← Back
Two family brick
71-53 71 PLACE
QUEENS · BIN 4089862
💬 Discuss this project
1910Year Built
2Stories
B1Building Class
R4-1Zoning
2,296 sfGross Floor Area
2Units
1 Open Violation ▸
Two family brick · 1,593 sf lot · 1.44 FAR built · Flood zone X
Locations of Work
Cellar1p · 1 filing · 5 docs
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
03/15/2022$880K—— → —$383/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
QUAMAR ZAMAN310/22/2023
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
TD CONSULTING & EXPEDITING603/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
K.N.C ELECTRIC INCElectrical103/22/2026
US FOLKES CONSTRUCTIONGeneral Contractor107/08/2026
ROCK E SMALL PLBG&HTG INCPlumbing107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
ASKON ARCHITECT, P.C.3596210/22/2023
Building Lifecycle
All (27)Filed (3)Permit Issued (2)Signed Off (2)Violation (4)Inspection (5)Objection (8)Special Inspection (3)
01/16/2024
Signed off — Alteration
General construction renovation of building for relocation of kitchens on the 1st and 2nd floor. New bathroom in cellar.
Q08050054-I1
01/12/2024
Signed off — Alteration
Plumbing renovation of building for relocation of kitchens on 1st and 2nd floor. New bathroom in cellar. Work include Restrictive declaration for three (3) cellar bathroom.
Q08050056-I1
11/02/2023
Special inspection requirement — Fire-Resistant Penetrations and Joints
Akeeb Shekoni
10/22/2023
Filed — Alteration
Plumbing renovation of building for relocation of kitchens on 1st and 2nd floor. New bathroom in cellar. Work include Restrictive declaration for three (3) cellar bathroom.
Q08050056-P1
09/06/2023
Special inspection requirement — Fire-Resistant Penetrations and Joints
Akeeb Shekoni
08/28/2023
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
08/17/2023
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
07/28/2023
Inspection — Certified Gas-Gas-Piping-Roughing
Certified
View inspection ↗
07/28/2023
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
07/28/2023
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Underground
Certified
View inspection ↗
03/23/2023
Permit issued — Plumbing
Q08050056-I1-PL
01/26/2023
Permit issued — General Construction
Q08050054-I1-GC
12/29/2022
Objection raised — Zoning
12/29/2022
Objection resolved — Addressed
12/29/2022
Objection raised — Scope
12/29/2022
Objection resolved — Addressed
12/29/2022
Objection raised — Zoning
12/29/2022
Objection resolved — Addressed
12/29/2022
Objection raised — Other
12/29/2022
Objection resolved — Addressed
12/19/2022
Filed — Alteration
General construction renovation of building for relocation of kitchens on the 1st and 2nd floor. New bathroom in cellar.
Q08050054-I1
12/19/2022
Filed — Alteration
Plumbing renovation of building for relocation of kitchens on 1st and 2nd floor. New bathroom in cellar. Work include Restrictive declaration for three (3) cellar bathroom.
Q08050056-I1
12/05/2022
Special inspection requirement — Final
QUAMAR ZAMAN
10/22/2018
Violation issued (HPD, open)
I
10/18/2018
Violation issued (HPD, closed)
C
10/18/2018
Violation issued (HPD, closed)
B
10/18/2018
Violation issued (HPD, closed)
C
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWPlumbingSigned-offROCK E SMALL PLBG&HTG INC03/23/2023
DOB NOWGeneral ConstructionSigned-offUS FOLKES CONSTRUCTION01/26/2023
1 project · most recent 08/29/2022
General Wiring
FiledStatusContractorScope
08/29/2022Permit IssuedK.N.C ELECTRIC INCGeneral Wiring
▾Field Inspections (DOB CAP) — 5
DateTypeResultReport
08/28/2023Pass-Final PL - Up to 3 Requested FloorsPassView ↗
08/17/2023Pass-Final PL - Up to 3 Requested FloorsPassView ↗
07/28/2023Certified Gas-Gas-Piping-RoughingCertifiedView ↗
07/28/2023Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
07/28/2023Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 3
DateRequirementInspectorRole
11/02/2023Fire-Resistant Penetrations and JointsAkeeb Shekonispecial
09/06/2023Fire-Resistant Penetrations and JointsAkeeb Shekonispecial
12/05/2022FinalQUAMAR ZAMANprogress
▾Documents — 15 on file (BIS + DOB NOW)
▸Plans & Drawings3
▸DOB NOWPlans/Sketch3
08/25/2026Q08050056-P1Request digital key ↗
08/25/2026Q08050056-I1Request digital key ↗
08/14/2026Q08050054-I1Request digital key ↗
▸Zoning, Tax Lot & Property Records3
▸DOB NOWRestrictive Declaration/Easement 13
08/13/2026Q08050056-P1Open ↗
08/13/2026Q08050054-I1Open ↗
08/13/2026Q08050056-I1Open ↗
▸Seals & Professional Certifications6
▸DOB NOWDPL-1: Design Professional Seal & Signature3
08/25/2026Q08050056-I1Open ↗
08/25/2026Q08050056-P1Open ↗
08/13/2026Q08050054-I1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature2
08/29/2026Q08050056-P1Open ↗
08/22/2026Q08050056-I1Open ↗
▸DOB NOWProgress Inspector Seal & Signature1
08/23/2026Q08050054-I1Open ↗
▸Environmental & Asbestos3
▸DOB NOWDEP ACP-5: Asbestos Assessment Report3
08/25/2026Q08050056-P1Open ↗
08/25/2026Q08050056-I1Open ↗
08/13/2026Q08050054-I1Open ↗