← Back
Zoned commercial or Manhattan residential
713 EAST 235TH STREET
BRONX · Wakefield-Woodlawn · BIN 2068238
💬 Discuss this project
0Year Built
—Stories
V1Building Class
R6Zoning
0 sfGross Floor Area
0Units
0 Open Violations
Zoned commercial or Manhattan residential · Owner of record: 713 EAST 235TH LLC · 2,290 sf lot · 0 FAR built · Flood zone X
Locations of Work
ElectricalMechanicalPlumbingFire ProtectionGeneral
Permit Issued — active, not yet Signed-off
Floor 3Under Construction14p · 3 filings · 20 docs
Floor 2Under Construction14p · 3 filings · 20 docs
Floor 1Under Construction17p · 4 filings · 20 docs
Site & exterior2p · 1 filing · 2 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
UNITED 24412209/15/2026
713 EAST 235TH403/21/2026
ENTIRE REMODELLING CONSTRUCTION103/21/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
05/15/2020$490K—— → —— not available
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
PIROOZ ENGINEERING, P.C.807/31/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
IVAN ROSA LLCGeneral Contractor1207/08/2026
INFINITI ESC PLUMBING CORPlumbing507/08/2026
GO PRO FIRE PROTECTION CFire Protection107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
PIROOZ ENGINEERING P.C7177607/24/2026
IP CONCRETE TESTING AND I6252112/11/2020
Building Lifecycle
All (76)Filed (8)Permit Issued (8)Signed Off (3)Violation (16)Inspection (15)Objection (6)Special Inspection (20)
09/23/2026
Objection resolved — Addressed
08/25/2026
Signed off — Alteration
X01094752-I1
08/24/2026
Inspection — Pass-Final Curb Cut Non-Directive 14
Pass
View inspection ↗
08/12/2026
Objection raised — Other
07/31/2026
Filed — Alteration
X01094752-P1
07/28/2026
Inspection — Fail-Final Curb Cut Non-Directive 14
Fail
View inspection ↗
07/24/2026
Filed — Alteration
INSTALLATION OF A NEW MECHANICAL SYSTEM
X00435381-P2
07/20/2026
Special inspection requirement — Heating Systems
PIROOZ SOLTANIZADEH
07/20/2026
Special inspection requirement — Mechanical Systems
PIROOZ SOLTANIZADEH
07/20/2026
Special inspection requirement — Final
SHAHRIAR QUAYYUM
07/20/2026
Special inspection requirement — HVAC insulation and sealing
PIROOZ SOLTANIZADEH
07/20/2026
Special inspection requirement — HVAC and service water heating equipment
PIROOZ SOLTANIZADEH
07/20/2026
Special inspection requirement — HVAC and service water heating system controls
PIROOZ SOLTANIZADEH
06/01/2026
Permit issued — Mechanical Systems
X00435381-I1-MS
05/19/2026
Objection resolved — Addressed
05/19/2026
Special inspection requirement — Final
SHAHRIAR QUAYYUM
05/19/2026
Special inspection requirement — Heating Systems
PIROOZ SOLTANIZADEH
05/19/2026
Special inspection requirement — Mechanical Systems
PIROOZ SOLTANIZADEH
05/19/2026
Special inspection requirement — HVAC and service water heating equipment
PIROOZ SOLTANIZADEH
05/19/2026
Special inspection requirement — HVAC insulation and sealing
PIROOZ SOLTANIZADEH
05/19/2026
Special inspection requirement — HVAC and service water heating system controls
PIROOZ SOLTANIZADEH
05/15/2026
Objection raised — Other
05/11/2026
Inspection — Fail-Final Curb Cut Non-Directive 14
Fail
View inspection ↗
05/04/2026
Filed — Alteration
INSTALLATION OF A NEW MECHANICAL SYSTEM
X00435381-P1
05/04/2026
Signed off — Alteration
INSTALLATION OF SPRINKLER HEADS AND RELATED PIPINGS IN CONJUNCTION WITH NEW BUILDING APPLICATION NUMBER 240290993
X00435386-I1
05/04/2026
Permit issued — Curb Cut
X01094752-I1-CC
05/04/2026
Special inspection requirement — HVAC insulation and sealing
PIROOZ SOLTANIZADEH
