Over six families without stores
717 58 STREET
BROOKLYN · BIN 3015913
💬 Discuss this project
1928Year Built
4Stories
C1Building Class
R6BZoning
11,360 sfGross Floor Area
16Units
Rent Stabilized16 Open Violations ▸FDNY Report ↗
Over six families without stores · 4,007 sf lot · 2.84 FAR built · Flood zone X
Locations of Work
ArchitectureElectricalPlumbing
Permit Issued — active, not yet Signed-off
Floor 12p · 1 filing · 6 docs
CellarUnder Construction5p · 2 filings · 19 docs
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
11/12/2025$2.9M—Private party → OUR BK HOME LLC$255/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
FLUSHING ENGINEERING SERVICE PC405/22/2026
MICHAEL MUROFF ARCHITECT LLC206/16/2022
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
M2 DESIGN403/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
K & BH PLUMBING & HTG INCPlumbing406/27/2026
AMERICAN FIRE RESTORATIONGeneral Contractor207/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
FLUSHING ENGINEERING SERV4373405/22/2026
METRIC CONSULTING AND INS1803206/16/2022
Building Lifecycle
All (94)Filed (6)Permit Issued (6)Signed Off (5)Violation (60)Inspection (2)Objection (8)Special Inspection (7)
08/26/2026
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
07/06/2026
Signed off — Alteration
install 16 gas boilers in the cellar existing boiler room. no change in use, occupancy or egress. existing co #B55519
B01338164-I1
07/06/2026
Signed off — Alteration
install 16 gas boilers in the cellar existing boiler room. no change in use, occupancy or egress. existing co #B55519
B01338164-S1
07/06/2026
Signed off — Alteration
install 16 gas boilers in the cellar existing boiler room. no change in use, occupancy or egress. existing co #B55519
B01338164-S2
06/24/2026
Inspection — Pass-Final Boiler Equipment Inspection
Pass
View inspection ↗
06/22/2026
Permit issued — Boiler Equipment
B01338164-S1-BE
06/22/2026
Permit issued — Boiler Equipment
B01338164-S2-BE
05/22/2026
Filed — Alteration
install 16 gas boilers in the cellar existing boiler room. no change in use, occupancy or egress. existing co #B55519
B01338164-S1
05/22/2026
Filed — Alteration
install 16 gas boilers in the cellar existing boiler room. no change in use, occupancy or egress. existing co #B55519
B01338164-S2
05/22/2026
Special inspection requirement — Tenant Protection Plan Compliance
KY FU
05/22/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
KY FU
03/24/2026
Permit issued — Plumbing
B01338163-I1-PL
03/24/2026
Permit issued — Boiler Equipment
B01338164-I1-BE
03/03/2026
Objection resolved — Addressed
02/07/2026
Objection resolved — Addressed
02/07/2026
Objection resolved — Addressed
02/07/2026
Objection resolved — Addressed
02/02/2026
Objection raised — Plumbing
02/02/2026
Objection raised — Cost
02/02/2026
Objection raised — Admin
02/02/2026
Objection raised — Plumbing
01/16/2026
Filed — Alteration
install 16 gas boilers in the cellar existing boiler room. no change in use, occupancy or egress. existing co #B55519
B01338164-I1
01/16/2026
Filed — Alteration
B01338163-I1
01/16/2026
Special inspection requirement — HVAC-R and service water piping design and insulation
KY FU
01/16/2026
Special inspection requirement — HVAC-R and service water heating system controls
KY FU
01/16/2026
Special inspection requirement — HVAC-R and service water heating equipment
KY FU
01/16/2026
Special inspection requirement — Tenant Protection Plan Compliance
KY FU
12/20/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
KY FU
11/14/2025
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
10/29/2025
Violation issued (HPD, closed)
C
06/06/2025
Violation issued (HPD, closed)
A
09/23/2024
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
04/08/2024
Violation issued (HPD, closed)
A
11/02/2023
Signed off — Alteration
B00722621-I1
11/02/2023
Signed off — Alteration
B00722621-S1
03/20/2023
Violation issued (HPD, closed)
A
01/23/2023
Violation issued (ECB, closed)
Construction
08/05/2022
Violation issued (HPD, closed)
B
07/26/2022
Permit issued — General Construction
B00722621-S1-GC
06/16/2022
Filed — Alteration
B00722621-S1
05/10/2022
Permit issued — Structural
B00722621-I1-ST
04/28/2022
Violation issued (HPD, closed)
A
04/28/2022
