← Back
Parochial school, yeshiva
Monsignor Mcclancy Memorial Hs
72-02 31 AVENUE · BIN 4437073
💬 Discuss this project
1954Year Built
3Stories
W2Building Class
R4Zoning
58,725 sfGross Floor Area
1Units
LL97 Covered25 Open Violations ▸FDNY Report ↗
Parochial school, yeshiva · 225,400 sf lot · 0.26 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralElectricalMechanicalPlumbing
Permit Issued — active, not yet Signed-off
RoofUnder Construction12p · 4 filings · 20 docs
Floor 32p · 1 filing · 13 docs
Floor 22p · 1 filing · 13 docs
Floor 1Under Construction44p · 3 filings · 20 docs
Basement2p · 1 filing · 4 docs
Sub-BasementUnder Construction6p · 1 filing · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
HKS CONSTRUCTION303/21/2026
CALAKAR CONSTRUCTION103/21/2026
▾Design Consultants (Architect / Engineer of Record)
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
YOUN DESIGN CORP203/21/2026
CITY WIDE EXPEDITING203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
THE LANDTEK GROUP INCGeneral Contractor1203/21/2026
IMPACT BUILDERS CORPGeneral Contractor707/08/2026
LUIGI CALIENDO & SONS,INCGeneral Contractor608/26/2026
NYS ESSENTIAL POWER INCGeneral Contractor303/21/2026
JERRY SARABELLAElectrical103/21/2026
JOSEPH CAMPISIElectrical103/21/2026
MEZZACAPPA, CHRISTIANElectrical103/21/2026
NOPE DESIGN & REN. LLCElectrical103/21/2026
RAPPO, FRANKElectrical103/21/2026
TORRES IVANElectrical103/21/2026
NATIONAL COOLING SERVICESGeneral Contractor107/08/2026
TRI CITY MECHANICAL GROUP CORPPlumbing109/24/2026
BRICKLAYERS AND ALLI COMPElectrical103/21/2026
NEPTUNE SIGNS AWNINGSScaffold107/08/2026
CEESAY, BELALElectrical103/21/2026
HAMMERL, JOSEFElectrical103/21/2026
JERRY G. SARABELLAElectrical103/21/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
DOYUN KIM; RA7415607/15/2026
HRF SERVICES CORP5616406/25/2026
P GEORGOPOULOS ARCHITECT889310/29/2025
THOMAS PETERSEN ARCHITECT7854107/09/2024
SOIL MECHANICS DRILLING C2325108/16/2021
Building Lifecycle
All (131)Filed (22)Permit Issued (17)Signed Off (5)Violation (36)Inspection (1)Objection (20)Special Inspection (30)
09/23/2026
Permit issued — Plumbing
Q00558742-S4-PL
08/25/2026
Permit issued — Earth Work
Q00558742-S1-FO-EA
08/25/2026
Permit issued — Support of Excavation
Q00558742-S5-SE
08/20/2026
Permit issued — General Construction
Q00558742-I1-GC
08/20/2026
Permit issued — Structural
Q00558742-S2-ST
08/20/2026
Permit issued — Mechanical Systems
Q00558742-S3-MS
07/15/2026
Filed — Alteration CO
FOUNDATION DESIGN TO FACILITATE CONSTRUCTON OF FITNESS CENTER AS EXTENSION IN EXISTING BUILDING
Q00558742-P5
07/15/2026
Special inspection requirement — Exterior lighting power
DOYUN KIM
07/15/2026
Special inspection requirement — Fenestration air leakage
DOYUN KIM
07/15/2026
Special inspection requirement — Lighting controls
DOYUN KIM
07/15/2026
Special inspection requirement — Structural Stability – Alterations of existing buildings
DOYUN KIM
07/15/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
DOYUN KIM
07/15/2026
Special inspection requirement — Interior lighting power
DOYUN KIM
07/15/2026
Special inspection requirement — Air barrier - visual inspection
DOYUN KIM
06/30/2026
Objection resolved — Addressed
06/29/2026
Special inspection requirement — Excavations - Sheeting, Shoring, and Bracing
SHAHRIAR QUAYYUM
06/29/2026
Special inspection requirement — Subsurface Investigations (Borings/Test Pits)
SHAHRIAR QUAYYUM
06/27/2026
Objection raised — Other
06/25/2026
Filed — Alteration CO
