← Back
Two stories - detached, small or mid-size
72 SIMONSON PLACE
STATEN ISLAND · BIN 5024091
💬 Discuss this project
1930Year Built
2.5Stories
A1Building Class
R3AZoning
1,832 sfGross Floor Area
1Units
0 Open ViolationsFDNY Report ↗
Two stories - detached, small or mid-size · 5,100 sf lot · 0.36 FAR built · Flood zone X
Locations of Work
No floor-level scope or drawing coverage on file for this building.
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
AVID DESIGNS, INC104/23/2021
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
CEE JAY REAL ESTATE DEVELOPMENTGeneral Contractor203/21/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
AVID DESIGNS, INC.453104/23/2021
Building Lifecycle
All (31)Filed (1)Permit Issued (1)Signed Off (1)Violation (1)Inspection (1)Objection (14)Special Inspection (12)
04/25/2023
Signed off — Alteration
S00504410-I1
03/22/2023
Inspection — Pass-Final General Construction Non-Directive 14
Pass
View inspection ↗
03/09/2023
Permit issued — General Construction
S00504410-I1-GC
02/14/2022
Objection raised — Other
02/14/2022
Objection resolved — Addressed
02/14/2022
Objection raised — Scope
02/14/2022
Objection resolved — Addressed
02/14/2022
Objection raised — Zoning
02/14/2022
Objection resolved — Addressed
02/14/2022
Objection raised — Structural
02/14/2022
Objection resolved — Addressed
02/14/2022
Objection raised — Other
02/14/2022
Objection resolved — Addressed
02/14/2022
Objection raised — Inspections
02/14/2022
Objection resolved — Addressed
05/04/2021
Objection raised — Scope
05/04/2021
Objection resolved — Addressed
04/23/2021
Filed — Alteration
S00504410-I1
04/16/2021
Special inspection requirement — Concrete - Cast-In-Place
Jeffrey Geary
04/16/2021
Special inspection requirement — Fire-Resistant Penetrations and Joints
Jeffrey Geary
04/16/2021
Special inspection requirement — Energy Code Compliance Inspections
Jeffrey Geary
04/16/2021
Special inspection requirement — Fire-Resistance Rated Construction
Jeffrey Geary
04/16/2021
Special inspection requirement — Insulation placement and R values
Jeffrey Geary
04/16/2021
Special inspection requirement — Fenestration air leakage
Jeffrey Geary
04/16/2021
Special inspection requirement — Interior lighting power
Jeffrey Geary
04/16/2021
Special inspection requirement — Air barrier — testing
Jeffrey Geary
04/16/2021
Special inspection requirement — Fenestration areas
Jeffrey Geary
04/16/2021
Special inspection requirement — Air barrier - visual inspection
Jeffrey Geary
04/16/2021
Special inspection requirement — Fenestration and door U-factor and product ratings
Jeffrey Geary
04/16/2021
Special inspection requirement — HVAC-R and service water piping design and insulation
Jeffrey Geary
12/16/2020
Violation issued (ECB, closed)
Construction
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWGeneral ConstructionSigned-offSTRUCTURETECH NY03/09/2023
BISOTISSUEDVENTURE HOME SOLAR LLC11/01/2019
2 projects · most recent 11/26/2019
FiledStatusContractorScope
11/26/2019CompleteVENTURE HOME SOLAR LLC—
10/29/2019CompleteVENTURE HOME SOLAR LLC1 meters
▾Field Inspections (DOB CAP) — 1
DateTypeResultReport
03/22/2023Pass-Final General Construction Non-Directive 14PassView ↗
▾Special Inspection Requirements (DOB NOW) — 12
DateRequirementInspectorRole
04/16/2021Concrete - Cast-In-PlaceJeffrey Gearyspecial
04/16/2021Fire-Resistant Penetrations and JointsJeffrey Gearyspecial
04/16/2021Energy Code Compliance InspectionsJeffrey Gearyprogress
04/16/2021Fire-Resistance Rated ConstructionJeffrey Gearyprogress
