| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/10/2025 | Signed-off | DOUG'S PLBG & HTG SERV CO | Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/08/2025 | Complete | DENNISON ELECTRIC CORP | General Wiring |
| 04/29/2024 | Complete | LIT MODE ELECL CONTG INC | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/10/2025 | Signed-off | DOUG'S PLBG & HTG SERV CO | Steel, Masonry |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/10/2025 | Signed-off | DOUG'S PLBG & HTG SERV CO | Earthwork |
| Owner | Filings | Most Recent |
|---|---|---|
| NEW LINE CONSTRUCTION | 40 | 07/08/2026 |
| 717 BARTHOLDI LLC | 3 | 03/22/2026 |
| N B A CONSTRUCTION | 1 | 03/22/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 06/15/2022 | $750K | — | — → — | — not available |
| Firm | Filings | Most Recent |
|---|---|---|
| NODE ARCHITECTURE,ENGINEERING, CONS | 13 | 06/10/2025 |
| GREENLITE CONSULTING CORP | 3 | 02/13/2024 |
| Representative | Filings | Most Recent |
|---|---|---|
| NODE ENGINEERING CONSULTING | 22 | 03/21/2026 |
| NODE ARCHITECTURE,ENGINEERING,CON | 4 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| NEW LINE CONSTRUCTION LLC | General Contractor | 22 | 07/08/2026 |
| N.B.A CONSTRUCTION INC | General Contractor | 3 | 03/21/2026 |
| DENNISON ELECTRIC CORP | Electrical | 2 | 03/22/2026 |
| LLOYD G DRUMMOND PLBG&GEN | Fire Protection | 1 | 07/08/2026 |
| DOUG'S PLBG & HTG SERV CO | Fire Protection | 1 | 07/08/2026 |
| LIT MODE ELECL CONTG INC | Electrical | 1 | 03/22/2026 |
| DOUG'S PLBG & HTG SERV CO | Plumbing | 1 | 07/08/2026 |
| LLOYD G DRUMMOND PLBG&GEN | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| NEW LINE CONSTRUCTION | 7226 | 8 | 06/10/2025 |
| INTERNATIONAL GEOTEHCNICA | 1795 | 1 | 12/22/2023 |
| NODE ARCHITECTURE,ENGINEE | 6799 | 1 | 12/22/2023 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Signed-off | DOUG'S PLBG & HTG SERV CO | 05/12/2025 |
| DOB NOW | Sprinklers | Signed-off | DOUG'S PLBG & HTG SERV CO | 05/12/2025 |
| DOB NOW | General Construction | Permit Issued | NEW LINE CONSTRUCTION LLC | 11/01/2024 |
| DOB NOW | Construction Fence | Signed-off | NEW LINE CONSTRUCTION LLC | 10/31/2024 |
| DOB NOW | Curb Cut | Signed-off | NEW LINE CONSTRUCTION LLC | 10/23/2024 |
| DOB NOW | General Construction | Permit Issued | NEW LINE CONSTRUCTION LLC | 07/24/2024 |
| DOB NOW | Plumbing | Signed-off | LLOYD G DRUMMOND PLBG&GEN | 01/03/2024 |
| DOB NOW | Sprinklers | Signed-off | LLOYD G. DRUMMOND | 01/03/2024 |
| DOB NOW | General Construction | Permit Issued | NEW LINE CONSTRUCTION LLC | 12/29/2023 |
| DOB NOW | Sidewalk Shed | Signed-off | N.B.A CONSTRUCTION INC | 11/14/2023 |
| DOB NOW | Earth Work | Signed-off | NEW LINE CONSTRUCTION LLC | 11/13/2023 |
| DOB NOW | Structural | Signed-off | NEW LINE CONSTRUCTION LLC | 11/13/2023 |
| DOB NOW | Construction Fence | Signed-off | NEW LINE CONSTRUCTION LLC | 11/13/2023 |
| DOB NOW | General Construction | Permit Issued | NEW LINE CONSTRUCTION LLC | 11/13/2023 |
| DOB NOW | Mechanical Systems | Signed-off | NEW LINE CONSTRUCTION LLC | 11/13/2023 |
