTION1
03/19/2021340740229Open ↗
▸Approvals, Objections & Sign-offs4
▸DOB NOWFee Exempt Supporting Document - DOF ACRIS report or BIB letter4
08/13/2026B00364448-P1Open ↗
08/13/2026B00364453-P1Open ↗
08/13/2026B00364453-I1Open ↗
Showing 3 of 4 on file for this type
▸Cost, Insurance & Ownership1
▸BISCOST AFFIDAVIT ESTIMATE: (PW3)1
02/23/2021340740229Open ↗
▸Filing & Intake Forms1
▸BISEFILING JOB APPLICATION COVER SHEET1
02/23/2021340740229Open ↗