DOB11/14/2025VIOLATION ISSUED-FAILURE TO FILE 2024 INTERNAL HGH PRESSURE INSPECTION
DOB11/14/2025VIOLATION ISSUED-FAILURE TO FILE 2024 EXTERNAL HGH PRESSURE INSPECTION
DOB11/14/2025VIOLATION ISSUED-FAILURE TO FILE 2024 EXTERNAL LOW PRESSURE INSPECTION
ECB11/04/2024FAILURE TO FILE REQUIRED ANNUAL BOILER INSPECTION REPORTS FOR LOW-PRESSURE BOILER 30000097719N0001 IN ACCORDANCE WITH THE RULES OF THE DEPARTMENT.1RCNY 103-01(D)(1)REQUIRES THAT AN ANNUAL INSPECTION REPORT FOR$3K due
DOB09/23/2024VIOLATION ISSUED-FAILURE TO FILE 2023 EXTERNAL LOW PRESSURE INSPECTION
DOB09/23/2024VIOLATION ISSUED-FAILURE TO FILE 2023 EXTERNAL HGH PRESSURE INSPECTION
DOB09/23/2024VIOLATION ISSUED-FAILURE TO FILE 2023 INTERNAL HGH PRESSURE INSPECTION
DOB06/30/2023VIOLATION ISSUED-FAILURE TO FILE 2020 EXTERNAL LOW PRESSURE INSPECTION
DOB06/30/2023VIOLATION ISSUED-FAILURE TO FILE 2021 INTERNAL HGH PRESSURE INSPECTION
DOB06/30/2023VIOLATION ISSUED-FAILURE TO FILE 2021 EXTERNAL LOW PRESSURE INSPECTION
DOB06/30/2023VIOLATION ISSUED-FAILURE TO FILE 2020 EXTERNAL HGH PRESSURE INSPECTION
DOB06/30/2023VIOLATION ISSUED-FAILURE TO FILE 2020 INTERNAL HGH PRESSURE INSPECTION
DOB06/30/2023VIOLATION ISSUED-FAILURE TO FILE 2021 EXTERNAL HGH PRESSURE INSPECTION
DOB06/20/2023VIOLATION ISSUED-FAILURE TO FILE 2018 EXTERNAL LOW PRESSURE INSPECTION
DOB06/20/2023VIOLATION ISSUED-FAILURE TO FILE 2019 EXTERNAL LOW PRESSURE INSPECTION
DOB04/25/2023VIOLATION ISSUED-FAILURE TO FILE 2022 EXTERNAL HIGH PRESSURE INSPECTION
DOB04/25/2023VIOLATION ISSUED-FAILURE TO FILE 2022 INTERNAL HIGH PRESSURE INSPECTION
DOB04/25/2023VIOLATION ISSUED-FAILURE TO FILE 2022 EXTERNAL LOW PRESSURE INSPECTION
DOB10/21/1991VP-VIOLATION UNSERVED ECB-ACTIVE
DOB10/21/1991V-DOB VIOLATION - ACTIVE
DOB10/21/1991VP-VIOLATION UNSERVED ECB-ACTIVE
DOB10/21/1991V-DOB VIOLATION - ACTIVE
DOB09/13/1991VP-VIOLATION UNSERVED ECB-ACTIVE
ECB10/20/2006HAZARDOUS, CEASE USE. 50A- A.O. SMITH HOT WATER HEATER SPILLING CARBONMONOXIDE FUMES DUE TO INCOMPLETE COMBUSTION LEVELS OF 3300-PPM. DETECTED IN BOILER RM.Nothing owed — awaiting certificate of correction
ECB09/14/199818A,18B,48A.Nothing owed — awaiting certificate of correction
ECB11/06/1991WORK DOES NOT CONFORM TO APPROVED PLANS. CONTRARY TO APPROVED PLANS DATED ACCEPTED 7/15/88. 1 ON THE EAST SIDE OF CELLAR CAST IRON PLUMBING DRAIN PIPES HAVE BEEN USED AS STRUCTURAL STEEL LOBBY COLUMNS. 2 AT WESNothing owed — awaiting certificate of correction
ECB11/06/1991WORK DOES NOT CONFORM TO APPROVED PLANS. CONTRARY TO APPROVED PLANS DATED ACCEPTED 7/15/88. 1 SIX 8" CONCRETE COLUMNS INSTALLED AT CENTER OF CELLAR UNDER CONCRETE SLAB, NOT SHOWN ON PLAN, OUT OF PLUMB AND NO CONothing owed — awaiting certificate of correction
ECB10/21/1991CONTRARY TO APPROVED PLANS DATED ACCEPTED 7/15/88 "WORK DOES NOT CONFORM TO APPROVED PLANS." 1 TRAP DOOR INSTALLED AT IST FLOOR TO CELLAR STAIRS. 2 NO HAND RAILS TO CELLAR STAIRS. 3 NO CONCRETE FILLED STAIR THRNothing owed — awaiting certificate of correction
Primarily 2 family with 1 store or office · 2,000 sf lot · 2 FAR built · Flood zone X