← Back
Over six families without stores
701 VAN SICLEN AVENUE
BROOKLYN · BIN 3096823
💬 Discuss this project
1925Year Built
3Stories
C1Building Class
R6Zoning
3,668 sfGross Floor Area
10Units
Rent Stabilized5 Open Violations ▸FDNY Report ↗
Over six families without stores · Owner of record: 701 VAN SICLEN LLC · 2,875 sf lot · 1.28 FAR built · Flood zone X
Locations of Work
ArchitectureFire Protection
Roof15p · 1 filing · 20 docs
Floor 213p · 1 filing · 20 docs
Floor 113p · 1 filing · 20 docs
Basement15p · 1 filing · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
MS INVESTMENTS 31507/08/2026
701 VAN SICLEN LLC103/22/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
05/21/2025$1.1M—TIMMOLT WALSH PROPERTIES INC. → 701 VAN SICLEN LLC$305/sf building
12/02/2014$325K—Private party → DEED LEADERS INC.$89/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
AG ENGINEERING PLLC408/27/2025
VASILIOS ARTEMIOU PE104/22/2025
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
BMG GROUP USA403/21/2026
XPDITE GROUP LLC (104)103/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
REVAMP NYC CORPGeneral Contractor204/09/2026
AMOK INCFire Protection107/08/2026
AMOK INCPlumbing107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
SHAHRISH SHUVO ENGINEERIN8524508/27/2025
Building Lifecycle
All (139)Filed (5)Permit Issued (4)Signed Off (3)Violation (17)Inspection (12)Objection (68)Special Inspection (30)
05/06/2026
Violation issued (HPD, open)
A
01/08/2026
Violation issued (HPD, open)
C
01/08/2026
Violation issued (HPD, open)
C
01/08/2026
Violation issued (HPD, open)
B
01/08/2026
Violation issued (HPD, open)
B
11/24/2025
Violation issued (HPD, closed)
I
10/03/2025
Signed off — Alteration CO
SPRINKLER APPLICATION FILED HEREWITH IN CONJUNCTION TO ALT-CO APPLICATION B01126694-I1
B01126694-S1
09/12/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
Shahrish Shuvo
09/12/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
Shahrish Shuvo
09/12/2025
Special inspection requirement — Fire-Resistance Rated Construction
Shahrish Shuvo
09/12/2025
Special inspection requirement — Energy Code Compliance Inspections
Shahrish Shuvo
09/12/2025
Special inspection requirement — Air barrier - visual inspection
Shahrish Shuvo
09/12/2025
Special inspection requirement — Air barrier — testing
Shahrish Shuvo
09/12/2025
Special inspection requirement — Lighting in dwelling units
Shahrish Shuvo
09/12/2025
Special inspection requirement — Fenestration and door U-factor and product ratings
Shahrish Shuvo
09/12/2025
Special inspection requirement — Interior lighting power
Shahrish Shuvo
09/12/2025
Special inspection requirement — Exterior lighting power
Shahrish Shuvo
09/12/2025
Special inspection requirement — Lighting controls
Shahrish Shuvo
09/12/2025
Special inspection requirement — Fenestration areas
Shahrish Shuvo
09/12/2025
Special inspection requirement — Metering
Shahrish Shuvo
09/12/2025
Special inspection requirement — Permanent certificate
Shahrish Shuvo
09/12/2025
Special inspection requirement — Fenestration air leakage
Shahrish Shuvo
09/12/2025
Special inspection requirement — Maintenance information
Shahrish Shuvo
09/08/2025
Objection resolved — Addressed
09/05/2025
Objection raised — Scope
08/27/2025
Filed — Alteration CO
SPRINKLER APPLICATION FILED HEREWITH IN CONJUNCTION TO ALT-CO APPLICATION B01126694-I1
B01126694-P2
08/26/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
Shahrish Shuvo
08/26/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
Shahrish Shuvo
08/26/2025
Special inspection requirement — Energy Code Compliance Inspections