05/04/2026
Special inspection requirement — HVAC and service water heating system controls
PIROOZ SOLTANIZADEH
05/04/2026
Special inspection requirement — Heating Systems
PIROOZ SOLTANIZADEH
05/04/2026
Special inspection requirement — Final
05/04/2026
Special inspection requirement — HVAC and service water heating equipment
PIROOZ SOLTANIZADEH
05/04/2026
Special inspection requirement — Mechanical Systems
PIROOZ SOLTANIZADEH
05/01/2026
Signed off — Alteration
X00558256-I1
04/27/2026
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
03/25/2026
Inspection — Certified Sprinkler-SP-Fixtures-Finish
Certified
View inspection ↗
03/23/2026
Inspection — Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test
Certified
View inspection ↗
10/24/2025
Violation issued (ECB, closed)
Construction
10/24/2025
Violation issued (ECB, closed)
Construction
08/01/2025
Inspection — Certified Gas-Gas-Piping-Roughing
Certified
View inspection ↗
08/01/2025
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
08/01/2025
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Underground
Certified
View inspection ↗
07/29/2025
Inspection — Certified Remove/Cap - work done in accordance with code
Certified
View inspection ↗
06/02/2025
Permit issued — Construction Fence
X00558256-I1-FN
05/05/2025
Permit issued — Sprinklers
X00435386-I1-EW-SP
02/06/2025
Inspection — Certified Storm Drainage-ST-Piping-Roughing
Certified
View inspection ↗
02/06/2025
Inspection — Certified Storm Drainage-ST-Piping-Underground
Certified
View inspection ↗
02/06/2025
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
02/06/2025
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Underground
Certified
View inspection ↗
01/24/2025
Permit issued — Plumbing
X00435384-I1-PL
01/02/2025
Filed — Alteration
X01094752-I1
01/02/2025
Objection raised — Structural
01/02/2025
Objection resolved — Addressed
10/25/2024
Violation issued (ECB, closed)
Construction
06/04/2024
Permit issued — Construction Fence
X00558256-I1-FN
10/27/2023
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
02/07/2023
Permit issued — Construction Fence
X00558256-I1-FN
02/23/2022
Permit issued — Construction Fence
X00558256-I1-FN
02/04/2022
Filed — Alteration
X00558256-I1
12/14/2020
Filed — Alteration
INSTALLATION OF A NEW MECHANICAL SYSTEM
X00435381-I1
12/11/2020
Filed — Alteration
X00435384-I1
Latest 60 of 76 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWMechanical SystemsPermit IssuedIVAN ROSA LLC06/01/2026
DOB NOWCurb CutSigned-offIVAN ROSA LLC05/04/2026
DOB NOWConstruction FenceSigned-offIVAN ROSA LLC06/02/2025
DOB NOWSprinklersSigned-offGO PRO FIRE PROTECTION C05/05/2025
DOB NOWPlumbingSigned-offINFINITI ESC PLUMBING COR01/24/2025
DOB NOWConstruction FenceSigned-offIVAN ROSA LLC06/04/2024
DOB NOWConstruction FenceSigned-offIVAN ROSA LLC02/07/2023
DOB NOWConstruction FenceSigned-offIVAN ROSA LLC02/23/2022
BIS—ISSUEDIVAN ROSA LLC11/13/2025
BIS—ISSUEDIVAN ROSA LLC09/10/2025
BIS—ISSUEDIVAN ROSA LLC11/15/2024
BIS—ISSUEDIVAN ROSA LLC10/21/2024
BIS—ISSUEDIVAN ROSA LLC06/03/2024
BIS—ISSUEDIVAN ROSA LLC10/20/2023
BIS—ISSUEDIVAN ROSA LLC10/20/2023
BIS—ISSUEDNAB MGMT.ASSOC.S,INC.06/14/2007
1 project · most recent 07/24/2026
Heating and Air Conditioning Systems Ventilation Systems
FiledStatusContractorScopeMake / Model / Capacity
07/24/2026Permit IssuedIVAN ROSA LLCHeating and Air Conditioning Systems, Ventilation Systems
Heat / Cool
Mitsubishi Electric MXZ-8C48NAHZ2, MSZ-FS09NA, MSZ-FS09NA, MSZ-FS09NA, MSZ-FS12NA 48,000 BTU · Heat Pump Outdoor ×2
