← Back
Three families
709 EAST 215 STREET
BRONX · Williamsbridge-Olinville · BIN 2112899
💬 Discuss this project
2004Year Built
3Stories
C0Building Class
R7AZoning
3,723 sfGross Floor Area
3Units
Rent Stabilized0 Open ViolationsFDNY Report ↗
Three families · Owner of record: 709 EAST 215 LLC · 2,610 sf lot · 1.43 FAR built · Flood zone X
Locations of Work
ArchitectureMechanicalPlumbingFire Protection
Roof13p · 1 filing · 20 docs
Floor 313p · 1 filing · 20 docs
Floor 248p · 1 filing · 20 docs
Floor 113p · 1 filing · 20 docs
Site & exterior13p · 1 filing · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
WESTORCHARD MANAGEMENT907/08/2026
DARECO HOLDING503/21/2026
709 EAST 215 LLC103/22/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
07/16/2024$975K—— → —$262/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
ADB ASSOCIATES904/21/2025
VASILIOS ARTEMIOU PE209/11/2024
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
NYC DESIGN FILE1103/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
MABE GROUP INCGeneral Contractor407/08/2026
A M B MECHANICALGeneral Contractor203/22/2026
PRIME PIPING & HEATING INPlumbing207/08/2026
PRIME PIPING & HEATING INFire Protection107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
HRF SERVICES CORP5616604/21/2025
Building Lifecycle
All (81)Filed (11)Permit Issued (4)Signed Off (3)Violation (14)Inspection (9)Objection (10)Special Inspection (30)
10/03/2025
Signed off — Alteration CO
Filing sprinkler application subsequent to primary approved job #X01023898-I1
X01023898-S2
07/01/2025
Signed off — Alteration CO
Filing sprinkler application subsequent to primary approved job #X01023898-I1
X01023898-S3
05/13/2025
Inspection — Pass-Final SP - Up to 9 Requested Floors
Pass
View inspection ↗
04/30/2025
Special inspection requirement — Maintenance information
FAHAD FATEH
04/30/2025
Special inspection requirement — Interior lighting power
FAHAD FATEH
04/30/2025
Special inspection requirement — Fire-Resistance Rated Construction
FAHAD FATEH
04/30/2025
Special inspection requirement — Fenestration areas
FAHAD FATEH
04/30/2025
Special inspection requirement — Fenestration and door U-factor and product ratings
FAHAD FATEH
04/30/2025
Special inspection requirement — Energy Code Compliance Inspections
FAHAD FATEH
04/30/2025
Special inspection requirement — Metering
FAHAD FATEH
04/30/2025
Special inspection requirement — Permanent certificate
FAHAD FATEH
04/30/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
FAHAD FATEH
04/30/2025
Special inspection requirement — Fenestration air leakage
FAHAD FATEH
04/30/2025
Special inspection requirement — Insulation placement and R values
FAHAD FATEH
04/30/2025
Special inspection requirement — Air barrier - visual inspection
FAHAD FATEH
04/30/2025
Special inspection requirement — Exterior Insulation and Finish Systems (EIFS)
FAHAD FATEH
04/21/2025
Filed — Alteration CO
Filing sprinkler application subsequent to primary approved job #X01023898-I1
X01023898-P8
04/21/2025
Special inspection requirement — Exterior Insulation and Finish Systems (EIFS)
FAHAD FATEH
04/21/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
FAHAD FATEH
04/21/2025
Special inspection requirement — Energy Code Compliance Inspections
FAHAD FATEH
04/21/2025
Special inspection requirement — Fenestration air leakage
FAHAD FATEH
04/21/2025
Special inspection requirement — Maintenance information
FAHAD FATEH
04/21/2025
Special inspection requirement — Fenestration areas
FAHAD FATEH
04/21/2025
Special inspection requirement — Interior lighting power
FAHAD FATEH
04/21/2025
Special inspection requirement — Air barrier - visual inspection
FAHAD FATEH
04/21/2025
Special inspection requirement — Insulation placement and R values
FAHAD FATEH
04/21/2025
