Office with commercial, 7-19 stories
720 5TH AVENUE
MANHATTAN · BIN 1035051
💬 Discuss this project
1954Year Built
15Stories
O6Building Class
C5-3Zoning
113,292 sfGross Floor Area
18Units
LL97 Covered0 Active ViolationsFISP: SWARMP
Office with commercial, 7-19 stories · Owner of record: 720 Fifth USA · 7,553 sf lot · 15 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralElectricalMechanicalPlumbingFire ProtectionEquipmentCivilGeneral
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
Permit Issued — active, not yet Signed-off
Whole building & multi-floor projectsTemporary pipe scaffold for remedial work1 filing
Floor 3Prada1p · 5 filings · 20 docs
Floor 2PradaUnder Construction10p · 10 filings · 20 docs
Floor 1Prada, ProjectUnder Construction12p · 13 filings · 20 docs
CellarPrada, ProjectUnder Construction6p · 8 filings · 20 docs
Site & exteriorPradaUnder Construction8 filings · 17 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
720 Fifth9303/22/2026
Promenade Real Estate1903/21/2026
720 Fifith Avenue1503/21/2026
720 5th Ave Associates1103/21/2026
Arcana Associates703/22/2026
Wharton Realty703/21/2026
720 5 Avenue Associates403/21/2026
Dakota Realty303/21/2026
Recaae 720 5th Bavellc203/21/2026
720 Fifth Ave LLC Promenade Realty103/21/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
12/19/2023$397.4M—— → —$3,508/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
Design Republic408/27/2026
Tohfaz Uddin PE512/30/2025
Studio Huji202/25/2025
Fiskaa Engineering502/11/2025
Gilsanz Murray Steficek209/18/2024
SYNC Architecture201/26/2024
Andrew Katz Engineers203/08/2021
Syed Engineering109/02/2020
Green Design108/19/2020
Haider Engineering, P.E111/08/2019
AP Professional Engineering206/18/2019
Navi Structural Engineering104/18/2019
Royal T&E103/30/2019
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
Alba Fire Safety203/21/2026
Aca Associates103/21/2026
Signs Cad403/21/2026
Milrose Consultants2003/21/2026
Municipal Building Consultants103/21/2026
Spring Scaffolding603/21/2026
SNR Expediting Design203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
Kings Group NYScaffold1907/08/2026
JT Magen & CompanyGeneral Contractor1307/08/2026
Spring ScaffoldingScaffold708/13/2026
King Hoist & ScaffoldingScaffold403/21/2026
Sirina Fire ProtectionFire Protection307/08/2026
Signs CadSign hanger207/08/2026
L & Z RestorationScaffold203/21/2026
Enok Electrical CoElectrical203/21/2026
V. Vass ElectricElectrical103/21/2026
Omd ElectricalElectrical103/22/2026
United King ConstructionScaffold107/08/2026
Lab Plumbing & Heating CoPlumbing107/08/2026
Olympic Plumbing & Heating ServicesFire Protection107/08/2026
Winick ProductionsGeneral Contractor107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
Milrose Consultants2003602/11/2025
Gilsanz Murray Steficek240108/22/2024
David Katz, P.E6087203/08/2021
Building Lifecycle
All (189)Filed (29)Permit Issued (37)Signed Off (11)Facade (FISP) (14)Violation (60)Inspection (8)Special Inspection (30)
08/27/2026
Filed — Alteration
DEMOLITION AND INTERIOR RENOVATIONS / MODIFICATIONS AS PER PLANS FILED HEREWITH. NO CHANGE TO USE, EGRESS OR OCCUPANCY
M01087511-P1
08/17/2026
Special inspection requirement — Final
barry ludlow
08/12/2026
Permit issued — Sidewalk Shed
M01204381-I1-SH
05/29/2026
Permit issued — Sidewalk Shed
M01204381-I1-SH
03/04/2026
Permit issued — Sidewalk Shed
M01204381-I1-SH
02/04/2026
Permit issued — General Construction
M01096421-I1-GC
12/30/2025
Filed — Alteration
INSTALLATION OF TEMPORARY CUSTOM COLOR SIDEWALK SHED AS PER PLAN. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.THE CUSTOM COLOR SIDEWALK SHED AT WEST 56TH STREET AND 5TH AVENUE ELEVATIONS.