FOUNDATION DESIGN TO FACILITATE CONSTRUCTON OF FITNESS CENTER AS EXTENSION IN EXISTING BUILDING
Q00558742-S5
06/15/2026
Permit issued — Construction Fence
Q01413831-I1-FN
06/09/2026
Filed — Alteration
Herewith filed for an 8 ft plywood construction fence
Q01413831-I1
01/16/2026
Violation issued (FDNY_ORDER, closed)
10/29/2025
Filed — Alteration CO
FOUNDATION DESIGN TO FACILITATE CONSTRUCTON OF FITNESS CENTER AS EXTENSION IN EXISTING BUILDING
Q00558742-S4
10/29/2025
Filed — Alteration CO
FOUNDATION DESIGN TO FACILITATE CONSTRUCTON OF FITNESS CENTER AS EXTENSION IN EXISTING BUILDING
Q00558742-S3
10/24/2025
Special inspection requirement — Shutoff dampers
Vasilios Georgopoulos
10/24/2025
Special inspection requirement — HVAC-R and service water heating system controls
Vasilios Georgopoulos
10/24/2025
Special inspection requirement — HVAC-R and service water piping design and insulation
Vasilios Georgopoulos
10/24/2025
Special inspection requirement — Maintenance information
Vasilios Georgopoulos
10/24/2025
Special inspection requirement — Energy Code Compliance Inspections
Vasilios Georgopoulos
10/24/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
Vasilios Georgopoulos
10/24/2025
Special inspection requirement — HVAC-R and service water piping design and insulation
Vasilios Georgopoulos
10/24/2025
Special inspection requirement — HVAC-R and service water heating equipment
Vasilios Georgopoulos
10/07/2025
Special inspection requirement — Final
SHAHRIAR QUAYYUM
10/07/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
SHAHRIAR QUAYYUM
10/07/2025
Special inspection requirement — Subgrade Inspections
SHAHRIAR QUAYYUM
10/07/2025
Special inspection requirement — Designated Seismic System
SHAHRIAR QUAYYUM
10/07/2025
Special inspection requirement — Subsurface Investigations (Borings/Test Pits)
SHAHRIAR QUAYYUM
10/07/2025
Special inspection requirement — Footing and Foundation
SHAHRIAR QUAYYUM
10/07/2025
Special inspection requirement — Concrete - Cast-In-Place
SHAHRIAR QUAYYUM
09/25/2025
Special inspection requirement — Designated Seismic System
SHAHRIAR QUAYYUM
09/25/2025
Special inspection requirement — Masonry
SHAHRIAR QUAYYUM
09/25/2025
Special inspection requirement — Structural Steel - High Strength Bolting
SHAHRIAR QUAYYUM
09/25/2025
Special inspection requirement — Final
SHAHRIAR QUAYYUM
09/25/2025
Special inspection requirement — Structural Steel - Details
SHAHRIAR QUAYYUM
09/25/2025
Special inspection requirement — Structural Steel - Welding
SHAHRIAR QUAYYUM
09/24/2025
Objection resolved — Addressed
09/16/2025
Objection resolved — Addressed
09/12/2025
Objection raised — Admin
09/09/2025
Objection raised — Scope
09/05/2025
Filed — Alteration CO
FOUNDATION DESIGN TO FACILITATE CONSTRUCTON OF FITNESS CENTER AS EXTENSION IN EXISTING BUILDING
Q00558742-P4
09/05/2025
Filed — Alteration CO
FOUNDATION DESIGN TO FACILITATE CONSTRUCTON OF FITNESS CENTER AS EXTENSION IN EXISTING BUILDING
Q00558742-P3
08/25/2025
Signed off — Alteration
Installation of PV System on existing rooftop. No changes to Egress or use of occupancy.
Q01075443-I1
08/12/2025
Filed — Alteration CO
FOUNDATION DESIGN TO FACILITATE CONSTRUCTON OF FITNESS CENTER AS EXTENSION IN EXISTING BUILDING
Q00558742-P2
06/25/2025
Objection resolved — Addressed
06/25/2025
Objection resolved — Addressed
06/24/2025
Signed off — Alteration
Install new VRF system for existing school. There is no change of use, egress or occupancy filed under this application.