Special inspection requirement — Fenestration and door U-factor and product ratings
FAHAD FATEH
04/21/2025
Special inspection requirement — Fire-Resistance Rated Construction
FAHAD FATEH
04/21/2025
Special inspection requirement — Metering
FAHAD FATEH
04/21/2025
Special inspection requirement — Permanent certificate
FAHAD FATEH
04/17/2025
Inspection — Pass-Final SP - Up to 9 Requested Floors
Pass
View inspection ↗
04/10/2025
Signed off — Alteration CO
Filing sprinkler application subsequent to primary approved job #X01023898-I1
X01023898-S1
03/31/2025
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
03/27/2025
Inspection — Pass-Final SP - Up to 9 Requested Floors
Pass
View inspection ↗
03/17/2025
Inspection — Fail-Final SP - Up to 3 Requested Floors
Fail
View inspection ↗
03/07/2025
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
01/27/2025
Inspection — Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test
Certified
View inspection ↗
12/19/2024
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
12/19/2024
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Underground
Certified
View inspection ↗
12/02/2024
Permit issued — Sprinklers
X01023898-S3-EW-SP
12/02/2024
Permit issued — Plumbing
X01023898-S2-PL
11/25/2024
Violation issued (HPD, closed)
I
11/13/2024
Filed — Alteration CO
Filing sprinkler application subsequent to primary approved job #X01023898-I1
X01023898-P7
11/13/2024
Special inspection requirement — Air barrier - visual inspection
FAHAD FATEH
11/13/2024
Special inspection requirement — Fenestration and door U-factor and product ratings
FAHAD FATEH
11/13/2024
Special inspection requirement — Permanent certificate
FAHAD FATEH
11/13/2024
Special inspection requirement — Fenestration air leakage
FAHAD FATEH
10/29/2024
Permit issued — Mechanical Systems
X01023898-S1-MS
10/17/2024
Permit issued — General Construction
X01023898-I1-GC
09/26/2024
Filed — Alteration CO
Filing sprinkler application subsequent to primary approved job #X01023898-I1
X01023898-P6
09/23/2024
Filed — Alteration CO
Filing sprinkler application subsequent to primary approved job #X01023898-I1
X01023898-P4
09/19/2024
Filed — Alteration CO
Filing sprinkler application subsequent to primary approved job #X01023898-I1
X01023898-P5
09/11/2024
Filed — Alteration CO
Filing sprinkler application subsequent to primary approved job #X01023898-I1
X01023898-P3
09/05/2024
Objection resolved — Addressed
06/14/2024
Objection resolved — Addressed
06/14/2024
Objection resolved — Addressed
06/14/2024
Objection resolved — Addressed
06/13/2024
Objection raised — Other
06/11/2024
Filed — Alteration CO
Filing sprinkler application subsequent to primary approved job #X01023898-I1
X01023898-P1
05/20/2024
Objection resolved — Addressed
Latest 60 of 81 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSprinklersSigned-offA M B MECHANICAL INC12/02/2024
DOB NOWPlumbingSigned-offPRIME PIPING & HEATING IN12/02/2024
DOB NOWMechanical SystemsSigned-offAB BUILDERS NY10/29/2024
DOB NOWGeneral ConstructionPermit IssuedAB BUILDERS NY10/17/2024
BIS—ISSUEDFAS LLC05/18/2005
BISPLISSUEDVITELLO P & MECHANICAL INC01/05/2005
BISEQISSUEDFAS LLC12/28/2004
BISEQISSUEDFAS LLC08/20/2004
1 project · most recent 04/21/2025
Heating and Air Conditioning Systems Ventilation Systems
FiledStatusContractorScopeMake / Model / Capacity
04/21/2025Signed-offAB BUILDERS NYHeating and Air Conditioning Systems, Ventilation Systems
Heat / Cool
Daikin RXS12LVJUA 108,000 BTU · Heat Pump Outdoor ×9
2MXS18NMVJUA 18,000 BTU · Heat Pump Outdoor ×1
Ventilation
Nutone 2MXS18NMVJUA 150 CFM · Kitchen Exhaust ×10
AEN110 110 CFM · Exhaust Fan ×10
1 project · most recent 04/21/2025
Sprinkler System
FiledStatusContractorScope
04/21/2025Signed-offPRIME PIPING & HEATING INSprinkler System