Shahrish Shuvo
08/26/2025
Special inspection requirement — Fire-Resistance Rated Construction
Shahrish Shuvo
08/26/2025
Special inspection requirement — Interior lighting power
Shahrish Shuvo
08/26/2025
Special inspection requirement — Air barrier — testing
Shahrish Shuvo
08/26/2025
Special inspection requirement — Maintenance information
Shahrish Shuvo
08/26/2025
Special inspection requirement — Fenestration air leakage
Shahrish Shuvo
08/26/2025
Special inspection requirement — Lighting controls
Shahrish Shuvo
08/26/2025
Special inspection requirement — Air barrier - visual inspection
Shahrish Shuvo
08/26/2025
Special inspection requirement — Metering
Shahrish Shuvo
08/26/2025
Special inspection requirement — Lighting in dwelling units
Shahrish Shuvo
08/26/2025
Special inspection requirement — Exterior lighting power
Shahrish Shuvo
08/26/2025
Special inspection requirement — Permanent certificate
Shahrish Shuvo
08/14/2025
Signed off — Alteration CO
SPRINKLER APPLICATION FILED HEREWITH IN CONJUNCTION TO ALT-CO APPLICATION B01126694-I1
B01126694-S3
08/07/2025
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
08/04/2025
Inspection — Certified Sprinkler-SP-Fixtures-Finish
Certified
View inspection ↗
08/04/2025
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
07/31/2025
Inspection — Fail-Final CND-Occupancy Inspection
Fail
View inspection ↗
07/30/2025
Inspection — Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test
Certified
View inspection ↗
07/23/2025
Signed off — Alteration CO
SPRINKLER APPLICATION FILED HEREWITH IN CONJUNCTION TO ALT-CO APPLICATION B01126694-I1
B01126694-S2
07/09/2025
Inspection — Certified Storm Drainage-ST-Piping-Underground
Certified
View inspection ↗
07/03/2025
Inspection — Certified Storm Drainage-ST-Piping-Underground
Certified
View inspection ↗
07/03/2025
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Underground
Certified
View inspection ↗
06/30/2025
Inspection — Certified Gas-Gas-Piping-Roughing
Certified
View inspection ↗
06/25/2025
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
06/25/2025
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Underground
Certified
View inspection ↗
06/11/2025
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Underground
Certified
View inspection ↗
06/06/2025
Permit issued — General Construction
B01126694-I1-GC
05/23/2025
Permit issued — Sprinklers
B01126694-S3-EW-SP
05/23/2025
Permit issued — Plumbing
B01126694-S1-PL
05/22/2025
Permit issued — Mechanical Systems
B01126694-S2-MS
05/14/2025
Objection resolved — Addressed
05/14/2025
Objection resolved — Addressed
Latest 60 of 139 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWGeneral ConstructionPermit IssuedREVAMP NYC CORP06/06/2025
DOB NOWSprinklersSigned-offAMOK INC05/23/2025
DOB NOWPlumbingSigned-offAMOK INC05/23/2025
DOB NOWMechanical SystemsSigned-offREVAMP NYC CORP05/22/2025
1 project · most recent 08/27/2025
Heating and Air Conditioning Systems
FiledStatusContractorScopeMake / Model / Capacity
08/27/2025Permit IssuedREVAMP NYC CORPHeating and Air Conditioning Systems
Heat / Cool
Daikin DAIKIN- 2MXM18AVJU9 DAIKIN- RXF12BVJU9 18,500 BTU ×9
DAIKIN - 3MXM24AVJU9 24,000 BTU · Heat Pump Outdoor ×1
1 project · most recent 08/27/2025
Sprinkler System
FiledStatusContractorScope
08/27/2025Signed-offAMOK INCSprinkler System
1 project · most recent 08/27/2025
Gas Water/Sanitary
FiledStatusContractorScope
08/27/2025Signed-offAMOK INCGas, Water/Sanitary
2 projects · most recent 08/08/2025
General Wiring
FiledStatusContractorScope
08/08/2025CompleteAG POWER ELECTRIC CORPGeneral Wiring
