| Owner | Filings | Most Recent |
|---|---|---|
| 714 EAST 2ND ST | 68 | 07/08/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| JRS CONSULTING | 5 | 08/14/2025 |
| LESTER KATZ, NCARB | 7 | 04/02/2025 |
| HY PE STRUCTURAL ENGINEERING | 4 | 10/03/2022 |
| H & O ENGINEERING, DPC | 1 | 07/29/2021 |
| Representative | Filings | Most Recent |
|---|---|---|
| EXPEDITER GROUP | 32 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| BARRY HALPERN CHANY CONST | General Contractor | 28 | 07/08/2026 |
| PIPE SOLUTIONS ADVIS INC | Plumbing | 4 | 07/08/2026 |
| D & F CONSTRUCTION GROUP | General Contractor | 3 | 03/22/2026 |
| FLINT MECHANICAL CORP | Fire Protection | 1 | 07/08/2026 |
| P & D MECHANICAL CORP | Fire Protection | 1 | 07/08/2026 |
| FRIED ELECTRIC CO. | Electrical | 1 | 03/22/2026 |
| DESIGN N SAFETY INC | General Contractor | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| CITY-WIDE TESTING INC | 416 | 14 | 08/14/2025 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Curb Cut | Signed-off | BARRY HALPERN CHANY CONST | 05/21/2025 |
| DOB NOW | Plumbing | Signed-off | BLETSAS P&H CORP | 05/19/2025 |
| DOB NOW | Sprinklers | Signed-off | PIPE SOLUTIONS ADVIS INC | 05/01/2025 |
| DOB NOW | General Construction | Permit Issued | BARRY HALPERN CHANY CONST | 03/17/2025 |
| DOB NOW | Mechanical Systems | Signed-off | BARRY HALPERN CHANY CONST | 03/13/2025 |
| DOB NOW | Structural | Signed-off | BARRY HALPERN CHANY CONST | 03/13/2025 |
| DOB NOW | Construction Fence | Signed-off | BARRY HALPERN CHANY CONST | 04/18/2024 |
| DOB NOW | Mechanical Systems | Signed-off | BARRY HALPERN CHANY CONST | 12/27/2023 |
| DOB NOW | Earth Work | Signed-off | BARRY HALPERN CHANY CONST | 12/07/2023 |
| DOB NOW | Structural | Signed-off | BARRY HALPERN CHANY CONST | 12/06/2023 |
| DOB NOW | Sprinklers | Signed-off | PIPE SOLUTIONS ADVIS INC | 11/22/2023 |
| DOB NOW | Plumbing | Signed-off | P & D MECHANICAL CORP | 11/20/2023 |
| DOB NOW | General Construction | Permit Issued | BARRY HALPERN CHANY CONST | 10/13/2023 |
| DOB NOW | Construction Fence | Signed-off | BARRY HALPERN CHANY CONST | 05/18/2023 |
| DOB NOW | Foundation | Signed-off | BARRY HALPERN CHANY CONST | 01/06/2023 |
| DOB NOW | Structural | Signed-off | BARRY HALPERN CHANY CONST | 01/05/2023 |
| DOB NOW | General Construction | Permit Issued | BARRY HALPERN CHANY CONST | 10/25/2022 |
| DOB NOW | Construction Fence | Signed-off | BARRY HALPERN CHANY CONST | 06/17/2022 |
| DOB NOW | Construction Fence | Signed-off | DESIGN N SAFETY INC | 08/31/2021 |
| BIS | — | ISSUED | DESIGN N SAFETY INC | 10/14/2021 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 08/14/2025 | Signed-off | BARRY HALPERN CHANY CONST | Heating and Air Conditioning Systems, Ventilation Systems | Heat / Cool Mitsubishi Electric MXZ-SM60NAM2 60,000 BTU · Heat Pump Outdoor ×6 MXZ-3C24NA4 24,000 BTU · Vrf Outdoor ×2 MXZ-SM48NAM2 48,000 BTU · Heat Pump Outdoor ×2 Ventilation |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/14/2025 | Signed-off | BLETSAS P&H CORP | Sprinkler System |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/14/2025 | Signed-off | DOUBLE SOLUTIONS INC | Gas, Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/25/2025 | Complete | FRIED ELECTRIC CO. | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/14/2025 | Signed-off | BARRY HALPERN CHANY CONST | Steel, Masonry |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/14/2025 | Signed-off | BARRY HALPERN CHANY CONST | Fence |
| Date | Type | Result | Report |
|---|---|---|---|
| 08/05/2025 | Pass-Final Curb Cut Non-Directive 14 | Pass | View ↗ |
| 07/14/2025 | Fail-Final Curb Cut Non-Directive 14 | Fail | View ↗ |
| 06/20/2025 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 05/29/2025 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 05/22/2025 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 05/20/2025 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 05/15/2025 | Pass-Final PL - Up to 9 Requested Floors | Pass | View ↗ |
| 09/17/2024 | Pass-Final PL - Up to 9 Requested Floors | Pass | View ↗ |
| 04/01/2024 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 10/07/2025 | HVAC-R and service water piping design and insulation | ELIAS RASABI | energy_progress |
| 10/07/2025 | Ventilation and air distribution system | ELIAS RASABI | energy_progress |
| 10/07/2025 | Duct leakage testing, insulation and design | ELIAS RASABI | energy_progress |
| 10/07/2025 | Energy Code Compliance Inspections | ELIAS RASABI | progress |
| 10/07/2025 | Final | ELIAS RASABI | progress |
| 10/07/2025 | Mechanical Systems | ELIAS RASABI | special |
| 10/07/2025 | Fire-Resistant Penetrations and Joints | ELIAS RASABI | special |
| 10/07/2025 | Maintenance information | ELIAS RASABI | energy_progress |
| 10/07/2025 | HVAC-R and service water heating system controls | ELIAS RASABI | energy_progress |
| 10/07/2025 | HVAC-R and service water heating equipment | ELIAS RASABI | energy_progress |
| 08/26/2025 | Maintenance information | ELIAS RASABI | energy_progress |
| 08/26/2025 | HVAC-R and service water heating system controls | ELIAS RASABI | energy_progress |
| 08/26/2025 | HVAC-R and service water piping design and insulation | ELIAS RASABI | energy_progress |
| 08/26/2025 | HVAC-R and service water heating equipment | ELIAS RASABI | energy_progress |
| 08/26/2025 | Energy Code Compliance Inspections | ELIAS RASABI | progress |
| 08/26/2025 | Fire-Resistant Penetrations and Joints | ELIAS RASABI | special |
| 08/26/2025 | Seismic Isolation Systems | ELIAS RASABI | special |
| 08/26/2025 | Sprinkler Systems | ELIAS RASABI | special |
| 08/26/2025 | Post-installed Anchors | ELIAS RASABI | special |
| 08/05/2025 | Fire-Resistant Penetrations and Joints | ELIAS RASABI | special |
| 08/05/2025 | HVAC-R and service water heating equipment | ELIAS RASABI | energy_progress |
| 08/05/2025 | HVAC-R and service water heating system controls | ELIAS RASABI | energy_progress |
| 08/05/2025 | Duct leakage testing, insulation and design | ELIAS RASABI | energy_progress |
| 08/05/2025 | Final | ELIAS RASABI | progress |
| 08/05/2025 | Energy Code Compliance Inspections | ELIAS RASABI | progress |