Q01065006-I1
06/15/2025
Objection resolved — Addressed
06/10/2025
Objection raised — Admin
06/10/2025
Objection raised — Inspections
06/10/2025
Objection raised — Structural
Latest 60 of 131 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWPlumbingPermit IssuedTRI CITY MECHANICAL GROUP CORP09/23/2026
DOB NOWEarth WorkPermit IssuedLUIGI CALIENDO & SONS,INC08/25/2026
DOB NOWSupport of ExcavationPermit IssuedLUIGI CALIENDO & SONS,INC08/25/2026
DOB NOWGeneral ConstructionPermit IssuedLUIGI CALIENDO & SONS,INC08/20/2026
DOB NOWStructuralPermit IssuedLUIGI CALIENDO & SONS,INC08/20/2026
DOB NOWMechanical SystemsPermit IssuedLUIGI CALIENDO & SONS,INC08/20/2026
DOB NOWConstruction FencePermit IssuedLUIGI CALIENDO & SONS,INC06/15/2026
DOB NOWMechanical SystemsSigned-offNATIONAL COOLING SERVICES08/23/2024
DOB NOWSolarSigned-offNYS ESSENTIAL POWER INC07/15/2024
DOB NOWSignSigned-offNEPTUNE SIGNS&AWNINGS INC03/06/2023
DOB NOWEarth WorkPermit IssuedTHE LANDTEK GROUP INC01/08/2022
DOB NOWEarth WorkPermit IssuedTHE LANDTEK GROUP INC01/07/2022
DOB NOWConstruction FenceSigned-offIMPACT BUILDERS CORP09/24/2021
DOB NOWGeneral ConstructionPermit IssuedTHE LANDTEK GROUP INC09/21/2021
DOB NOWEarth WorkPermit IssuedTHE LANDTEK GROUP INC09/21/2021
DOB NOWFoundationPermit IssuedIMPACT BUILDERS CORP09/10/2021
DOB NOWStructuralSigned-offIMPACT BUILDERS CORP08/24/2021
BISEQISSUEDHKS CONSTRUCTION CORP07/31/2015
BISPLISSUEDMMI PLUMBING & HEATING INC.08/23/2013
BIS—ISSUEDFOREMOST CONTRACTING & BU04/02/2013
BISPLISSUEDMMI PLUMBING & HEATING INC.01/10/2013
BISSPISSUEDFIREQUEST CORP01/10/2013
BISPLISSUEDMMI PLUMBING & HEATING INC.01/03/2013
BISPLISSUEDPLBG P & H INC08/28/2012
BISOTISSUEDEAST COAST BUILDERS & AS*08/17/2012
BISPLISSUEDMMI PLUMBING & HEATING INC.07/30/2012
BIS—ISSUEDFOREMOST CONTRACTING & BU04/02/2012
BIS—ISSUEDFOREMOST CONTRACTING & BU03/30/2012
BIS—ISSUEDFOREMOST CONTRACTING & BU03/27/2012
BISEQISSUEDFOREMOST CONTRACTING & BU03/27/2012
BISEQISSUEDEASY CONTRACTING LLC02/03/2012
BISSPISSUEDFIREQUEST CORP01/10/2012
BISPLISSUEDMMI PLUMBING & HEATING INC.01/10/2012
BISPLISSUEDMMI PLUMBING & HEATING INC.11/09/2011
BIS—ISSUEDFOREMOST CONTRACTING LLC11/04/2011
BIS—ISSUEDFOREMOST CONTRACTING LLC11/03/2011
BISEQISSUEDFOREMOST CONTRACTING LLC10/28/2011
BISPLISSUEDMMI PLUMBING & HEATING INC.08/29/2011
BISMHISSUEDEAST COAST BUILDERS & AS*08/25/2011
BISOTISSUEDEAST COAST BUILDERS & AS*08/25/2011
+ 14 more permits on file
3 projects · most recent 09/30/2024
General Wiring Lighting
FiledStatusContractorScope
09/30/2024CompleteJD ELECTRICAL ENTERPRISES—
11/03/2022CompleteJONG HYUN KIM—
06/19/2018CompleteJAVELIN ELECTRIC INCGeneral Wiring, Lighting
3 projects · most recent 07/15/2026
Steel Concrete Masonry
FiledStatusContractorScope
07/15/2026Permit IssuedFLAVIO MECHANICAL CORPSteel, Concrete, Masonry
08/18/2021Permit IssuedIMPACT BUILDERS CORP1 scope_items
08/16/2021Permit IssuedTHE LANDTEK GROUP INC1 scope_items
1 project · most recent 06/09/2026
Fence
FiledStatusContractorScope
06/09/2026Permit IssuedLUIGI CALIENDO & SONS,INCFence
1 project · most recent 08/16/2021
Earthwork
FiledStatusContractorScope
08/16/2021Permit IssuedTHE LANDTEK GROUP INCEarthwork
▾Field Inspections (DOB CAP) — 1
DateTypeResultReport