M01204381-S1
12/30/2025
Permit issued — Supported Scaffold
M01204381-S1-SF
09/04/2025
Filed — Alteration
INSTALLATION OF TEMPORARY CUSTOM COLOR SIDEWALK SHED AS PER PLAN. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.THE CUSTOM COLOR SIDEWALK SHED AT WEST 56TH STREET AND 5TH AVENUE ELEVATIONS.
M01204381-P1
08/13/2025
Signed off — Alteration
MODIFICATIONS TO EXISTING HVAC AND DUCTWORK AS PER PLANS FILED HEREWITH. NO CHANGE TO USE, EGRESS, OR OCCUPANCY.
M01077415-I1
08/01/2025
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
06/30/2025
Inspection — Certified StandPipe-SD-Fixtures-Finish-SD
Certified
View inspection ↗
06/17/2025
Inspection — Certified StandPipe-SD-Piping-Hydrostatic Test
Certified
View inspection ↗
05/19/2025
Signed off — Alteration
INSTALL A NON-ILLUMINATED WALL SIGN A @WEST 56 STREET "PRADA"
M01168174-I1
05/19/2025
Signed off — Alteration
INSTALL A NON-ILLUMINATED WALL SIGN B @FIFTH AVENUE "PRADA"
M01168194-I1
05/06/2025
Inspection — Certified Remove/Cap - work done in accordance with code
Certified
View inspection ↗
05/06/2025
Inspection — Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test
Certified
View inspection ↗
04/03/2025
Permit issued — Sidewalk Shed
M01204381-I1-SH
04/02/2025
Filed — Alteration
INSTALLATION OF TEMPORARY CUSTOM COLOR SIDEWALK SHED AS PER PLAN. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.THE CUSTOM COLOR SIDEWALK SHED AT WEST 56TH STREET AND 5TH AVENUE ELEVATIONS.
M01204381-I1
03/31/2025
Signed off — Alteration
M01094713-I1
03/31/2025
Signed off — Alteration
INSTALLATION OF PLYWOOD ENCLOSURE AS PER PLANS. NO CHANGE IN EGRESS, USE, OR OCCUPANCY.
M01187428-I1
03/11/2025
Permit issued — Structural
M01096444-I1-ST
02/27/2025
Filed — Alteration
INSTALLATION OF PLYWOOD ENCLOSURE AS PER PLANS. NO CHANGE IN EGRESS, USE, OR OCCUPANCY.
M01187428-I1
02/27/2025
Permit issued — Sign
M01168174-I1-SG
02/27/2025
Permit issued — Construction Fence
M01187428-I1-FN
02/26/2025
Permit issued — Sign
M01168194-I1-SG
02/25/2025
Filed — Alteration
INSTALL A NON-ILLUMINATED WALL SIGN A @WEST 56 STREET "PRADA"
M01168174-I1
02/25/2025
Filed — Alteration
INSTALL A NON-ILLUMINATED WALL SIGN B @FIFTH AVENUE "PRADA"
M01168194-I1
02/24/2025
Special inspection requirement — Final
Ryan Hung
02/20/2025
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
02/12/2025
Special inspection requirement — Post-installed Anchors
Christopher Drutjons
02/12/2025
Special inspection requirement — Sprinkler Systems
Christopher Drutjons
02/11/2025
Filed — Alteration
PLUMBING AND SPRINKLER MODIFICATIONS AS PER PLANS FILED HEREWITH. NO CHANGE TO USE, EGRESS OR OCCUPANCY.