| DOB NOW | General Construction | Permit Issued | NEW LINE CONSTRUCTION LLC | 09/26/2023 |
| DOB NOW | Structural | Signed-off | NEW LINE CONSTRUCTION LLC | 08/31/2023 |
| DOB NOW | Construction Fence | Signed-off | NEW LINE CONSTRUCTION LLC | 07/25/2023 |
| DOB NOW | Foundation | Signed-off | NEW LINE CONSTRUCTION LLC | 06/19/2023 |
| DOB NOW | Mechanical Systems | Signed-off | NEW LINE CONSTRUCTION LLC | 02/09/2023 |
| DOB NOW | Construction Fence | Signed-off | NEW LINE CONSTRUCTION LLC | 08/22/2022 |
| Date | Type | Result | Report |
|---|---|---|---|
| 07/03/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 06/06/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 05/22/2025 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 05/19/2025 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 02/12/2025 | Pass-Final Curb Cut Non-Directive 14 | Pass | View ↗ |
| 01/03/2025 | Fail-Final Curb Cut Non-Directive 14 | Fail | View ↗ |
| 03/15/2024 | Certified Storm Drainage-ST-Piping-Roughing | Certified | View ↗ |
| 03/15/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 07/07/2025 | Fire-Resistance Rated Construction | AUGUSTINE OKUNDAYE | progress |
| 07/07/2025 | Interior lighting power | AUGUSTINE OKUNDAYE | energy_progress |
| 07/07/2025 | Fenestration air leakage | AUGUSTINE OKUNDAYE | energy_progress |
| 07/07/2025 | Fenestration areas | AUGUSTINE OKUNDAYE | energy_progress |
| 07/07/2025 | Air barrier - visual inspection | AUGUSTINE OKUNDAYE | energy_progress |
| 07/07/2025 | Protection of exposed foundation insulation | AUGUSTINE OKUNDAYE | energy_progress |
| 07/07/2025 | Lighting controls | AUGUSTINE OKUNDAYE | energy_progress |
| 07/07/2025 | Insulation placement and R values | AUGUSTINE OKUNDAYE | energy_progress |
| 07/07/2025 | Metering | AUGUSTINE OKUNDAYE | energy_progress |
| 07/07/2025 | Exterior lighting power | AUGUSTINE OKUNDAYE | energy_progress |
| 07/07/2025 | Maintenance information | AUGUSTINE OKUNDAYE | energy_progress |
| 07/07/2025 | Fenestration and door U-factor and product ratings | AUGUSTINE OKUNDAYE | energy_progress |
| 07/07/2025 | Lighting in dwelling units | AUGUSTINE OKUNDAYE | energy_progress |
| 07/07/2025 | Fire-Resistant Penetrations and Joints | AUGUSTINE OKUNDAYE | special |
| 07/07/2025 | Energy Code Compliance Inspections | AUGUSTINE OKUNDAYE | progress |
| 01/30/2025 | Insulation placement and R values | AUGUSTINE OKUNDAYE | energy_progress |
| 01/30/2025 | Air barrier - visual inspection | AUGUSTINE OKUNDAYE | energy_progress |
| 01/30/2025 | Lighting controls | AUGUSTINE OKUNDAYE | energy_progress |
| 01/30/2025 | Interior lighting power | AUGUSTINE OKUNDAYE | energy_progress |
| 01/30/2025 | Fenestration air leakage | AUGUSTINE OKUNDAYE | energy_progress |
| 01/30/2025 | Lighting in dwelling units | AUGUSTINE OKUNDAYE | energy_progress |
| 01/30/2025 | Fenestration and door U-factor and product ratings | AUGUSTINE OKUNDAYE | energy_progress |
| 01/30/2025 | Maintenance information | AUGUSTINE OKUNDAYE | energy_progress |
| 01/30/2025 | Metering | AUGUSTINE OKUNDAYE | energy_progress |
| 01/30/2025 | Fenestration areas | AUGUSTINE OKUNDAYE | energy_progress |