← Back
Two family brick
716 TAYLOR AVENUE
BRONX · BIN 2022182
💬 Discuss this project
1920Year Built
2Stories
B1Building Class
R6Zoning
2,260 sfGross Floor Area
2Units
3 Open Violations 1 unresolved · 2 paperwork only ▸
Two family brick · 2,500 sf lot · 0.9 FAR built · Flood zone X
Locations of Work
Architecture
Roof2p · 1 filing · 15 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
GREENLINE BLDG CONSULTANTS103/21/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
TOM PETERSEN ARCHITECT, LLC211/07/2025
LESLIE GOOD107/08/2025
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
ACDE GROUP103/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
BERGER QUALITY ELEC'L CONElectrical103/22/2026
VILLAGE ELECTL CONTRS INCElectrical103/22/2026
SOLAR CONTRACTING LLCGeneral Contractor104/09/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
THOMAS PETERSEN ARCHITECT7854211/07/2025
Building Lifecycle
All (15)Filed (3)Permit Issued (1)Signed Off (1)Objection (10)
07/31/2026
Signed off — Alteration
SCOPE OF WORK IS SOLELY FOR THE INSTALLATION OF THE SOLAR ELECTRONICGENERATING SYSTEM. ALL OTHER WORK IS NOT TO BE RELIED UPON AS BEINGAPPROVED AND/OR PERMITTED BY THE NYC DEPARTMENT OF BUILDINGS.*NO CHANGE TO USE, EGRESS OR OCCUPANCY.*
X01032012-I1
01/28/2026
Permit issued — Solar
X01032012-I1-SL
01/12/2026
Objection resolved — Addressed
01/12/2026
Objection resolved — Addressed
01/12/2026
Objection resolved — Addressed
01/02/2026
Objection resolved — Addressed
11/21/2025
Objection raised — Admin
11/21/2025
Objection raised — Admin
11/21/2025
Objection raised — Admin
11/21/2025
Objection raised — Admin
11/07/2025
Filed — Alteration
SCOPE OF WORK IS SOLELY FOR THE INSTALLATION OF THE SOLAR ELECTRONICGENERATING SYSTEM. ALL OTHER WORK IS NOT TO BE RELIED UPON AS BEINGAPPROVED AND/OR PERMITTED BY THE NYC DEPARTMENT OF BUILDINGS.*NO CHANGE TO USE, EGRESS OR OCCUPANCY.*
X01032012-P1
07/08/2025
Filed — Alteration
X01252511-I1
05/10/2024
Objection resolved — Addressed
05/02/2024
Objection raised — Admin
04/22/2024
Filed — Alteration
SCOPE OF WORK IS SOLELY FOR THE INSTALLATION OF THE SOLAR ELECTRONICGENERATING SYSTEM. ALL OTHER WORK IS NOT TO BE RELIED UPON AS BEINGAPPROVED AND/OR PERMITTED BY THE NYC DEPARTMENT OF BUILDINGS.*NO CHANGE TO USE, EGRESS OR OCCUPANCY.*
X01032012-I1
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSolarSigned-offSOLAR CONTRACTING LLC01/28/2026
3 projects · most recent 04/02/2026
FiledStatusContractorScope
04/02/2026CompleteSOLAR ELEC CONTRACTNG LLC3 meters
10/28/2025CompleteVILLAGE ELECTL CONTRS INC—
04/22/2024Permit IssuedBERGER QUALITY ELEC'L CON—
1 project · most recent 11/07/2025
FiledStatusContractorScope
11/07/2025Signed-offSOLAR CONTRACTING LLC42 panels, 18 kw, 326.52 roof_area_sqft
▾Special Inspection Requirements (DOB NOW) — 8
DateRequirementInspectorRole
01/26/2026Air barrier - visual inspectionTOM PETERSENenergy_progress
01/26/2026Fire-Resistant Penetrations and JointsTOM PETERSENspecial
01/26/2026Energy Code Compliance InspectionsTOM PETERSENprogress
01/26/2026FinalTOM PETERSENprogress
10/29/2025Fire-Resistant Penetrations and JointsTOM PETERSENspecial
10/29/2025Energy Code Compliance InspectionsTOM PETERSENprogress
10/29/2025FinalTOM PETERSENprogress
10/29/2025Air barrier - visual inspectionTOM PETERSENenergy_progress
▾Documents — 18 on file (BIS + DOB NOW)
▸Plans & Drawings3
▸DOB NOWPlans/Sketch3
08/19/2026X01252511-I1Request digital key ↗
08/17/2026X01032012-I1Request digital key ↗
08/17/2026X01032012-P1Request digital key ↗
▸Seals & Professional Certifications11
▸DOB NOWProgress Inspector Seal & Signature6
09/01/2026X01032012-I1Open ↗
09/01/2026X01032012-I1Open ↗
09/01/2026X01032012-I1Open ↗
Showing 3 of 6 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature3
08/19/2026X01252511-I1Open ↗
08/17/2026X01032012-I1Open ↗
08/17/2026X01032012-P1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature2
09/01/2026X01032012-I1Open ↗
08/27/2026X01032012-P1Open ↗
▸Environmental & Asbestos3
▸DOB NOWDEP ACP-5: Asbestos Assessment Report3
08/19/2026X01252511-I1Open ↗
08/17/2026X01032012-P1Open ↗
08/17/2026X01032012-I1Open ↗
▸Approvals, Objections & Sign-offs1
▸DOB NOWUtility Company Final Acceptance Letter1
08/17/2026X01032012-I1Open ↗