M01077430-P1
02/10/2025
Special inspection requirement — Post-installed Anchors
Christopher Drutjons
02/10/2025
Special inspection requirement — Sprinkler Systems
Christopher Drutjons
01/21/2025
Permit issued — Standpipe
M01130576-I1-EW-SD
01/16/2025
Permit issued — Sprinklers
M01077430-I1-PL
01/14/2025
Permit issued — Plumbing
M01077430-I1-EW-SP
01/08/2025
Permit issued — General Construction
M01087511-I1-GC
12/17/2024
Filed — Alteration
Relocated/extended Siamese connections for standpipe as per plans filed herewith. No change to use, egress or occupancy.
M01130576-I1
11/07/2024
Signed off — Alteration
pipe scaffold
M00153576-I1
10/23/2024
Inspection — Certified Sprinkler-SP-Fixtures-Finish
Certified
View inspection ↗
10/23/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
Christopher Drutjons
10/22/2024
Special inspection requirement — Standpipe Systems
Christopher Drutjons
10/16/2024
Inspection — Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test
Certified
View inspection ↗
09/30/2024
Permit issued — General Construction
M01077408-I1-GC
09/27/2024
Permit issued — General Construction
M01087511-I1-GC
09/27/2024
Permit issued — Mechanical Systems
M01077415-I1-MS
09/26/2024
Permit issued — Structural
M01091816-I1-ST
09/19/2024
Permit issued — Sprinklers
M01078155-I1-EW-SP
09/18/2024
Filed — Alteration
M01096444-I1
09/17/2024
Filed — Alteration
M01096421-I1
09/16/2024
Filed — Alteration
Installation of temp loop as per plans filed herewith. No change in use, egress or occupancy.
M01078155-I1
09/16/2024
Permit issued — Mechanical Systems
M01077415-I1-MS
09/12/2024
Special inspection requirement — Vestibules
Christopher Drutjons
09/12/2024
Special inspection requirement — Fenestration air leakage
Christopher Drutjons
09/12/2024
Special inspection requirement — Fenestration and door U-factor and product ratings
Christopher Drutjons
09/12/2024
Special inspection requirement — Insulation placement and R values
Christopher Drutjons
09/03/2024
Special inspection requirement — Structural Steel - High Strength Bolting
Christopher Drutjons
09/03/2024
Special inspection requirement — Post-installed Anchors
Christopher Drutjons
Latest 60 of 189 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSidewalk ShedPermit IssuedSpring Scaffolding08/12/2026
DOB NOWSidewalk ShedPermit IssuedSpring Scaffolding05/29/2026
DOB NOWSidewalk ShedPermit IssuedSpring Scaffolding03/04/2026
DOB NOWGeneral ConstructionSigned-offJT Magen & Company02/04/2026
DOB NOWSupported ScaffoldPermit IssuedSpring Scaffolding12/30/2025
DOB NOWSidewalk ShedPermit IssuedSpring Scaffolding04/03/2025
DOB NOWStructuralPermit IssuedJT Magen & Company03/11/2025
DOB NOWSignSigned-offSigns Cad02/27/2025
DOB NOWConstruction FenceSigned-offKing Hoist & Scaffolding02/27/2025
DOB NOWSignSigned-offSigns Cad02/26/2025
DOB NOWStandpipeSigned-offSirina Fire Protection01/21/2025
DOB NOWPlumbingSigned-offLab Plumbing & Heating Co01/16/2025
DOB NOWSprinklersSigned-offSirina Fire Protection01/14/2025