07/22/2025CompleteAG POWER ELECTRIC CORP—
▾Field Inspections (DOB CAP) — 12
DateTypeResultReport
08/07/2025Pass-Final CND-Occupancy InspectionPassView ↗
08/04/2025Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
08/04/2025Pass-Final PL - Up to 3 Requested FloorsPassView ↗
07/31/2025Fail-Final CND-Occupancy InspectionFailView ↗
07/30/2025Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
07/09/2025Certified Storm Drainage-ST-Piping-UndergroundCertifiedView ↗
07/03/2025Certified Storm Drainage-ST-Piping-UndergroundCertifiedView ↗
07/03/2025Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
06/30/2025Certified Gas-Gas-Piping-RoughingCertifiedView ↗
06/25/2025Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
06/25/2025Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
06/11/2025Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 38
DateRequirementInspectorRole
09/12/2025Structural Stability – Alterations of existing buildingsShahrish Shuvospecial
09/12/2025Fire-Resistant Penetrations and JointsShahrish Shuvospecial
09/12/2025Fire-Resistance Rated ConstructionShahrish Shuvoprogress
09/12/2025Energy Code Compliance InspectionsShahrish Shuvoprogress
09/12/2025Air barrier - visual inspectionShahrish Shuvoenergy_progress
09/12/2025Air barrier — testing Shahrish Shuvoenergy_progress
09/12/2025Lighting in dwelling unitsShahrish Shuvoenergy_progress
09/12/2025Fenestration and door U-factor and product ratingsShahrish Shuvoenergy_progress
09/12/2025Interior lighting powerShahrish Shuvoenergy_progress
09/12/2025Exterior lighting powerShahrish Shuvoenergy_progress
09/12/2025Lighting controlsShahrish Shuvoenergy_progress
09/12/2025Fenestration areasShahrish Shuvoenergy_progress
09/12/2025MeteringShahrish Shuvoenergy_progress
09/12/2025Permanent certificateShahrish Shuvoenergy_progress
09/12/2025Fenestration air leakageShahrish Shuvoenergy_progress
09/12/2025Maintenance informationShahrish Shuvoenergy_progress
08/26/2025Fire-Resistant Penetrations and JointsShahrish Shuvospecial
08/26/2025Structural Stability – Alterations of existing buildingsShahrish Shuvospecial
08/26/2025Energy Code Compliance InspectionsShahrish Shuvoprogress
08/26/2025Fire-Resistance Rated ConstructionShahrish Shuvoprogress
08/26/2025Interior lighting powerShahrish Shuvoenergy_progress
08/26/2025Air barrier — testing Shahrish Shuvoenergy_progress
08/26/2025Maintenance informationShahrish Shuvoenergy_progress
08/26/2025Fenestration air leakageShahrish Shuvoenergy_progress
08/26/2025Lighting controlsShahrish Shuvoenergy_progress
Latest 25 of 38.
▾Documents — 26 on file (BIS + DOB NOW)
▸Plans & Drawings5
▸DOB NOWPlans/Sketch5
08/20/2026B01126694-S3Request digital key ↗
08/20/2026B01126694-S1Request digital key ↗
08/20/2026B01126694-I1Request digital key ↗
Showing 3 of 5 on file for this type
▸Seals & Professional Certifications16
▸DOB NOWProgress Inspector Seal & Signature8
08/28/2026B01126694-S1Open ↗
08/28/2026B01126694-S1Open ↗
08/27/2026B01126694-P2Open ↗
Showing 3 of 8 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature5
08/13/2026B01126694-I1Open ↗
08/13/2026B01126694-S2Open ↗
08/13/2026B01126694-P2Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature3
08/28/2026B01126694-S1Open ↗
08/27/2026B01126694-P2Open ↗
08/24/2026B01126694-I1Open ↗
▸Safety & Tenant Protection2
▸DOB NOWStreet Tree Checklist2
08/13/2026B01126694-P2Open ↗
08/13/2026B01126694-I1Open ↗
▸Other Documents3
▸DOB NOWProperty Ownership Certification2
08/13/2026B01126694-I1Open ↗
08/13/2026B01126694-P2Open ↗
▸DOB NOWFinal Survey1
08/13/2026B01126694-I1Open ↗