04/16/2021Insulation placement and R valuesJeffrey Gearyenergy_progress
04/16/2021Fenestration air leakageJeffrey Gearyenergy_progress
04/16/2021Interior lighting powerJeffrey Gearyenergy_progress
04/16/2021Air barrier — testing Jeffrey Gearyenergy_progress
04/16/2021Fenestration areasJeffrey Gearyenergy_progress
04/16/2021Air barrier - visual inspectionJeffrey Gearyenergy_progress
04/16/2021Fenestration and door U-factor and product ratingsJeffrey Gearyenergy_progress
04/16/2021HVAC-R and service water piping design and insulationJeffrey Gearyenergy_progress
▾Documents — 47 on file (BIS + DOB NOW)
▸Plans & Drawings1
▸DOB NOWPlans/Sketch1
08/15/2026S00504410-I1Request digital key ↗
▸Applications & Permits2
▸BISPLAN / WORK APPROVAL APPLICATION1
10/31/2019540170517Open ↗
▸BISWORK PERMIT APPLICATION1
10/31/2019540170517Open ↗
▸Zoning, Tax Lot & Property Records2
▸DOB NOWZD1: DOB Zoning Diagram1
08/13/2026S00504410-I1Open ↗
▸DOB NOWZoning Exhibit form (1-5)1
08/13/2026S00504410-I1Open ↗
▸Seals & Professional Certifications16
▸DOB NOWProgress Inspector Seal & Signature10
08/28/2026S00504410-I1Open ↗
08/28/2026S00504410-I1Open ↗
08/28/2026S00504410-I1Open ↗
Showing 3 of 10 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature2
08/28/2026S00504410-I1Open ↗
08/28/2026S00504410-I1Open ↗
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION1
10/31/2019540170517Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT1
10/31/2019540170517Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY1
10/31/2019540170517Open ↗
▸DOB NOWDPL-1: Design Professional Seal & Signature1
08/25/2026S00504410-I1Open ↗
▸Trade Schedules & Equipment1
▸DOB NOWDEP: Sewer Certification (Sanitary/Storm)1
08/13/2026S00504410-I1Open ↗
▸Safety & Tenant Protection1
▸BISTENANT PROTECTION PLAN AND NOTES1
10/31/2019540170517Open ↗
▸Environmental & Asbestos2
▸BISASBESTOS: CERTIFICATION (DEP ACP5)1
10/31/2019540170517Open ↗
▸DOB NOWDEP ACP-5: Asbestos Assessment Report1
08/15/2026S00504410-I1Open ↗
▸Energy Compliance8
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY3
01/16/2020540170517Open ↗
10/31/2019540170517Open ↗
10/31/2019540170517Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY FOR ENERGY CODE PROGRESS INSPECTIONS1
10/31/2019540170517Open ↗
▸BISAS-BUILT ENERGY ANALYSIS1
01/16/2020540170517Open ↗
▸BISPTA4: SOLAR TAX ABATEMENT APPLICATION (PRELIMINARY)1
10/31/2019540170517Open ↗
▸BISPTA4: SOLAR TAX ABATEMENT APPLICATION (FINAL)1
01/16/2020540170517Open ↗
▸DOB NOWEN2: As Built Energy Analysis.1
08/13/2026S00504410-I1Open ↗
▸Inspections & Test Reports5
▸BISTECHNICAL REPORT: RESPONSIBILITY4
01/16/2020540170517Open ↗
01/16/2020540170517Open ↗
10/31/2019540170517Open ↗
Showing 3 of 4 on file for this type
▸BISDIR-14 ID OF RESPONSIBILITY (TR1)1
10/31/2019540170517Open ↗
▸Approvals, Objections & Sign-offs2
▸BISUtility Company PV System Interconnection Acknowledgement Letter1
01/16/2020540170517Open ↗
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST1
01/16/2020540170517Open ↗
▸Cost, Insurance & Ownership2
▸BISCOST AFFIDAVIT2
01/16/2020540170517Open ↗
10/31/2019540170517Open ↗
▸Filing & Intake Forms2
▸BISADDITIONAL INFORMATION1
01/28/2020540170517Open ↗
▸BISEFILING JOB APPLICATION COVER SHEET1
10/31/2019540170517Open ↗
▸Other Documents3
▸BISCONSTRUCTION - SUPPORTING DOCUMENTATION1
10/31/2019540170517Open ↗
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone1
08/13/2026S00504410-I1Open ↗
▸DOB NOWPlot Diagram1
08/13/2026S00504410-I1Open ↗