DOB NOWGeneral ConstructionPermit IssuedJT Magen & Company01/08/2025
DOB NOWGeneral ConstructionPermit IssuedJT Magen & Company09/30/2024
DOB NOWGeneral ConstructionPermit IssuedJT Magen & Company09/27/2024
DOB NOWMechanical SystemsSigned-offJT Magen & Company09/27/2024
DOB NOWStructuralPermit IssuedJT Magen & Company09/26/2024
DOB NOWSprinklersSigned-offSirina Fire Protection09/19/2024
DOB NOWMechanical SystemsSigned-offJT Magen & Company09/16/2024
DOB NOWStructuralPermit IssuedJT Magen & Company08/30/2024
DOB NOWGeneral ConstructionPermit IssuedJT Magen & Company08/22/2024
DOB NOWConstruction FenceSigned-offKing Hoist & Scaffolding08/12/2024
DOB NOWGeneral ConstructionPermit IssuedJT Magen & Company07/15/2024
DOB NOWGeneral ConstructionSigned-offWinick Productions01/29/2024
DOB NOWSidewalk ShedPermit IssuedKings Group NY03/11/2021
DOB NOWSidewalk ShedPermit IssuedKings Group NY03/08/2021
DOB NOWSprinklersSigned-offOlympic Plumbing & Heating Services11/19/2020
DOB NOWSupported ScaffoldSigned-offKings Group NY09/03/2020
DOB NOWSupported ScaffoldPermit IssuedUnited King Construction08/20/2020
DOB NOWSidewalk ShedPermit IssuedKings Group NY11/08/2019
DOB NOWSidewalk ShedPermit IssuedKings Group NY10/03/2019
DOB NOWSupported ScaffoldSigned-offKings Group NY09/20/2019
DOB NOWSupported ScaffoldSigned-offKings Group NY09/19/2019
DOB NOWSupported ScaffoldSigned-offMichael Dellavecchia & Sons04/23/2019
DOB NOWSupported ScaffoldSigned-offKings Group NY04/01/2019
DOB NOWSidewalk ShedPermit IssuedKings Group NY11/13/2018
BISEQISSUEDUniversal Builders Supply02/03/2023
BISEQISSUEDUniversal Builders Supply02/08/2022
BISEQISSUEDUniversal Builders Supply03/08/2021
+ 47 more permits on file
2 projects · most recent 02/11/2025
FiledStatusContractorScope
02/11/2025Signed-offSirina Fire Protection178 heads
09/16/2024Signed-offSirina Fire Protection—
1 project · most recent 02/11/2025
Water/Sanitary
FiledStatusContractorScope
02/11/2025Signed-offLab Plumbing & Heating CoWater/Sanitary
8 projects · most recent 04/03/2025
General Wiring
FiledStatusContractorScope
04/03/2025Permit IssuedTop Shelf Electric—
12/31/2024CompleteH. & L. ElectricGeneral Wiring
08/10/2023CompleteInter Connection EletricGeneral Wiring
06/27/2023Permit IssuedOmd Electrical1 meters, 1 new_meters
07/09/2020Permit IssuedRichard Neu—
11/14/2019CompleteWCK Electric—
07/03/2019CompleteVerde ElectricGeneral Wiring
11/09/2018Permit IssuedMeo Electric—
1 project · most recent 08/22/2024
Steel
FiledStatusContractorScope
08/22/2024Permit IssuedJT Magen & CompanySteel
2 projects · most recent 12/30/2025
Sidewalk Shed Scaffold
FiledStatusContractorScope
12/30/2025Permit IssuedSpring ScaffoldingSidewalk Shed
08/19/2020Permit IssuedUnited King ConstructionScaffold
▾Field Inspections (DOB CAP) — 8
DateTypeResultReport
08/01/2025Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
06/30/2025Certified StandPipe-SD-Fixtures-Finish-SDCertifiedView ↗
06/17/2025Certified StandPipe-SD-Piping-Hydrostatic TestCertifiedView ↗