03/13/2023Pass-Final Sign Permit InspectionPassView ↗
▾Special Inspection Requirements (DOB NOW) — 74
DateRequirementInspectorRole
07/15/2026Air barrier - visual inspectionDOYUN KIMenergy_progress
07/15/2026Lighting controlsDOYUN KIMenergy_progress
07/15/2026Interior lighting powerDOYUN KIMenergy_progress
07/15/2026Fire-Resistant Penetrations and JointsDOYUN KIMspecial
07/15/2026Structural Stability – Alterations of existing buildingsDOYUN KIMspecial
07/15/2026Exterior lighting powerDOYUN KIMenergy_progress
07/15/2026Fenestration air leakageDOYUN KIMenergy_progress
06/29/2026Excavations - Sheeting, Shoring, and BracingSHAHRIAR QUAYYUMspecial
06/29/2026Subsurface Investigations (Borings/Test Pits)SHAHRIAR QUAYYUMspecial
10/24/2025HVAC-R and service water piping design and insulationVasilios Georgopoulosenergy_progress
10/24/2025HVAC-R and service water piping design and insulationVasilios Georgopoulosenergy_progress
10/24/2025Fire-Resistant Penetrations and JointsVasilios Georgopoulosspecial
10/24/2025Shutoff dampersVasilios Georgopoulosenergy_progress
10/24/2025Energy Code Compliance InspectionsVasilios Georgopoulosprogress
10/24/2025HVAC-R and service water heating system controlsVasilios Georgopoulosenergy_progress
10/24/2025Maintenance informationVasilios Georgopoulosenergy_progress
10/24/2025HVAC-R and service water heating equipmentVasilios Georgopoulosenergy_progress
10/07/2025Structural Stability – Alterations of existing buildingsSHAHRIAR QUAYYUMspecial
10/07/2025Designated Seismic SystemSHAHRIAR QUAYYUMspecial
10/07/2025Footing and FoundationSHAHRIAR QUAYYUMprogress
10/07/2025FinalSHAHRIAR QUAYYUMprogress
10/07/2025Subgrade InspectionsSHAHRIAR QUAYYUMspecial
10/07/2025Subsurface Investigations (Borings/Test Pits)SHAHRIAR QUAYYUMspecial
10/07/2025Concrete - Cast-In-PlaceSHAHRIAR QUAYYUMspecial
09/25/2025MasonrySHAHRIAR QUAYYUMspecial
Latest 25 of 74.
▾Tenants in the building
TenantSpaceFloorsRenovation projects
Mcclancey Memorial High SchoolEducation—
Project Q01075443 Alteration · LOC Issued · 07/09/2024
Monsingor McClancy SchoolEducationGround
Project Q00564062 Alteration · Permit Entire · 08/18/2021
Monsignor McClancy Memorial High SchoolEducation—
Project Q00574134 Alteration · Permit Entire · 08/16/2021
Read from each project’s drawing title blocks and cover sheets and checked twice; a name appears only when it is the occupant, never the owner, landlord or designer.
▾Documents — 329 on file (BIS + DOB NOW)
▸Plans & Drawings22
▸DOB NOWPlans/Sketch22
08/27/2026Q00564061-I1Request digital key ↗
08/27/2026Q00574134-I1Request digital key ↗
08/27/2026Q00564062-I1Request digital key ↗
Showing 3 of 22 on file for this type
▸Applications & Permits46
▸BISPLAN / WORK APPROVAL APPLICATION27
01/31/2024420350756Open ↗
01/15/2019420350756Open ↗
09/01/2015421188324Open ↗
Showing 3 of 27 on file for this type
▸BISWORK PERMIT APPLICATION18
07/30/2015440239760Open ↗
04/08/2013420349867Open ↗
09/06/2012420593940Open ↗
Showing 3 of 18 on file for this type
▸BISCERTIFICATE OF OCCUPANCY: APPLICATION1
01/06/2014420349867Open ↗
▸Zoning, Tax Lot & Property Records7
▸DOB NOWZD1: DOB Zoning Diagram4
08/18/2026Q00558742-P5Open ↗
08/13/2026Q00558742-I1Open ↗
08/13/2026Q00558742-P1Open ↗
