| Owner | Filings | Most Recent |
|---|---|---|
| OWNERS REP | 8 | 09/13/2026 |
| BLUE SHINE BUILDERS INC DBA BLUE SK | 23 | 08/21/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 06/18/2025 | $10.8M | — | 703 MYRTLE LLC → MYRTLE SPENCER LLC | — not available |
| Firm | Filings | Most Recent |
|---|---|---|
| SONI ENGINEERING CONSULTING | 4 | 08/11/2026 |
| PAUL PERDEK, PROF. ENG. PLLC | 1 | 07/28/2026 |
| ELEVATED ENGINEERING NYC | 4 | 06/29/2026 |
| VASILIOS ARTEMIOU PE | 4 | 03/10/2026 |
| AZSK ARCHITECTS PC | 3 | 02/05/2026 |
| ARYEH SIEGEL ARCHITECT | 1 | 05/30/2025 |
| Representative | Filings | Most Recent |
|---|---|---|
| EXPRESS FILING INC | 20 | 03/21/2026 |
| AVALON DESIGNS | 4 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| INNOVATIVE CONSTR NYC LLC | General Contractor | 7 | 08/21/2026 |
| CORE SCAFFOLD SYSTEMS INC. | General Contractor | 5 | 08/14/2026 |
| SWIFT SERVICES CORP | General Contractor | 1 | 04/09/2026 |
| MPI PLUMBING CORP | Plumbing | 1 | 07/23/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| NEXUS INSPECTIONS AND TES | 9686 | 7 | 06/29/2026 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Structural | Permit Issued | INNOVATIVE CONSTR NYC LLC | 08/20/2026 |
| DOB NOW | Protection and Mechanical Methods | Permit Issued | CORE SCAFFOLD SYSTEMS INC. | 08/13/2026 |
| DOB NOW | Protection and Mechanical Methods | Permit Issued | CORE SCAFFOLD SYSTEMS INC. | 08/11/2026 |
| DOB NOW | Supported Scaffold | Permit Issued | CORE SCAFFOLD SYSTEMS INC. | 07/28/2026 |
| DOB NOW | Protection and Mechanical Methods | Permit Issued | CORE SCAFFOLD SYSTEMS INC. | 07/27/2026 |
| DOB NOW | Sidewalk Shed | Permit Issued | CORE SCAFFOLD SYSTEMS INC. | 07/27/2026 |
| DOB NOW | Plumbing | Permit Issued | MPI PLUMBING CORP | 07/22/2026 |
| DOB NOW | Structural | Permit Issued | INNOVATIVE CONSTR NYC LLC | 06/17/2026 |
| DOB NOW | Structural | Permit Issued | INNOVATIVE CONSTR NYC LLC | 06/10/2026 |
| DOB NOW | Support of Excavation | Permit Issued | INNOVATIVE CONSTR NYC LLC | 06/10/2026 |
| DOB NOW | Earth Work | Permit Issued | INNOVATIVE CONSTR NYC LLC | 06/10/2026 |
| DOB NOW | Construction Fence | Permit Issued | INNOVATIVE CONSTR NYC LLC | 06/10/2026 |
| DOB NOW | Full Demolition | Signed-off | SWIFT SERVICES CORP | 03/11/2026 |
| DOB NOW | Construction Fence | Permit Issued | INNOVATIVE CONSTR NYC LLC | 01/12/2026 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 06/29/2026 | Permit Issued | INNOVATIVE CONSTR NYC LLC | Heating and Air Conditioning Systems | Heat / Cool Daikin RXTA48AAVJU 52,000 BTU · Vrf Outdoor ×23 RXTA60AAVJU 60,000 BTU · Vrf Outdoor ×16 RXTA36AAVJU 40,000 BTU · Vrf Outdoor ×2 RZA18AAVJU 20,000 BTU · Condensing Unit ×1 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/29/2026 | — | — | Sprinkler System |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/29/2026 | Permit Issued | MPI PLUMBING CORP | Gas, Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/08/2026 | Permit Issued | KWONG MING ELECTRIC INC | — |
| 08/07/2026 | Permit Issued | SOLAS ELECTRICAL CORP | — |
| 07/28/2026 | Permit Issued | SOLAS ELECTRICAL CORP | — |
| 06/21/2026 | Permit Issued | HIVOLTS ELECTRICAL INC | 1 meters, 1 new_meters |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/29/2026 | Permit Issued | INNOVATIVE CONSTR NYC LLC | Concrete |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/28/2026 | Permit Issued | CORE SCAFFOLD SYSTEMS INC | Scaffold |
| 06/29/2026 | Permit Issued | INNOVATIVE CONSTR NYC LLC | Fence |
| 05/30/2025 | Permit Issued | INNOVATIVE CONSTR NYC LLC | Fence |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/29/2026 | Permit Issued | INNOVATIVE CONSTR NYC LLC | Earthwork |
| Date | Type | Result | Report |
|---|---|---|---|
| 08/06/2026 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 08/06/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 03/02/2026 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 02/27/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 01/08/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 12/16/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 10/10/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 07/28/2026 | Excavations - Sheeting, Shoring, and Bracing | Junda Qiu | special |
| 07/28/2026 | Construction Operations Influencing Adjacent Structures | Junda Qiu | special |
| 07/28/2026 | Structural Steel - Details | — | special |
| 07/28/2026 | Subsurface Conditions – Fill Placement & In-Place Density | Junda Qiu | special |
| 07/28/2026 | Subsurface Investigations (Borings/Test Pits) | Bin Li | special |
| 07/28/2026 | Post-installed Anchors | — | special |
| 07/28/2026 | Structural Steel - Welding | — | special |
| 07/28/2026 | Subgrade Inspections | Junda Qiu | special |
| 06/29/2026 | Structural Steel - Details | — | special |
| 06/29/2026 | Structural Steel - Welding | — | special |
| 06/29/2026 | Post-installed Anchors | — | special |
| 06/26/2026 | Subgrade Inspections | Junda Qiu | special |
| 06/26/2026 | Subsurface Conditions – Fill Placement & In-Place Density | Junda Qiu | special |
| 06/26/2026 | Construction Operations Influencing Adjacent Structures | Junda Qiu | special |
| 06/26/2026 | Excavations - Sheeting, Shoring, and Bracing | Junda Qiu | special |
| 06/26/2026 | Subsurface Investigations (Borings/Test Pits) | Bin Li | special |
| 03/16/2026 | HVAC-R and service water heating equipment | Junda Qiu | energy_progress |
| 03/16/2026 | HVAC-R and service water piping design and insulation | Junda Qiu | energy_progress |
| 03/16/2026 | HVAC-R and service water heating system controls | Junda Qiu | energy_progress |
| 03/16/2026 | Maintenance information | Junda Qiu | energy_progress |
| 03/10/2026 | Energy Code Compliance Inspections | — | progress |
| 03/10/2026 | Post-installed Anchors | — | special |
| 03/10/2026 | Fire-Resistant Penetrations and Joints | — | special |
| 03/10/2026 | HVAC-R and service water heating system controls | — | energy_progress |
| 03/10/2026 | Maintenance information | — | energy_progress |