05/06/2025Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
05/06/2025Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
02/20/2025Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
10/23/2024Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
10/16/2024Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 38
DateRequirementInspectorRole
08/17/2026Finalbarry ludlowprogress
02/24/2025FinalRyan Hungprogress
02/12/2025Post-installed AnchorsChristopher Drutjonsspecial
02/12/2025Sprinkler SystemsChristopher Drutjonsspecial
02/10/2025Post-installed AnchorsChristopher Drutjonsspecial
02/10/2025Sprinkler SystemsChristopher Drutjonsspecial
10/23/2024Fire-Resistant Penetrations and JointsChristopher Drutjonsspecial
10/22/2024Standpipe SystemsChristopher Drutjonsspecial
09/12/2024VestibulesChristopher Drutjonsenergy_progress
09/12/2024Fenestration air leakageChristopher Drutjonsenergy_progress
09/12/2024Fenestration and door U-factor and product ratingsChristopher Drutjonsenergy_progress
09/12/2024Insulation placement and R valuesChristopher Drutjonsenergy_progress
09/03/2024Structural Steel - High Strength BoltingChristopher Drutjonsspecial
09/03/2024Post-installed AnchorsChristopher Drutjonsspecial
09/03/2024Structural Cold-Formed SteelChristopher Drutjonsspecial
09/03/2024Structural Stability – Alterations of existing buildingsChristopher Drutjonsspecial
09/03/2024Structural Steel - DetailsChristopher Drutjonsspecial
09/03/2024Structural Steel - WeldingChristopher Drutjonsspecial
08/20/2024Structural Steel - High Strength BoltingRamon Gilsanzspecial
08/20/2024Structural Steel - WeldingRamon Gilsanzspecial
08/20/2024Post-installed AnchorsRamon Gilsanzspecial
08/20/2024Structural Steel - DetailsRamon Gilsanzspecial
08/20/2024Structural Stability – Alterations of existing buildingsRamon Gilsanzspecial
08/14/2024FinalRamon Gilsanzprogress
08/14/2024FinalChristopher Drutjonsprogress
Latest 25 of 38.
▾Tenants in the building
TenantSpaceFloorsRenovation projects
PradaRetailCellar, Floors 1–3
Project M01204381 Alteration · Permit Entire · 04/02/2025
Project M01187428 Alteration · LOC Issued · 02/27/2025
Project M01168174 Alteration · LOC Issued · 02/25/2025
Project M01168194 Alteration · LOC Issued · 02/25/2025
Project M01130576 Alteration · Permit Entire · 12/17/2024
Project M01096444 Alteration · Permit Entire · 09/18/2024
Project M01096421 Alteration · Permit Entire · 09/17/2024
Project M01078155 Alteration · Permit Entire · 09/16/2024
Project M01077430 Alteration · Permit Entire · 08/22/2024
Project M01091816 Alteration · Permit Entire · 08/22/2024
Project M01077415 Alteration · LOC Issued · 08/21/2024
Project M01087511 Alteration · Permit Entire · 08/20/2024
ProjectEvents & gatheringsCellar, Floor 1
Project M00994499 Alteration · LOC Issued · 01/23/2024
Names are taken automatically from the text of each project’s filed documents (title blocks and cover sheets) and screened to exclude owners, landlords and designers. They may be incomplete or wrong; check the filing.