MXZ-4C36NA2, MSZ-GL09NA, MSZ-GL09NA,MSZ-GL12 36,000 BTU · Heat Pump Outdoor ×1
Ventilation
Panasonic FV-05VQ5 50 CFM · Exhaust Fan ×6
FV-15VQ5 150 CFM · Exhaust Fan ×3
1 project · most recent 06/10/2026
General Wiring
FiledStatusContractorScope
06/10/2026CompleteRONEY ELECTRIC INCGeneral Wiring
▾Field Inspections (DOB CAP) — 15
DateTypeResultReport
08/24/2026Pass-Final Curb Cut Non-Directive 14PassView ↗
07/28/2026Fail-Final Curb Cut Non-Directive 14FailView ↗
05/11/2026Fail-Final Curb Cut Non-Directive 14FailView ↗
04/27/2026Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
03/25/2026Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
03/23/2026Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
08/01/2025Certified Gas-Gas-Piping-RoughingCertifiedView ↗
08/01/2025Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
08/01/2025Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
07/29/2025Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
02/06/2025Certified Storm Drainage-ST-Piping-RoughingCertifiedView ↗
02/06/2025Certified Storm Drainage-ST-Piping-UndergroundCertifiedView ↗
02/06/2025Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
02/06/2025Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
10/27/2023Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 20
DateRequirementInspectorRole
07/20/2026Heating SystemsPIROOZ SOLTANIZADEHspecial
07/20/2026Mechanical SystemsPIROOZ SOLTANIZADEHspecial
07/20/2026FinalSHAHRIAR QUAYYUMprogress
07/20/2026HVAC insulation and sealing PIROOZ SOLTANIZADEHenergy_progress
07/20/2026HVAC and service water heating equipment PIROOZ SOLTANIZADEHenergy_progress
07/20/2026HVAC and service water heating system controls PIROOZ SOLTANIZADEHenergy_progress
05/19/2026FinalSHAHRIAR QUAYYUMprogress
05/19/2026Heating SystemsPIROOZ SOLTANIZADEHspecial
05/19/2026Mechanical SystemsPIROOZ SOLTANIZADEHspecial
05/19/2026HVAC and service water heating equipment PIROOZ SOLTANIZADEHenergy_progress
05/19/2026HVAC insulation and sealing PIROOZ SOLTANIZADEHenergy_progress
05/19/2026HVAC and service water heating system controls PIROOZ SOLTANIZADEHenergy_progress
05/04/2026HVAC insulation and sealing PIROOZ SOLTANIZADEHenergy_progress
05/04/2026HVAC and service water heating system controls PIROOZ SOLTANIZADEHenergy_progress
05/04/2026Heating SystemsPIROOZ SOLTANIZADEHspecial
05/04/2026Final—progress
05/04/2026HVAC and service water heating equipment PIROOZ SOLTANIZADEHenergy_progress
05/04/2026Mechanical SystemsPIROOZ SOLTANIZADEHspecial
12/08/2020Fire-Resistant Penetrations and JointsPIROOZ SOLTANIZADEHspecial
12/02/2020Sprinkler SystemsPIROOZ SOLTANIZADEHspecial
▾Documents — 110 on file (BIS + DOB NOW)
▸Plans & Drawings9
▸DOB NOWPlans/Sketch - Mechanical Systems4
08/22/2026X00435381-P2Request digital key ↗
08/16/2026X00435381-P2Request digital key ↗
08/16/2026X00435381-I1Request digital key ↗
Showing 3 of 4 on file for this type
▸DOB NOWPlans/Sketch3
08/24/2026X00558256-I1Request digital key ↗
08/20/2026X01094752-P1Request digital key ↗
08/20/2026X01094752-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Sprinkler1
08/15/2026X00435386-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Plumbing1
08/25/2026X00435384-I1Request digital key ↗
▸Applications & Permits24
▸BISPLAN / WORK APPROVAL APPLICATION19
12/18/2025240305665Open ↗
08/08/2024240290993Open ↗
08/06/2024240290993Open ↗
Showing 3 of 19 on file for this type
▸BISWORK PERMIT APPLICATION3
10/24/2023240290993Open ↗
10/24/2023240290993Open ↗
10/24/2023240290993Open ↗