Showing 3 of 4 on file for this type
▸BISZONING DIAGRAM1
07/02/2011420349867Open ↗
▸BISTAX LOT- TENTATIVE LOT NUMBER ISSUED1
08/31/2011420349867Open ↗
▸DOB NOWHouse Number Verification: TOPO Stamp1
08/13/2026Q00558742-I1Open ↗
▸Seals & Professional Certifications81
▸DOB NOWDPL-1: Design Professional Seal & Signature22
08/27/2026Q00592517-I1Open ↗
08/25/2026Q00825588-I1Open ↗
08/20/2026Q01168669-I1Open ↗
Showing 3 of 22 on file for this type
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION18
07/29/2015421188324Open ↗
04/29/2014420349867Open ↗
04/08/2014420349867Open ↗
Showing 3 of 18 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature16
09/02/2026Q00558742-S1Open ↗
09/02/2026Q00558742-S1Open ↗
09/01/2026Q00564062-I1Open ↗
Showing 3 of 16 on file for this type
▸DOB NOWProgress Inspector Seal & Signature15
09/02/2026Q00558742-S1Open ↗
09/01/2026Q00564062-I1Open ↗
08/31/2026Q00558742-S2Open ↗
Showing 3 of 15 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM4
07/18/2012420593940Open ↗
07/18/2012420593940Open ↗
07/12/2012420591443Open ↗
Showing 3 of 4 on file for this type
▸BISPROFESSIONAL CERTIFIED CHECKLIST3
07/18/2012420593940Open ↗
07/12/2012420591443Open ↗
02/07/2012420529707Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT1
07/30/2015440239760Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY1
07/30/2015440239760Open ↗
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION1
07/30/2015440239760Open ↗
▸Trade Schedules & Equipment23
▸BISSELF-CERT PLUMBING NOTICE10
08/30/2013420459435Open ↗
01/29/2013420459435Open ↗
01/04/2013420591443Open ↗
Showing 3 of 10 on file for this type
▸BISSCHEDULE B - PLUMBING9
03/19/2013420349867Open ↗
03/12/2013420459435Open ↗
03/12/2013420349867Open ↗
Showing 3 of 9 on file for this type
▸DOB NOWDEP: Sewer Certification (Sanitary/Storm)4
08/18/2026Q00558742-P5Open ↗
08/13/2026Q00558742-P2Open ↗
08/13/2026Q00558742-P1Open ↗
Showing 3 of 4 on file for this type
▸Safety & Tenant Protection11
▸DOB NOWStreet Tree Checklist4
08/18/2026Q00558742-P5Open ↗
08/13/2026Q00558742-P1Open ↗
08/13/2026Q00558742-I1Open ↗
Showing 3 of 4 on file for this type
▸BISDEMOLITION SUBMITTAL CERTIFICATION FORM3
09/21/2015421188324Open ↗
11/04/2011420349867Open ↗
09/09/2011420349867Open ↗
▸BISSTREET TREE CHECKLIST2
05/02/2011420350756Open ↗
05/02/2011420349867Open ↗
▸BISEXCAVATION OR DEMOLITION: 5-DAY NOTICE1
10/28/2011420349867Open ↗
▸DOB NOWParks Department Acknowledgment Letter for Street Trees Plan1
08/13/2026Q00558742-I1Open ↗
▸Environmental & Asbestos23
▸DOB NOWDEP ACP-5: Asbestos Assessment Report15
08/20/2026Q01168669-I1Open ↗
08/20/2026Q01065006-I1Open ↗
08/20/2026Q01065006-P1Open ↗
Showing 3 of 15 on file for this type
▸BISASBESTOS: CERTIFICATION (DEP ACP5)2
07/29/2015421188324Open ↗
07/18/2012420593940Open ↗
▸BISASBESTOS EXEMPTION CERTIFICATION LETTER2
07/12/2012420591443Open ↗
09/08/2011420480385Open ↗
▸BISDEP ASBESTOS PROJECT COMPLETION FORM1
12/29/2011420349867Open ↗
▸BISTHIS IS 'NOT AN ASBESTOS PROJECT'1
06/22/2011420367043Open ↗
▸BISASBESTOS INSPECTION REPORT1
10/31/2011420349867Open ↗
▸DOB NOWDEP ACP-20/ACP-21: Asbestos Project Conditional Completion Form/Asbestos Project Completion Form1
08/13/2026Q00564061-I1Open ↗
▸Energy Compliance15