▾Documents — 816 on file (BIS + DOB NOW)
▸Plans & Drawings30
▸DOB NOWPlans/Sketch20
09/05/2026M00098335-I1Request digital key ↗
08/28/2026M00994499-I1Request digital key ↗
08/26/2026M01077408-I1Request digital key ↗
Showing 3 of 20 on file for this type
▸DOB NOWPlans/Sketch - Supported Scaffold4
09/05/2026M00148590-I1Request digital key ↗
09/05/2026M00148590-S1Request digital key ↗
09/05/2026M00153576-I1Request digital key ↗
Showing 3 of 4 on file for this type
▸DOB NOWPlans/Sketch - Sidewalk Shed3
09/05/2026M00098335-I1Request digital key ↗
09/05/2026M00098335-P1Request digital key ↗
09/05/2026M00260736-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Sprinkler2
09/04/2026M00365710-I1Request digital key ↗
08/15/2026M00365710-P1Request digital key ↗
▸DOB NOWPlans/Sketch - Temporary Place of Assembly1
08/28/2026M00994600-I1Request digital key ↗
▸Applications & Permits146
▸BISPLAN / WORK APPROVAL APPLICATION84
11/12/2020140944959Open ↗
11/04/2020140944959Open ↗
08/27/2020140944959Open ↗
Showing 3 of 84 on file for this type
▸BISWORK PERMIT APPLICATION61
09/10/2020123843369Open ↗
05/01/2019123852973Open ↗
04/12/2019140842685Open ↗
Showing 3 of 61 on file for this type
▸BISEQUIPMENT (EQ) PERMITS1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Seals & Professional Certifications213
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION86
03/10/2020123843369Open ↗
02/05/2020123852973Open ↗
02/05/2020123852973Open ↗
Showing 3 of 86 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature29
09/05/2026M00098335-I1Open ↗
09/05/2026M00098335-P1Open ↗
09/05/2026M00260736-I1Open ↗
Showing 3 of 29 on file for this type
▸BISPROFESSIONAL CERTIFIED CHECKLIST25
03/10/2020123843369Open ↗
03/20/2019123852973Open ↗
03/05/2019123754767Open ↗
Showing 3 of 25 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT20
08/27/2020140944959Open ↗
03/10/2020123843369Open ↗
04/12/2019140842685Open ↗
Showing 3 of 20 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature15
09/01/2026M00365710-I1Open ↗
08/29/2026M01091816-I1Open ↗
08/29/2026M01091816-I1Open ↗
Showing 3 of 15 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM14
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 14 on file for this type
▸DOB NOWProgress Inspector Seal & Signature12
10/14/2026M01087511-P1Open ↗
08/30/2026M01096421-I1Open ↗
08/30/2026M01096421-I1Open ↗
Showing 3 of 12 on file for this type
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION6
08/27/2020140944959Open ↗
04/12/2019140842685Open ↗
Showing 2 of 6 on file for this type
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY6
08/27/2020140944959Open ↗
04/12/2019140842685Open ↗
Showing 2 of 6 on file for this type
▸Trade Schedules & Equipment64
▸BISSELF-CERT PLUMBING NOTICE24
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 24 on file for this type
▸BISSCHEDULE B - PLUMBING15
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 15 on file for this type
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE10
12/16/2019123852973Open ↗
12/16/2019123852973Open ↗
12/10/2019123852973Open ↗
Showing 3 of 10 on file for this type
▸BISSPRINKLER INSP REPORT : FP-857
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 7 on file for this type
▸BISFA - FDNY APPROVAL : FD-FAA6
07/17/2020122133306Open ↗
10/18/2019122250492Open ↗
Showing 2 of 6 on file for this type
▸BISEQUIPMENT USE APPLICATION/PERMIT1
11/02/2015122190770Open ↗
▸BISEQUIPMENT USE PERMITS1
11/02/2015122190770Open ↗
▸Safety & Tenant Protection1
▸BISTENANT PROTECTION PLAN AND NOTES1
08/27/2020140944959Open ↗
▸Environmental & Asbestos71
▸BISTHIS IS 'NOT AN ASBESTOS PROJECT'28
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 28 on file for this type
▸BISASBESTOS: CERTIFICATION (DEP ACP5)16
03/20/2019123852973Open ↗
12/17/2018123512172Open ↗
08/09/2018123460021Open ↗
