| Owner | Filings | Most Recent |
|---|---|---|
| ARBER CONSTRUCTION | 14 | 08/29/2026 |
| ALL RECI REALTY | 2 | 03/21/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 03/20/2024 | $290K | — | 722 EAST 218TH CORP. → 722 RECI REALTY LLC | — not available |
| 03/23/2018 | $197K | — | Private party → 722 EAST 218TH CORP. | — not available |
| Firm | Filings | Most Recent |
|---|---|---|
| GERALD CALIENDO ARCHITECTS | 7 | 03/18/2026 |
| FABIAN CRUZ PE PLLC | 2 | 02/20/2025 |
| Representative | Filings | Most Recent |
|---|---|---|
| GERALD J CALIENDO ARCHITECT | 11 | 03/21/2026 |
| GERALD J. CALIENDO R.A., P.C. | 1 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| ARBER CONSTRUCTION CORP | General Contractor | 12 | 04/09/2026 |
| GERALD J CALIENDO ARCHITECT | General Contractor | 4 | 03/22/2026 |
| PRIME PIPING HEATING IN | Plumbing | 2 | 03/22/2026 |
| PRIME PIPING & HEATING IN | Fire Protection | 1 | 07/08/2026 |
| HORBRIDGE PLUMBING & HEATING | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| S&S CONCRETE & SOIL TESTI | 1008 | 6 | 03/18/2026 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Curb Cut | Signed-off | ARBER CONSTRUCTION | 09/11/2025 |
| DOB NOW | Structural | Signed-off | ARBER CONSTRUCTION | 09/11/2025 |
| DOB NOW | Earth Work | Signed-off | ARBER CONSTRUCTION | 07/16/2025 |
| DOB NOW | Mechanical Systems | Signed-off | ARBER CONSTRUCTION | 07/16/2025 |
| DOB NOW | General Construction | Permit Issued | ARBER CONSTRUCTION | 07/16/2025 |
| DOB NOW | Construction Fence | Signed-off | ARBER CONSTRUCTION | 07/16/2025 |
| DOB NOW | Sprinklers | Signed-off | A M B MECHANICAL INC | 06/23/2025 |
| DOB NOW | Sprinklers | Signed-off | HORBRIDGE PLUMBING & HEAT | 04/29/2025 |
| DOB NOW | Mechanical Systems | Signed-off | ARBER CONSTRUCTION | 03/28/2025 |
| DOB NOW | General Construction | Permit Issued | ARBER CONSTRUCTION | 03/27/2025 |
| DOB NOW | Foundation | Signed-off | ARBER CONSTRUCTION | 03/26/2025 |
| DOB NOW | Construction Fence | Signed-off | ARBER CONSTRUCTION | 03/13/2025 |
| BIS | FS | ISSUED | PULLMAN FUEL OIL CO INC | 01/18/1994 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 03/18/2026 | Signed-off | ARBER CONSTRUCTION CORP | Heating and Air Conditioning Systems, Ventilation Systems |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 03/18/2026 | Signed-off | PRIME PIPING & HEATING IN | Sprinkler System |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 03/18/2026 | Signed-off | HORBRIDGE PLUMBING & HEAT | Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 11/17/2025 | Complete | K.A.B. ELECTRIC CORP | General Wiring |
| Date | Type | Result | Report |
|---|---|---|---|
| 12/18/2025 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 11/28/2025 | Pass-Final Curb Cut Non-Directive 14 | Pass | View ↗ |
| 11/04/2025 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 10/10/2025 | Fail-Final Curb Cut Non-Directive 14 | Fail | View ↗ |
| 09/03/2025 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 08/28/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 06/23/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 05/14/2025 | Certified Storm Drainage-ST-Piping-Roughing | Certified | View ↗ |
| 05/14/2025 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 05/14/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 02/28/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 02/26/2025 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 03/18/2026 | Fenestration areas | GLEN LANGER | energy_progress |
| 03/18/2026 | Insulation placement and R values | GLEN LANGER | energy_progress |
| 03/18/2026 | Permanent certificate | GLEN LANGER | energy_progress |
| 03/18/2026 | Metering | GLEN LANGER | energy_progress |
| 03/18/2026 | Air barrier - visual inspection | GLEN LANGER | energy_progress |
| 03/18/2026 | Interior lighting power | GLEN LANGER | energy_progress |
| 03/18/2026 | Protection of exposed foundation insulation | GLEN LANGER | energy_progress |
| 03/18/2026 | Fire-Resistant Penetrations and Joints | GLEN LANGER | special |
| 03/18/2026 | Fire-Resistance Rated Construction | GLEN LANGER | progress |
| 03/18/2026 | Air barrier — testing | GLEN LANGER | energy_progress |
| 03/18/2026 | Electric vehicle service equipment requirements | GLEN LANGER | energy_progress |
| 03/18/2026 | Fenestration and door U-factor and product ratings | GLEN LANGER | energy_progress |
| 03/18/2026 | Fenestration air leakage | GLEN LANGER | energy_progress |
| 02/20/2025 | Shutoff dampers | GLEN LANGER | energy_progress |
| 02/20/2025 | Duct leakage testing, insulation and design | GLEN LANGER | energy_progress |
| 02/20/2025 | HVAC-R and service water piping design and insulation | GLEN LANGER | energy_progress |
| 02/20/2025 | Maintenance information | GLEN LANGER | energy_progress |
| 02/20/2025 | HVAC-R and service water heating system controls | GLEN LANGER | energy_progress |
| 02/20/2025 | HVAC-R and service water heating equipment | GLEN LANGER | energy_progress |
| 02/20/2025 | Ventilation and air distribution system | GLEN LANGER | energy_progress |
| 02/19/2025 | Maintenance information | GLEN LANGER | energy_progress |
| 02/19/2025 | HVAC-R and service water piping design and insulation | GLEN LANGER | energy_progress |
| 02/19/2025 | HVAC-R and service water heating equipment | GLEN LANGER | energy_progress |
| 02/19/2025 | HVAC-R and service water heating system controls | GLEN LANGER | energy_progress |
| 11/18/2024 | Sprinkler Systems | GLEN LANGER | special |