1 project · most recent 03/17/2025
General Wiring
FiledStatusContractorScope
03/17/2025CompletePOWER DIRECT ELECTRIC INCGeneral Wiring
▾Field Inspections (DOB CAP) — 9
DateTypeResultReport
05/13/2025Pass-Final SP - Up to 9 Requested FloorsPassView ↗
04/17/2025Pass-Final SP - Up to 9 Requested FloorsPassView ↗
03/31/2025Pass-Final CND-Occupancy InspectionPassView ↗
03/27/2025Pass-Final SP - Up to 9 Requested FloorsPassView ↗
03/17/2025Fail-Final SP - Up to 3 Requested FloorsFailView ↗
03/07/2025Pass-Final CND-Occupancy InspectionPassView ↗
01/27/2025Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
12/19/2024Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
12/19/2024Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 90
DateRequirementInspectorRole
04/30/2025Exterior Insulation and Finish Systems (EIFS)FAHAD FATEHspecial
04/30/2025Air barrier - visual inspectionFAHAD FATEHenergy_progress
04/30/2025Fenestration and door U-factor and product ratingsFAHAD FATEHenergy_progress
04/30/2025MeteringFAHAD FATEHenergy_progress
04/30/2025Insulation placement and R valuesFAHAD FATEHenergy_progress
04/30/2025Permanent certificateFAHAD FATEHenergy_progress
04/30/2025Fenestration areasFAHAD FATEHenergy_progress
04/30/2025Interior lighting powerFAHAD FATEHenergy_progress
04/30/2025Maintenance informationFAHAD FATEHenergy_progress
04/30/2025Fenestration air leakageFAHAD FATEHenergy_progress
04/30/2025Energy Code Compliance InspectionsFAHAD FATEHprogress
04/30/2025Fire-Resistance Rated ConstructionFAHAD FATEHprogress
04/30/2025Fire-Resistant Penetrations and JointsFAHAD FATEHspecial
04/21/2025Exterior Insulation and Finish Systems (EIFS)FAHAD FATEHspecial
04/21/2025Maintenance informationFAHAD FATEHenergy_progress
04/21/2025Fenestration air leakageFAHAD FATEHenergy_progress
04/21/2025Permanent certificateFAHAD FATEHenergy_progress
04/21/2025Fenestration and door U-factor and product ratingsFAHAD FATEHenergy_progress
04/21/2025Fenestration areasFAHAD FATEHenergy_progress
04/21/2025Insulation placement and R valuesFAHAD FATEHenergy_progress
04/21/2025Air barrier - visual inspectionFAHAD FATEHenergy_progress
04/21/2025Interior lighting powerFAHAD FATEHenergy_progress
04/21/2025MeteringFAHAD FATEHenergy_progress
04/21/2025Fire-Resistance Rated ConstructionFAHAD FATEHprogress
04/21/2025Energy Code Compliance InspectionsFAHAD FATEHprogress
Latest 25 of 90.
▾Documents — 62 on file (BIS + DOB NOW)
▸Plans & Drawings11
▸DOB NOWPlans/Sketch11
08/20/2026X01023898-P4Request digital key ↗
08/20/2026X01023898-P3Request digital key ↗
08/20/2026X01023898-S2Request digital key ↗
Showing 3 of 11 on file for this type
▸Seals & Professional Certifications28
▸DOB NOWDPL-1: Design Professional Seal & Signature11
08/20/2026X01023898-P4Open ↗
08/20/2026X01023898-P3Open ↗
08/20/2026X01023898-P1Open ↗
Showing 3 of 11 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature9
09/27/2026X01023898-P7Open ↗
09/27/2026X01023898-P7Open ↗
09/01/2026X01023898-P8Open ↗
Showing 3 of 9 on file for this type
▸DOB NOWProgress Inspector Seal & Signature8
09/27/2026X01023898-P7Open ↗
09/27/2026X01023898-P7Open ↗
09/01/2026X01023898-P8Open ↗
Showing 3 of 8 on file for this type
▸Safety & Tenant Protection6
▸DOB NOWStreet Tree Checklist6
08/20/2026X01023898-P5Open ↗
08/20/2026X01023898-I1Open ↗
08/20/2026X01023898-P8Open ↗
Showing 3 of 6 on file for this type
▸Environmental & Asbestos11
▸DOB NOWDEP ACP-5: Asbestos Assessment Report11
08/20/2026X01023898-P4Open ↗
08/20/2026X01023898-P3Open ↗
08/20/2026X01023898-S2Open ↗
Showing 3 of 11 on file for this type
▸Other Documents6
▸DOB NOWProperty Ownership Certification6
08/20/2026X01023898-P5Open ↗
08/20/2026X01023898-I1Open ↗
08/20/2026X01023898-P8Open ↗
Showing 3 of 6 on file for this type