Showing 3 of 16 on file for this type
▸DOB NOWDEP ACP-5: Asbestos Assessment Report14
08/26/2026M01087511-P1Open ↗
08/26/2026M01091816-I1Open ↗
08/26/2026M01077430-I1Open ↗
Showing 3 of 14 on file for this type
▸BISASBESTOS INSPECTION REPORT8
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 8 on file for this type
▸BISASBESTOS EXEMPTION CERTIFICATION LETTER4
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 4 on file for this type
▸BISAPPLICANT SHALL PROVIDE 1 ACP-21 FORMPRIOR TO SIGN OFF: TRU1311MN201
05/14/2021123843369Open ↗
▸Energy Compliance32
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS15
03/10/2020123843369Open ↗
11/04/2019123460021Open ↗
12/17/2018123512172Open ↗
Showing 3 of 15 on file for this type
▸BISAS-BUILT ENERGY ANALYSIS7
11/04/2019123460021Open ↗
01/25/2018123193935Open ↗
11/15/2017123134205Open ↗
Showing 3 of 7 on file for this type
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY3
08/27/2020140944959Open ↗
Showing 1 of 3 on file for this type
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY FOR ENERGY CODE PROGRESS INSPECTIONS2
08/27/2020140944959Open ↗
Showing 1 of 2 on file for this type
▸BISTECHNICAL REPORT: ENERGY2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISAS-BUILT ENERGY ANALYSIS (EN2)1
05/14/2021123843369Open ↗
▸BISELECTRICAL APPLICATION FOR SIDEWALK SHED LIGHTING1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BISENERGY CODE COMPLIANCE INSPECTIONS1
05/14/2021123843369Open ↗
▸Inspections & Test Reports12
▸BISTECHNICAL REPORT: RESPONSIBILITY8
09/11/2023140842685Open ↗
09/11/2023140842685Open ↗
08/27/2020140944959Open ↗
Showing 3 of 8 on file for this type
▸BISHYDRAULIC FLOW CALCULATIONS2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISSTRUCTURAL STABILITY - EXISTING BUILDINGS1
05/14/2021123843369Open ↗
▸BISMASONRY1
05/14/2021123843369Open ↗
▸Approvals, Objections & Sign-offs84
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST38
09/11/2023140842685Open ↗
11/15/2021122133306Open ↗
05/14/2021123843369Open ↗
Showing 3 of 38 on file for this type
▸BISADMINISTRATIVE OBJECTIONS26
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 26 on file for this type
▸BISLETTERS - SUPPORTING DOCUMENTATION16
11/04/2019123460021Open ↗
01/11/2016122235385Open ↗
12/03/2015122190770Open ↗
Showing 3 of 16 on file for this type
▸BISFINAL1
05/14/2021123843369Open ↗
▸BISLANDMARKS APPROVAL1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BISCCD1-Construction Code Determination1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BISSHED LETTER1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Cost, Insurance & Ownership89
▸BISCOST AFFIDAVIT88
08/27/2020140944959Open ↗
06/10/2020123852973Open ↗
06/10/2020123852973Open ↗
Showing 3 of 88 on file for this type
▸BISCOST AFFIDAVIT (FINAL): PW31
05/14/2021123843369Open ↗
▸Filing & Intake Forms65
▸BISEFILING COVER SHEET36
03/10/2020123843369Open ↗
03/20/2019123852973Open ↗
03/05/2019123754767Open ↗
Showing 3 of 36 on file for this type
▸BISBOROUGH INTAKE FORM14
03/25/2020123852973Open ↗
03/02/2020123852973Open ↗
12/10/2019123852973Open ↗
Showing 3 of 14 on file for this type
▸BISADDITIONAL INFORMATION9
11/12/2020140944959Open ↗
12/16/2019123852973Open ↗
12/10/2019123852973Open ↗
Showing 3 of 9 on file for this type
▸BISEFILING JOB APPLICATION COVER SHEET6
08/27/2020140944959Open ↗
04/12/2019140842685Open ↗
Showing 2 of 6 on file for this type
▸Other Documents9
▸BISEXTERNAL FORMS - SUPPORTING DOCUMENTATION4
08/26/2015140351018Open ↗
Showing 1 of 4 on file for this type
▸BISCONSTRUCTION - SUPPORTING DOCUMENTATION2
09/10/2020123843369Open ↗
Showing 1 of 2 on file for this type
▸DOB NOWBSA Meeting Minutes/BSA Resolution2
09/05/2026M00098335-I1Open ↗
09/05/2026M00098335-P1Open ↗
▸BISSupporting Document: Fee Exempt1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type