▸BISTECHNICAL REPORT: ENERGY6
04/30/2012420349867Open ↗
10/28/2011420349867Open ↗
09/09/2011420349867Open ↗
Showing 3 of 6 on file for this type
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS5
07/29/2015421188324Open ↗
04/29/2014420349867Open ↗
09/06/2012420593940Open ↗
Showing 3 of 5 on file for this type
▸BISTR8: Energy Code Progress Inspections2
04/30/2012420349867Open ↗
08/30/2011420367043Open ↗
▸BISAS-BUILT ENERGY ANALYSIS1
04/08/2014420349867Open ↗
▸DOB NOWPreliminary Commissioning Report Certification1
08/13/2026Q01065006-I1Open ↗
▸Inspections & Test Reports11
▸DOB NOWSOIL REPORT4
08/15/2026Q00558742-S5Open ↗
08/13/2026Q00558742-S1Open ↗
08/13/2026Q00564062-I1Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWTR4 Test Report and Plot Diagram3
08/15/2026Q00558742-S5Open ↗
08/13/2026Q00558742-S1Open ↗
08/13/2026Q00564062-I1Open ↗
▸BISTECHNICAL REPORT: RESPONSIBILITY1
07/30/2015440239760Open ↗
▸BISTECHNICAL REPORT: CONCRETE DESIGN MIX1
10/28/2011420349867Open ↗
▸BISTECHNICAL REPORT: CONCRETE/TEST CYLINDER1
10/28/2011420349867Open ↗
▸DOB NOWTR4 Plot Diagram1
08/13/2026Q00564062-I1Open ↗
▸Approvals, Objections & Sign-offs37
▸DOB NOWFee Exempt Supporting Document - DOF ACRIS report or BIB letter21
08/27/2026Q00592517-I1Open ↗
08/18/2026Q00558742-P5Open ↗
08/16/2026Q01413831-I1Open ↗
Showing 3 of 21 on file for this type
▸BISADMINISTRATIVE OBJECTIONS9
07/29/2015421188324Open ↗
07/18/2012420593940Open ↗
07/12/2012420591443Open ↗
Showing 3 of 9 on file for this type
▸BISLETTERS - SUPPORTING DOCUMENTATION5
08/17/2013420349867Open ↗
03/28/2012420480385Open ↗
03/27/2012420349867Open ↗
Showing 3 of 5 on file for this type
▸BISSCHEDULE A - OCCUPANCY / USE1
08/09/2011420349867Open ↗
▸DOB NOWUtility Company Final Acceptance Letter1
08/13/2026Q01075443-I1Open ↗
▸Cost, Insurance & Ownership16
▸BISCOST AFFIDAVIT11
03/28/2024420350756Open ↗
03/26/2024420350756Open ↗
01/15/2019420350756Open ↗
Showing 3 of 11 on file for this type
▸BISPROJECT-SPECIFIC GL INSURANCE3
04/08/2013420349867Open ↗
04/03/2012420349867Open ↗
10/28/2011420349867Open ↗
▸DOB NOWCertificate of Insurance1
08/18/2026Q00558742-I1Open ↗
▸DOB NOWCertification by Insurance Broker or Agency1
08/18/2026Q00558742-I1Open ↗
▸Filing & Intake Forms15
▸BISEFILING COVER SHEET14
07/29/2015421188324Open ↗
07/18/2012420593940Open ↗
07/18/2012420593940Open ↗
Showing 3 of 14 on file for this type
▸BISEFILING JOB APPLICATION COVER SHEET1
07/30/2015440239760Open ↗
▸Other Documents22
▸DOB NOWPlot Diagram7
08/18/2026Q00558742-P5Open ↗
08/15/2026Q00558742-S5Open ↗
08/13/2026Q00558742-P2Open ↗
Showing 3 of 7 on file for this type
▸DOB NOWSite Survey: Initial4
08/18/2026Q00558742-P5Open ↗
08/13/2026Q00558742-P2Open ↗
08/13/2026Q00558742-P1Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone4
08/18/2026Q00558742-P5Open ↗
08/13/2026Q00558742-P1Open ↗
08/13/2026Q00558742-P2Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWAdjoining Owners Notification2
08/18/2026Q00558742-S1Open ↗
08/13/2026Q00574134-I1Open ↗
▸DOB NOWPARTIAL DEMO: 10-DAY Notice2
08/18/2026Q00558742-S2Open ↗
08/13/2026Q00564061-I1Open ↗
▸BISPLOT DIAGRAM1
05/02/2011420349867Open ↗
▸DOB NOWFinal Survey1
08/13/2026Q00558742-I1Open ↗
▸DOB NOWAdditional Insured Authorizations1