Two family frame
72 HELENE COURT
STATEN ISLAND · Annadale-Huguenot-Prince's Bay-Woodrow · BIN 5085692
💬 Discuss this project
1984Year Built
2Stories
B2Building Class
R3-1Zoning
2,472 sfGross Floor Area
2Units
Two family frame · 6,267 sf lot · 0.39 FAR built · Flood zone X
Locations of Work
ArchitectureElectrical
Roof2p · 1 filing · 7 docs
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
GREEN RIVER ENVIRONMENTAL ENGINEERI111/06/2024
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
NY State Solar LLC203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
NYSS LLCGeneral Contractor303/21/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
GREEN RIVER ENVIRONMENTAL7841111/06/2024
Building Lifecycle
All (8)Filed (1)Permit Issued (1)Signed Off (1)Special Inspection (5)
12/19/2024
Signed off — Alteration
INSTALLATION OF PHOTOVOLTAIC SOLAR ARRAY ON EXISTING ROOF SYSTEM AS PER PLANS
S01137690-I1
11/07/2024
Permit issued — Solar
S01137690-I1-SL
11/06/2024
Filed — Alteration
INSTALLATION OF PHOTOVOLTAIC SOLAR ARRAY ON EXISTING ROOF SYSTEM AS PER PLANS
S01137690-I1
11/05/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
ROBERT MASONE
11/05/2024
Special inspection requirement — Structural Stability – Alterations of existing buildings
ROBERT MASONE
11/05/2024
Special inspection requirement — Energy Code Compliance Inspections
ROBERT MASONE
11/05/2024
Special inspection requirement — Final
ROBERT MASONE
11/05/2024
Special inspection requirement — Air barrier - visual inspection
ROBERT MASONE
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSolarSigned-offNYSS LLC11/07/2024
BISOTISSUEDGRECIAN POOLS INTERNATIONAL08/05/2003
1 project · most recent 10/16/2024
FiledStatusContractorScope
10/16/2024CompleteNY SOLAR ELECTRICAL LLC—
▾Special Inspection Requirements (DOB NOW) — 5
DateRequirementInspectorRole
11/05/2024Fire-Resistant Penetrations and JointsROBERT MASONEspecial
11/05/2024Structural Stability – Alterations of existing buildingsROBERT MASONEspecial
11/05/2024Energy Code Compliance InspectionsROBERT MASONEprogress
11/05/2024FinalROBERT MASONEprogress
11/05/2024Air barrier - visual inspectionROBERT MASONEenergy_progress
▾Documents — 7 on file (BIS + DOB NOW)
▸Plans & Drawings1
▸DOB NOWPlans/Sketch1
08/20/2026S01137690-I1Request digital key ↗
▸Seals & Professional Certifications4
▸DOB NOWProgress Inspector Seal & Signature2
08/24/2026S01137690-I1Open ↗
08/24/2026S01137690-I1Open ↗
▸DOB NOWDPL-1: Design Professional Seal & Signature1
08/13/2026S01137690-I1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature1
08/24/2026S01137690-I1Open ↗
▸Environmental & Asbestos1
▸DOB NOWDEP ACP-5: Asbestos Assessment Report1
08/13/2026S01137690-I1Open ↗
▸Approvals, Objections & Sign-offs1
▸DOB NOWUtility Company Final Acceptance Letter1
08/13/2026S01137690-I1Open ↗