▸BISBPP-5 - Authorization to the Department of Transportation1
10/12/2023240305665Open ↗
▸BISPLAN - WORK & PERMITS - SUPPPORTING DOCUMENTATION1
03/18/2022201129787Open ↗
▸Zoning, Tax Lot & Property Records8
▸BISEASEMENT AND RESTRICTIVE DECLARATIONS - SUPPPORTING DOCUMENTATION2
01/18/2024240290993Open ↗
07/13/2023240290993Open ↗
▸BISTAX LOT: TENTATIVE LOT NUMBER ISSUED2
10/11/2023240305665Open ↗
03/03/2023240290993Open ↗
▸BISZONING EXHIBIT III:DESC. & OWNRSHP.STMNT1
03/03/2023240290993Open ↗
▸BISADDRESS: NEW HOUSE NUMBER APPROVED1
03/16/2023240290993Open ↗
▸BISZONING DIAGRAM1
08/16/2024240290993Open ↗
▸BISZONING EXHIBIT I: CERTIFICATION1
03/03/2023240290993Open ↗
▸Seals & Professional Certifications29
▸DOB NOWProgress Inspector Seal & Signature11
08/27/2026X00435381-P1Open ↗
08/27/2026X00435381-P1Open ↗
08/27/2026X00435381-P1Open ↗
Showing 3 of 11 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature8
08/25/2026X00435386-I1Open ↗
08/25/2026X00435384-I1Open ↗
08/24/2026X00558256-I1Open ↗
Showing 3 of 8 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature7
09/20/2026X00435386-I1Open ↗
08/27/2026X00435381-P1Open ↗
08/27/2026X00435381-P1Open ↗
Showing 3 of 7 on file for this type
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION2
10/23/2023240290993Open ↗
10/23/2023240290993Open ↗
▸BISAPPLICANT OWNER SIGNATURE1
06/23/2021240305665Open ↗
▸Trade Schedules & Equipment2
▸BISDEP STORMWATER SEWER CERTIFICATION (HCP/SCP)1
03/03/2023240290993Open ↗
▸BISDEP SANITARY SEWER CERTIFICATION (HCP/SCP)1
03/03/2023240290993Open ↗
▸Safety & Tenant Protection3
▸BISSTREET TREE CHECKLIST2
10/12/2023240305665Open ↗
03/03/2023240290993Open ↗
▸BISSTREET TREES SITE PLAN1
02/16/2023240305665Open ↗
▸Environmental & Asbestos8
▸DOB NOWOER: Notice to Proceed5
08/16/2026X00435381-I1Open ↗
08/13/2026X00435384-I1Open ↗
08/13/2026X00435381-I1Open ↗
Showing 3 of 5 on file for this type
▸BISENVIRONMENTAL RESTRICTIONS - OER NOTICE TO PROCEED2
10/11/2023240305665Open ↗
03/03/2023240290993Open ↗
▸DOB NOWOER: Notice of Satisfaction1
08/13/2026X00435384-I1Open ↗
▸Energy Compliance3
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS1
10/23/2023240290993Open ↗
▸BISTR8: ENERGY CODE PROGRESS INSPS TECHNICAL REPORT1
03/03/2023240290993Open ↗
▸DOB NOWEN2: As Built Energy Analysis.1
08/25/2026X00435384-I1Open ↗
▸Inspections & Test Reports7
▸BISTECHNICAL REPORT: RESPONSIBILITY2
09/22/2023240290993Open ↗
08/29/2023240290993Open ↗
▸BISTR3: CONCRETE DESIGN MIX TECHNICAL REPORT1
08/29/2023240290993Open ↗
▸BISSOIL REPORT1
03/16/2023240290993Open ↗
▸BISDEMOLITION (DM) JOB SIGNOFF1
08/29/2023240290993Open ↗
▸BISTR2: CONCRETE FIELD TESTING TECHNICAL REPORT1
08/29/2023240290993Open ↗
▸BISSUBSURFACE / SOILS INVESTIGATION (BORINGS/TEST PITS)1
03/03/2023240290993Open ↗
▸Approvals, Objections & Sign-offs6
▸BISSCHEDULE A - OCCUPANCY / USE6
08/08/2024240290993Open ↗
08/06/2024240290993Open ↗
08/05/2024240290993Open ↗
Showing 3 of 6 on file for this type
▸Cost, Insurance & Ownership1
▸BISPROJECT-SPECIFIC GL INSURANCE1
10/23/2023240290993Open ↗
▸Filing & Intake Forms5
▸BISADDITIONAL INFORMATION3
01/22/2024240290993Open ↗
01/22/2024240290993Open ↗
01/18/2024240290993Open ↗
▸BISEFILING JOB APPLICATION COVER SHEET1
06/23/2021240305665Open ↗
▸BISBOROUGH INTAKE FORM1
10/23/2023240290993Open ↗
▸Other Documents5
▸BISBPP - SUPPORTING DOCUMENTATION4
10/11/2023240305665Open ↗
02/16/2023240305665Open ↗
02/16/2023240305665Open ↗
Showing 3 of 4 on file for this type
▸BISSUSTAINABLE ROOF ZONE FORM1
03/16/2023240290993Open ↗