Violation issued (HPD, open)
A
04/28/2022
Violation issued (HPD, open)
A
04/28/2022
Violation issued (HPD, open)
A
04/27/2022
Filed — Alteration
B00722621-I1
04/04/2022
Violation issued (HPD, closed)
A
04/04/2022
Violation issued (HPD, closed)
C
04/04/2022
Violation issued (HPD, closed)
B
04/04/2022
Violation issued (HPD, closed)
C
04/04/2022
Violation issued (HPD, closed)
C
03/24/2022
Violation issued (HPD, closed)
I
03/24/2022
Violation issued (HPD, closed)
I
03/24/2022
Violation issued (HPD, closed)
I
03/24/2022
Violation issued (HPD, closed)
I
03/24/2022
Violation issued (HPD, closed)
I
03/24/2022
Violation issued (HPD, closed)
I
03/22/2022
Violation issued (HPD, open)
C
03/17/2022
Violation issued (HPD, closed)
C
03/17/2022
Violation issued (HPD, closed)
C
Latest 60 of 94 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWBoiler EquipmentSigned-offK & BH PLUMBING & HTG INC06/22/2026
DOB NOWBoiler EquipmentSigned-offK & BH PLUMBING & HTG INC06/22/2026
DOB NOWPlumbingPermit IssuedK & BH PLUMBING & HTG INC03/24/2026
DOB NOWBoiler EquipmentSigned-offK & BH PLUMBING & HTG INC03/24/2026
DOB NOWGeneral ConstructionSigned-offAMERICAN FIRE RESTORATION07/26/2022
DOB NOWStructuralSigned-offAMERICAN FIRE RESTORATION05/10/2022
BISBLISSUEDMICHAEL S. KAPLAN03/26/2014
2 projects · most recent 08/18/2025
General Wiring
FiledStatusContractorScope
08/18/2025CompleteJ Y ELECTRIC INCGeneral Wiring
01/09/2023CompleteELECTL CONTG SOLUTIONS COGeneral Wiring
▾Field Inspections (DOB CAP) — 2
DateTypeResultReport
08/26/2026Pass-Final PL - Up to 3 Requested FloorsPassView ↗
06/24/2026Pass-Final Boiler Equipment InspectionPassView ↗
▾Special Inspection Requirements (DOB NOW) — 7
DateRequirementInspectorRole
05/22/2026Tenant Protection Plan ComplianceKY FUspecial
05/22/2026Fire-Resistant Penetrations and JointsKY FUspecial
01/16/2026HVAC-R and service water piping design and insulationKY FUenergy_progress
01/16/2026HVAC-R and service water heating system controlsKY FUenergy_progress
01/16/2026HVAC-R and service water heating equipmentKY FUenergy_progress
01/16/2026Tenant Protection Plan ComplianceKY FUspecial
12/20/2025Fire-Resistant Penetrations and JointsKY FUspecial
▾Documents — 38 on file (BIS + DOB NOW)
▸Plans & Drawings6
▸DOB NOWPlans/Sketch6
08/29/2026B00722621-S1Request digital key ↗
08/29/2026B00722621-I1Request digital key ↗
08/18/2026B01338163-I1Request digital key ↗
Showing 3 of 6 on file for this type
▸Applications & Permits3
▸BISWORK PERMIT APPLICATION2
06/19/2014320977387Open ↗
06/19/2014320977387Open ↗
▸BISPLAN / WORK APPROVAL APPLICATION1
06/19/2014320977387Open ↗
▸Seals & Professional Certifications16
▸DOB NOWDPL-1: Design Professional Seal & Signature6
08/29/2026B00722621-S1Open ↗
08/29/2026B00722621-I1Open ↗
08/18/2026B01338163-I1Open ↗
Showing 3 of 6 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature4
08/29/2026B01338164-S2Open ↗
08/29/2026B01338164-S2Open ↗
08/26/2026B01338164-I1Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWProgress Inspector Seal & Signature3
08/26/2026B01338164-I1Open ↗
08/26/2026B01338164-I1Open ↗
08/26/2026B01338164-I1Open ↗
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION2
06/19/2014320977387Open ↗
06/19/2014320977387Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT1
06/19/2014320977387Open ↗
▸Trade Schedules & Equipment1
▸BISSCHEDULE C - HEATING & COMBUSTION EQUIPMENT1
06/19/2014320977387Open ↗
▸Environmental & Asbestos6
▸DOB NOWDEP ACP-5: Asbestos Assessment Report4
08/18/2026B01338163-I1Open ↗
08/16/2026B01338164-I1Open ↗
08/16/2026B01338164-S1Open ↗
Showing 3 of 4 on file for this type
▸BISASBESTOS: CERTIFICATION (DEP ACP5)1
06/19/2014320977387Open ↗
▸DOB NOWDEP ACP-20/ACP-21: Asbestos Project Conditional Completion Form/Asbestos Project Completion Form1
08/29/2026B00722621-S1Open ↗
▸Energy Compliance3
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS2
06/19/2014320977387Open ↗
06/19/2014320977387Open ↗
▸DOB NOWEN2: As Built Energy Analysis1
08/13/2026B00722621-S1Open ↗
▸Approvals, Objections & Sign-offs2
▸BISADMINISTRATIVE OBJECTIONS1
06/19/2014320977387Open ↗
▸BISCERTIFICATE OF OCCUPANCY - LOC: REQUEST1
09/16/2014320977387Open ↗
▸Filing & Intake Forms1
▸BISEFILING COVER SHEET1
06/19/2014320977387Open ↗